Marine Director and Harbour Master's Report and Current Issues
AgreedCommittee2 papers
River Hamble Harbour Management Committee agreed this item on Friday 30 September 2022. Below is the council's own wording, with the papers it was decided on.
That the Management Committee: a. notes that the Marine Director is seeking to amend the existing officer delegated spend limits from £25,000 to £40,000 but that this adjustment is subject to the agreement of the Director of CCBS. b. notes that, subject to existing officer delegated spend limits being adjusted as per recommendation a above, the Marine Director intends to approve a spend of £40,000 towards expediting the remedial works to the Bridge at Warsash. c. supports the contents of the remainder of this report to the Harbour Board.
Word for word from the decision Hampshire published for this meeting.Source: democracy.hants.gov.uk
Report to River Hamble Harbour Management Committee
Recommendation
2. It is recommended that the River Hamble Harbour Management Committee: a. notes that the Marine Director is seeking to amend the existing officer delegated spend limits from £25,000 to £40,000 but that this adjustment is subject to the agreement of the Director of CCBS. b. notes that, subject to existing officer delegated spend limits being adjusted as per recommendation a above, the Marine Director intends to approve a spend of £40,000 towards expediting the remedial works to the Bridge at Warsash. c. supports the contents of the remainder of this report to the Harbour Board.
Executive summary
3. This report summarises the incidents and events which have taken place in the Harbour and addresses any issues currently under consideration by the Harbour Master. Contextual Information
Patrols
4. The Harbour has been patrolled by the Duty Harbour Master at various times between 0700 and 2230 daily. Mooring and pontoon checks have been conducted daily throughout the period.
Issues
5. Marine Safety Management System Audit – The new RHHA Designated Person will have conducted an Audit by the time this paper is taken. To be updated verbally or in writing if time permits.
6. Warsash HM Jetty – Engineering Works – The Harbour Authority commissioned a routine engineering inspection of the Warsash Bridge in June to take advantage of access afforded by Southern Water’s scaffolding. The survey showed the Jetty to be in sound overall condition. It also highlighted the need for some remedial works to replace a single longitudinal weather-facing wooden beam and corroded metal sleeving at the top of the ten supporting piles. The Tender process to meet Hampshire County Council’s Contract Standing Orders has been commenced with the aim of commissioning these works early over the coming winter. The quotation process is ongoing at the time of writing this report. In the event that three quotations have not been received by the time of the Management Committee meeting, it will be important to ensure that a contingency is put in place to commission works in a timely manner. There is a reasonable possibility that these works may exceed the Harbour Master’s limit of delegated authority to spend £25k to expedite completion of these works without returning to the Board. Regarding these works, it is recommended that the Management Committee recommends to the Board approval of a spend of up to £40k to negate the requirement to bring the matter before the Board in January. Secondly, in the light of increases in manufacturing and material costs, it is recommended that the Management Committee also agrees to recommend to the Board steps to achieve an increase in Harbour Master’s delegated authority from £25k to £40k. This increased level of delegation will more accurately balance the need for a degree of control over larger expenditure and cater for the occasional requirement to undertake essential works expeditiously and obviate any need to convene an extraordinary meeting of the Board. Appendix 1 To Marine Director Report
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow River Hamble Harbour Management Committee at Hampshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.