Resolved
That the River Hamble Harbour Management Committee notes the contents of this report.
River Hamble Harbour Management Committee decided this item on Thursday 24 June 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
That the River Hamble Harbour Management Committee notes the contents of this report.
2. It is recommended that the River Hamble Harbour Management Committee:
(i) notes and supports the remainder of this report.
Updates
Harbour Works Consents
3. A review has been undertaken of those Harbour Works Consents (HWC) that have been granted by the Harbour Board but not yet completed by the developer. Applicants or their agent have been contacted to inform them of the decision made by the Harbour Board at its meeting of 19 March 2021 in respect of the approved process for renewal of expiring consents or reapplication for expired consents. In response, MDL Marinas Limited confirmed that it has no plans at the moment to progress the expired consent of 2017 for extension to the hammerheads at Hamble Point Marina, but may review this in due course, acknowledging the requirement for a new application.
4. Deacons Marina, following liaison with the Harbour Master, have confirmed its temporary removal of the public access pontoon it provided adjacent to its slipway. This is due to continued misuse by members of the public which generated safety concerns. Its installation was granted HWC in January 2019.
5. RHHA staff are looking into the feasibility and any potential consent requirements of reinstating the River Hamble Country Park pontoon back to its original size i.e. replacing the removed half of the hammerhead, in order to offer more space for members of the public who regularly use it to use it for crabbing, viewing the river and paddle sports.
Marine and Coastal Access Act 2009 - Marine Plans
6. All public authorities taking authorisation or enforcement decisions that affect or might affect the UK marine area must do so in accordance with the appropriate marine policy documents under section 58 of the Marine and Coastal Access Act 2009 (MCAA). As RHHA is one such authority, the EDM was invited to attend a marine plan implementation training session delivered by the Marine Management Organisation’s local Marine Planning team. https://www.gov.uk/government/collections/marine-planning-in-england
Hook Lake Coastal Management Study
7. Coastal Partners (the combined Local Authority team of Fareham, Havant, Portsmouth and Gosport councils) is responsible for the region’s flood and coastal erosion protection projects and related habitat compensation for the area from Southsea along to the east bank of the Hamble estuary. It has commenced a coastal management study focusing on the future management of Hook Lake (part of the Hook with Warsash Nature Reserve) to better understand the site, to explore the potential for creating new intertidal habitats, to look at wider recreation opportunities to benefit people, and to develop preliminary designs for a scheme. The two-year study will run from now until March 2023 and is to inform potential options, it will not involve groundworks. Coastal Partners is working with Hampshire County Council, who own and manage Hook Lake, the Environment Agency and the River Hamble Harbour Authority (RHHA). To date, RHHA has provided tidal information, various data sets on bathymetry, and information on the estuary’s environment. https://coastalpartners.org.uk/project/hook-lake-coastal-management-study
Habitat Restoration
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Environmental UpdateReport | 135 KB | DownloadRead as text |
Follow River Hamble Harbour Management Committee at Hampshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Sep 2026 | Marine Director and Harbour Master's Report and Current IssuesThe River Hamble Harbour Management Committee supported the contents of this report to the Harbour Board. | Decided | Open |
| 18 Sep 2026 | Environmental UpdateThe River Hamble Harbour Management Committee noted and supported the remainder of this report. | Noted | Open |
| 18 Sep 2026 | Annual Review of Business PlanThe River Hamble Harbour Management Committee recommended that the River Hamble Harbour Board supports the contents o... | Decided | Open |
| 18 Sep 2026 | Forward Plan for Future MeetingsThe River Hamble Harbour Management Committee noted the report. | Noted | Open |
| 12 Jun 2026 | Marine Director and Harbour Master's Report and Current IssuesRESOLVED The River Hamble Harbour Management Committee supported the contents of this report to the Harbour Board. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.