CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Hampshire County Council
Regulatory Committee, Wednesday 18 September 2024 at 10.00am

Roke Manor Quarry, Shootash,

Agreed Licensing 6 papers

Regulatory Committee agreed this item on Wednesday 18 September 2024. Below is the council's own wording, with the papers it was decided on.

Item185

Resolved

RESOLVED 1. Planning permission was GRANTED for planning application 24/00736/CMAS to extend the time within which the total site restoration of Roke Manor Quarry is to be completed, to 15 years from the date of commencement of the bell mouth access onto the A27 , subject to: a. The update report b. The conditions listed in Appendix A1 c. The deed of variation to the existing Section 106 legal agreement (to extend the long-term management of the adjacent woodland and the restored land under the haul road causeway), which will then link the end date of the long term woodland management plan to when the aftercare period is signed off by the development, and; d. A deed of variation to the existing Section 106 legal agreement will update the planning application reference so that it can continue to bind the varied permission sought. 2. Planning permission was GRANTED for planning application 24/00739/CMAS to extend the time within which the total site restoration of Roke Manor Quarry is to be completed, to 15 years from the date of commencement of the bell mouth access onto the A27 subject to: a. The update report b. The conditions listed in Appendix A2 c. The deed of variation to the existing Section 106 legal agreement (to extend the long-term management of the adjacent woodland and the restored land under the haul road causeway), which will then link the end date of the long term woodland management plan to when the aftercare period is signed off by the development, and; d. A deed of variation to the existing Section 106 legal agreement will update the planning application reference ... view the full minutes text for item 185.
Word for word from the decision Hampshire published for this meeting. Source: democracy.hants.gov.uk

Follow this further

Built from Hampshire's papers

What the report saysPro

Report to Regulatory Committee

Recommendation

1. That planning permission be GRANTED for planning application 24/00736/CMAS to extend the time within which the total site restoration of Roke Manor Quarry is to be completed, to 15 years from the date of commencement of the bell mouth access onto the A27, subject to the conditions listed in Appendix A1, the deed of variation to the existing Section 106 legal agreement (to extend the long-term management of the adjacent woodland and the restored land under the haul road causeway), which will then link the end date of the long term woodland management plan to when the aftercare period is signed off by the development, and a deed of variation to the existing Section 106 legal agreement will update the planning application reference so that it can continue to bind the varied permission sought.

2. That planning permission be GRANTED for planning application 24/00739/CMAS to extend the time within which the total site restoration of Roke Manor Quarry is to be completed, to 15 years from the date of

1 commencement of the bell mouth access onto the A27 subject to the conditions listed in Appendix A2, the deed of variation to the existing Section 106 legal agreement (to extend the long-term management of the adjacent woodland and the restored land under the haul road causeway), which will then link the end date of the long term woodland management plan to when the aftercare period is signed off by the development, and a deed of variation to the existing Section 106 legal agreement will update the planning application reference so that it can continue to bind the varied permission sought.

Executive summary

3. This report relates to two separate planning applications for the variation of two conditions on previously approved permissions at Roke Manor Quarry, Salisbury Road, Shootash, Hampshire SO51 6GA. They are as follows:

• Planning application 24/00736/CMAS – Seeks Variation of Condition 2 (time limits) of Planning Permission 10/02615/CMAS - to extend the time within which restoration of Roke Manor Quarry is required to be completed. This is an Environmental Impact Assessment (EIA) application under the Town & Country Planning (Environmental Impact Assessment) Regulations 2017. (An Environmental Statement was submitted as part of the planning application); and

• Planning application 24/00739/CMAS – Seeks Variation of Condition 2 (time limits) of planning permission 15/00826/CMAS– to extend the time within which restoration of Roke Manor Quarry is required to be completed.

4. A committee site visit by Members took place on 2nd September 2024 in advance of the proposal being considered by the Regulatory Committee.

5. Key issues raised are: • The need and associated impacts of the extension of time and cumulative impacts on Roke Manor Quarry; • Flooding and drainage; • Highways impact; and • Restoration of the site.

6. Planning application 24/00736/CMAS is directly linked to planning application 24/00739/CMAS and are essentially dependant on each other. They are being considered by the Regulatory Committee as application 24/00736/CMAS is a

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix BAppendix B 1.8 MB Download
PDF
Appendix CAppendix C 763 KB Download
PDF
Appendix DAppendix D 630 KB Download
PDF
Appendix EAppendix E 4.3 MB Download
PDF
Appendix FAppendix F 799 KB Download
PDF
Roke Manor Quarry, Shootash,Report 447 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 17 attended
SS
Sheena SayerOfficer, expected
PL
Councillor Peter LathamChairman, present
LQ
Councillor Lance QuantrillVice-Chairman, present
SB
Councillor Steven BroomfieldCommittee Member, present
MC
Councillor Mark CooperLiberal Democrats Spokesperson, present
RC
Councillor Rod CooperCommittee Member, present
MF
Councillor Michael FordCommittee Member, present
TG
Councillor Tim GrovesCommittee Member, present
PH
Councillor Pal HayreCommittee Member, present
JH
Councillor Juliet HendersonCommittee Member, apologies
KH
Councillor Keith HouseCommittee Member, apologies
AJ
Councillor Adam JackmanCommittee Member, apologies

All 17 on the meeting page

More from Hampshire Regulatory Committee

All decisions
MeetingDecisionOutcome
15 Jul 2026 Update to the Validation GuidanceRESOLVED That the Committee note the contents of the draft Planning Application Validation Guidance and approve the d... Noted Open
10 Jun 2026 Monitoring and Enforcement UpdateRESOLVED The Regulatory Committee noted the content of the report. Noted Open
10 Jun 2026 Impending legislation changes for Regulatory Committee including changes to the committee sizeRESOLVED The Regulatory Committee noted the anticipated legislation to come into force on 31 October 2026. The Regula... Noted Open
18 Mar 2026 Silverlake Automotive Recycling Ltd, Botley Road, Shedfield, SouthamptonThat planning permission be REFUSED for the reasons set out in the report of the Director of Universal Services. Refused Open
18 Mar 2026 Monitoring and Enforcement UpdateMembers noted the contents of the report. Noted Open