Hampshire Highways Service Contract - Contract Extension
DecidedCommittee3 papers
Transport and Environment Select Committee decided this item on Monday 3 October 2022. Below is the council's own wording, with the papers it was decided on.
Decision Day of the Executive Lead Member for Transport and Environment Strategy on 3 October 2022. The Select Committee was given a summary of the history of the contract along with the proposals going to the Executive Member. The following questions were answered: · The Parish Lengthsman scheme was subject to separate decision at a future decision day; · Officers were confident that the best price and value for money could be achieved through the arrangement; · Work was being completed faster, which in turn increased capacity Councillor Nick Adams-King, the Executive Member for Highways Operations highlighted the importance of Members being aware of issues in their local areas and reporting these, and was open for discussions with Members if required. RESOLVED The Select Committee supported the recommendations being proposed to the Executive Lead Member for Transport and Environment Strategy in paragraphs 2.-5 of the attached report.
Word for word from the decision Hampshire published for this meeting.Source: democracy.hants.gov.uk
Report to Transport and Environment Select Committee
Hampshire Highways Service Contract – Contract Extension
ETE Select Committee 3 October 2022
Tim Lawton – Assistant Director, Highways, Engineering & Implementation Hampshire Highways Service Contract - Overview • Contract started 1 August 2017, initial term of 7-years to 2024, extendable to 2029.
• Main contractor is Milestone Infrastructure Limited (part of M Group Services). Milestone are also a HCC (Gen4) supplier for major highway projects.
• Contract includes all highway maintenance operations (Planned, Reactive, Routine, Winter, Environmental).
• Includes provision to deliver larger capital improvement and maintenance projects (Redbridge Causeway, Town Mills, A326 South).
• Spend through the contract is circa £62m pa.
• From the outset the contract has been focussed on integration and collaboration - “one team, one service” ethos. Why consider an extension now? And why for the full 5 years?
1. Always intended to consider extensions beyond 2024 around this time (2022) to allow sufficient lead-time to consider other options should re-procurement be necessary for 2024.
2. The contract is in a stable position with a strong collaborative relationship in place.
3. Milestone are keen to continue working in Hampshire and have proposed an attractive ‘added value’ offer to HCC for the extension period.
4. A five year extension will enable maximum value to be secured from Milestone’s proposals and the highways contract, and allow HCC time to consider a revised contract model for 2029 onwards. Other options Considered Full re-procurement from 2024 • Prices likely to be very high – possibly 20% higher.
• Contracting sector is now very selective with bidding decisions. Also possible that there could be limited interest in tendering while the sector remains so unstable.
• There is significant congestion (market saturation) in the TMC market place over the next 3-4 years.
Shorter duration extension • Would not realise maximum value to HCC from the contract offer and would be less attractive to Milestone.
• Will still result in HCC entering the market while the sector is unstable. Market Conditions • Inflation is currently high, unpredictable and difficult to forecast ahead – this increases contract risk & uncertainty. Higher prices are already evident for materials and labour. Other overhead costs increasing, e.g. energy.
• The term maintenance sector has become a bidders’ market - compounded by known saturation/congestion in the UK sector for next 3-4 years
• Extending the contract to 2029 should mean the procurement of the next highways contract is undertaken during a period of greater certainty and stability. Work on this is likely to begin in 2025/6, subject to confirmation of the extension period, when a variety of delivery models can be considered.
• Other LA’s with similar arrangements have recognised the current sector issues and risks and have extended, or are in the process of extending, their TMC contracts. Safer, Greener Hampshire Highways – Beyond 2024 Milestone’s documented proposal for the extended period of the contract (2024-2029) provides credible and deliverable opportunities to improve and innovate Hampshire’s highways service. Their offer can be summarised as:-
• Continued service improvements and efficiencies across all contract activities. • Sustained carbon reduction (including further investment in materials recycling). • Improved resilience to climate adaption. • Local community support, e.g. parish lengthsman scheme. • Cashable savings over the 5 year extension period. • Additional social value. • Further innovation and smart solutions, including more use of data intelligence. HHSC Performance Management - Overview • Contract compliance and service delivery performance is routinely managed through data analysis and the jointly- managed contract governance structure, e.g. activity service leads, local depot management teams, HHSC Operations & Strategic Boards.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport and Environment Select Committee at Hampshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.