RESOLVED a) T he forecast outturn position for financial year 2024/25 was noted by the HIWFRA Full Authority. b) The updated capital programme forecasts (appendices A1 and A2) was approved by the HIWFRA Full Authority. c) The quarterly treasury management update report including the treasury management indicators (appendix B) was noted by the HIWFRA Full Authority. d) The quarterly prudential indicators (paragraph 27) were noted by the HIWFRA Full Authority. e) The Efficiency and Productivity appendix C was noted by the HIWFRA Full Authority.
Word for word from the decision Hampshire published for this meeting.Source: democracy.hants.gov.uk
1. This report sets out the quarter two forecast position for the Authority and provides financial updates following the Budget Report in February 2024.
2. An underspend of £619,000 is currently forecast against the revenue budget.
3. In addition the report provides an update on the forecast budget gap for next financial year following publication of the Local Government finance policy statement in November 2024.
Recommendation
4. That the forecast outturn position for financial year 2024/25 be noted by the HIWFRA Full Authority
5. That the updated capital programme forecasts (appendices A1 and A2) be approved by the HIWFRA Full Authority
6. That the quarterly treasury management update report including the treasury management indicators (appendix B) be noted by the HIWFRA Full Authority. 7. That the quarterly prudential indicators (paragraph 27) be noted by the HIWFRA Full Authority
8. That the Efficiency and Productivity appendix C be noted by the HIWFRA Full Authority.
Background
9. The Authority approved the 2024/25 revenue budget and precept in February 2024, alongside an updated Medium Term Financial Plan (MTFP). The Authority also approved updates to the capital programme, the Reserves Strategy, the Treasury Management Strategy and the Capital and Investment Strategy and received the Efficiency Plan for 2024/25.
2024/25 BUDGET MONITORING
10. This section covers the overall monitoring position. The forecast position for the Authority in 2024/25 is an underspend of £619,000. A breakdown of the position is set out below:
Over / 2024/25 2024/25 (under) Table 1 Budget Outturn spend £'000 £'000 £'000 Wholetime Firefighters 44,403 44,320 (83) On-call Firefighters 9,503 8,763 (740) Staff 19,646 18,955 (691) Other Employee Costs 2,392 2,803 411 Premises Related Expenditure 8,163 8,146 (17) Transport Related Expenditure 2,023 2,140 117 Supplies and Services 9,807 10,193 386 Third Party Payments 2,524 2,677 153 Income (4,066) (4,243) (177) Net Service Expenditure 94,395 93,754 (641) Contingency 500 500 0 Capital Financing 1,529 1,529 0 Planned contributions to reserves 10,305 10,305 0 Planned draws from reserves (4,767) (4,767) 0 Net Expenditure 101,962 101,321 (641) Funding (101,962) (101,940) 22 Net Position (0) (619) (619) 11. The overall forecast is an underspend of £0.619m. This is made up of an underspend on on-call firefighters and non-operational staff, partially offset by small overspends elsewhere.
(a) Wholetime firefighters - £0.083m underspend
(b) On-Call (Retained) firefighters – £0.740m underspend. Largely due to lower activity levels and ongoing recruitment and retention challenges. The forecast includes the estimated effect of the changes to on-call pay that take place from January 2025. However, the actual impact of the pay award may vary from the forecast effect.
(c) Non-operational staff – £0.691m underspend. Largely due to staff vacancies. The 24/25 Green book pay award was agreed in November and paid in December.
(d) Other employee costs – £0.411m overspend. Some of the overspend relates to higher costs for external suppliers covering work for vacant staff posts. Additionally, there are some higher than budgeted costs for ill health and injury pensions. These costs can be quite variable from year to year.
(e) Premises costs - £0.017m underspend due to a Business Rates revaluation.
(f) Transport costs - £0.117m overspend. This pressure relates to the costs of travel between the mainland and the Isle of Wight and higher costs for maintaining and repairing vehicles.
(g) Supplies and services - £0.386m overspend. This overspend primarily relates to one-off costs for an IT development, where it has been necessary to use external contractors to cover staff vacancies, meaning this is offset by an underspend on pay costs.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.