Buildings, Land and Procurement Panel approved this item on Tuesday 20 July 2021. Below is the council's own wording, with the papers it was decided on.
RESOLVED The Panel recommended that the Executive Member for Commercial Strategy, Estates and Property: a) Approve the allocation of an additional £349,500 of Schools Condition Allocation grant to the scheme to upgrade the atrium roof at Crestwood School, with a revised total scheme value of £2,390,580. b) Approve the allocation of an additional £400,000 of Schools Condition Allocation grant to the scheme to upgrade the roof at Stoke Park Infants School, with a revised total scheme value of £1,300,000. c) Recommend the addition of the scheme for the upgrade of the roof at Rowlands Castle St John’s CEC Primary School to the 2021/22 capital programme at a value of £407,000 funded from the 2021/22 Schools Condition Allocation grant. d) Approve the project appraisals for the roof upgrades to Crestwood School atrium, Stoke Park Infant school and St John’s CEC Primary School set out in the report.
Word for word from the decision Hampshire published for this meeting.Source: democracy.hants.gov.uk
That the Buildings, Land and Procurement Panel recommends that the Executive Member for Commercial Strategy, Estates and Property:
2. Approves the allocation of an additional £349,500 of Schools Condition Allocation grant to the scheme to upgrade the atrium roof at Crestwood School, with a revised total scheme value of £2,390,580.
3. Approves the allocation of an additional £400,000 of Schools Condition Allocation grant to the scheme to upgrade the roof at Stoke Park Infants School, with a revised total scheme value of £1,300,000.
4. Recommends the addition of the scheme for the upgrade of the roof at Rowlands Castle St John’s CEC Primary School to the 2021/22 capital programme at a value of £407,000 funded from the 2021/22 Schools Condition Allocation grant.
5. Approves the project appraisals for the roof upgrades to Crestwood School atrium, Stoke Park Infant school and St John’s CEC Primary School set out in this report.
Executive Summary 6. This report seeks approval to increase funding for two previously allocated capital projects and add a further named scheme to the 2021/22 capital programme. All schemes are funded from the Schools Condition Allocation grant as part of the wider programme of repairs and maintenance for the schools’ estate and address three of the highest priority liabilities for condition and health and safety on the school estate.
7. The additional funding is required for schemes at Crestwood School and Stoke Park Infant School due to changes in the scope of works identified during detailed development of the proposals and increased market costs arising from high demand in the commercial and domestic markets, supply challenges on key materials due to the impacts of the Covid pandemic and other factors. It is not unusual for the scope of works to change during the development of the project as early estimates are provisional when allocated. Property Services manages the overall programme of work on a rolling basis to ensure that the highest priorities are addressed and contained within the annual budget allocation. The County Council was the recipient of additional grant for schools condition in the summer of 202 as well as a larger grant than in previous years in 2021. This gives the additional flexibility in the budget to accommodate the change and scope and the increase in costs.
8. There is now strong evidence of availability and supply chain pressures in the industry leading to delays and additional costs. The Director of Culture, Communities and Business Services will continue to monitor the situation carefully and make adjustment to future budgets and timescales based on the latest position. This is a national issue which will affect delivery of all construction activity over the foreseeable time period.
9. An additional named scheme, to upgrade the flat roof at Rowlands Castle St John’s Primary school, is to be added to the 2021/22 capital programme.
10. Project appraisals are set out in the report together with the climate change impact assessment for each scheme.
Contextual Information
11. The Managing Hampshire’s Built Estate report was presented at the Executive Member for Commercial Strategy, Human Resources and Performance Decision Day on 17 March 2021. The Executive Member approved the high-level budget allocations for the 2021/22 repairs and maintenance programme for the schools estate, including carry forward of unspent funding from 2020/21.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Managing Hampshire’s Built EstateThat the Buildings, Land and Procurement Panel recommends that the Executive Member for Commercial Strategy, Estates ...
Managing Hampshire’s Built EstateThat the Buildings, Land and Procurement Panel recommends that the Executive Member for Commercial Strategy, Estates ...
Exclusion of the press and publicThe press and public were excluded from the meeting during the following item of business, as it was likely, in view ...
Managing Hampshire’s Built EstateThat the Buildings, Land and Procurement Panel recommends that the Executive Member for Commercial Strategy, Estates ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.