Resolved
That the Committee approved the revised Contract Standing Orders set out in Annex 2 of the report for recommendation to Cabinet for consideration and recommendation to the County Council for approval.
Audit Committee approved this item on Friday 24 January 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Committee approved the revised Contract Standing Orders set out in Annex 2 of the report for recommendation to Cabinet for consideration and recommendation to the County Council for approval.
1. Following the Procurement Act 2023 (PA 2023) receiving Royal Assent, a review of the County Council’s Contract Standing Orders has been undertaken in order to identify any changes required as a consequence of the new legislation. The review also identified a small number of additional desirable changes to the Contract Standing Orders.
2. This report seeks the Audit Committee’s approval of the proposed amendments to the Contract Standing Orders for recommendation to Cabinet for consideration and recommendation to the County Council for approval.
Contextual information
1 Further reports will be required to Cabinet and the County Council to change the Constitution. 3. The PA 2023, which received Royal Assent on 26 October 2023, will come into full force and effect on 24 February 2025. Together with secondary legislation supporting it, the PA 2023 establishes a new public procurement regime in England, Wales and Northern Ireland.
4. Although many of the concepts and rules from the previous procurement regime remain, these have been extensively rewritten to move away from the language of the EU directives on procurement and the Public Contract Regulations 2015 (PCR 2015). The PA 2023 adopts a new approach in respect of the objectives, its principles, contract management and transparency publication requirement.
5. The PA 2023 will only apply to new procurements commenced on or after 24 February 2025. The PCR 2015 will continue to apply to any procurement commenced or contract awarded before 24 February 2025.
6. A review of the County Council’s Contract Standing Orders, contained in Part 3, Chapter 6 of the County Council’s Constitution, has identified a number of amendments required to ensure that the County Council’s procedures comply with the new legislative requirements. Pursuant to Part 1, Chapter 7 of the County Council’s Constitution, the Audit Committee’s Terms of Reference include:
“to make recommendations to the County Council for the making or amending of financial regulations, standing orders related to contracts or regulations related to the conduct of the County Council’s business.”
7. This report proposes that a number of amendments be made to the Contract Standing Orders largely to reflect the requirements of the PA 2023 applying to new procurements from 24 February 2025. A copy of the County Council’s existing Contract Standing Orders is attached at Annex 1. A copy of the proposed revised Contract Standing Orders is attached at Annex 2. The proposed amendments are also detailed in the table below.
8. The following table sets out the Contract Standing Orders affected by the proposed changes, together with a brief description of the proposed change:
Contract Standing Order Description of Proposed Change Amended
Contract Standing Order 1 Introducing new definitions and amending existing definition to reflect the new PA 2023 and maintain the continuity of the PCR 2015 to existing procurements
Contract Standing Order 2.2 To make it clear that procurements under PCR 2015 or the Provider Selection Regime (PSR) started before 24 February 2025 (including resulting contracts and modifications to those contracts) will continue to be regulated by the existing procurement regime under the PCR 2015 and the PSR
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Review of Contract Standing OrdersReport | 244 KB | DownloadRead as text |
Follow Audit Committee at Hampshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 26 Jun 2026 | Information Compliance - Use of Regulated Investigatory PowersThat the Audit Committee received and noted the data/narrative regarding the County Council’s use of surveillance pow... | Noted | Open |
| 26 Jun 2026 | Annual Governance StatementRESOLVED The Audit Committee approved the for 2025/26. | Approved | Open |
| 26 Jun 2026 | Annual Internal Audit Conclusion 2025-26RESOLVED That the Audit Committee noted the Annual Internal Audit Conclusion for 2025/26 which confirmed that the fra... | Noted | Open |
| 26 Jun 2026 | External Audit: Audit Planning Report - Hampshire County CouncilRESOLVED The Audit Committee received and noted the external auditor’s Audit Planning Report for Hampshire County Cou... | Noted | Open |
| 26 Jun 2026 | External Audit: Audit Planning Report - Pension FundRESOLVED The Audit Committee received and noted the external auditor’s Audit Planning Report for the Hampshire Pensio... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.