RESOLVED That planning permission be REFUSED for the reasons outlined below: The proposal would result in unacceptable adverse landscape and visual amenity impacts and is not considered to be accordance with Policies 5 (Protection of the Countryside), 10 (Protecting public health, safety and amenity) and 13 (High quality design of minerals and waste developments) of the Hampshire Minerals and Waste Plan (2013) as well as Policies E1 (High quality development in the borough) and E3 (Protect, conserve and enhance landscape character) of the Test Valley Borough Council Local Plan (2016). On the basis of the above reason, the proposal is considered to be contrary to Policy 1 (Sustainable minerals and waste development) of the Hampshire Minerals and Waste Plan (2013). Therefore, the proposal does not constitute a sustainable waste development.
Word for word from the decision Hampshire published for this meeting.Source: democracy.hants.gov.uk
Update Report from Assistant Director of Waste & Environmental Services
Item No: 6
Vary condition 12 attached to planning application 22/01323/CMAS to increase the stockpile heights from 4m to 7m to enable flexibility of waste operations at the site at Salvidge Farm, Bunny Lane, Timsbury Hampshire SO51 0PG (Application No. 23/02231/CMAS Site Ref. TV066)
1) Amendments to the report and clarification:
Paragraphs 12 and 165 - Purpose of screening bund along east of northern part of site (changes in italic)
Clarification that the bund and planting introduced in the north east of the site under planning application 22/01323/CMAS was to improve the screening to the site and aid the reduction of noise emissions derived from the site’s operations. The paragraphs are amended as follows:
In relation to planning permission 22/01323/CMAS for the permanent retention of a wash plant, additional bunding and vegetative screening was required on the western edge of the southern third of the site and a new bund and planting along the eastern edge of the northern third of the site to screen the visual impact of the plant improve the screening to the site and aid the reduction of noise emissions derived from the site’s operations. This increased the height of this bund from 2m (approved under the Appeal decision) to 4m with additional planting added to this bund.
Paragraph then continues as in the report.
Paragraph 156 - Water discharge complaint
Since the complaint was received this has been subsequently investigated and the operator has ceased discharging. The paragraph is amended as follows:
A complaint regarding discharge of water from the site onto adjacent land to the south is currently being has been investigated by Officers. The operator has ceased discharging water from the site following instruction by Officers. and The Environment Agency has been alerted and are investigating as a potential breach of the site Environmental Permit. 2) Consultations:
Since the publication of the report, Braishfield Parish Council have restated their earlier objection to the planning application.
3) Representations:
Since the publication of the report, one additional representation has been received from the public. This restated their earlier representation.
END
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Update to the Validation GuidanceRESOLVED That the Committee note the contents of the draft Planning Application Validation Guidance and approve the d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.