Wight Fire and Rescue Authority approved this item on Wednesday 5 February 2025. Below is the council's own wording, with the papers it was decided on.
RESOLVED a) The Hampshire and Isle of Wight Fire Authority approved the HIWFRS Safety Plan for 2025–2030. b) The Hampshire and Isle of Wight Fire Authority approved the proposed implementation and reporting framework for the Safety Plan 2025–2030.
Word for word from the decision Hampshire published for this meeting.Source: democracy.hants.gov.uk
1. This paper seeks Fire Authority approval of the Hampshire and Isle of Wight Fire and Rescue Service (HIWFRS) Safety Plan which will cover the period 01 April 2025 to 31 March 2030. This Safety Plan 2025-30 can be found at appendix A.
2. The Safety Plan 2025-30 outlines the strategy and commitments of the Hampshire and Isle of Wight Fire and Rescue Authority (HIWFRA) for the plan period. It must be finalised and published by 01 April 2025, coinciding with the expiration of the current plan.
3. In 2023, HIWFRA approved a two-stage process for developing the Safety Plan 2025-30. Stage 1 focused on identifying and assessing foreseeable fire and rescue risks, while Stage 2 involved developing the plan and consulting on potential mitigations. The outcome of Stage 1 was approved on 10 October 2023, followed by the approval of the draft plan and public consultation on 8 October 2024.
4. The 10-week public consultation concluded on 18 December 2024. Responses from the public survey, external focus groups, and internal engagement were analysed, and the draft Safety Plan was updated to reflect the findings.
5. The fire and rescue national framework for England policy paper mandates that all fire and rescue services publicly share their risk assessments. Accordingly, the stage 1 outcome document and the Safety Plan 2025-30 will be published on the Service’s public website.
6. Throughout the plan’s duration, regular analysis will be conducted to refine our understanding of our communities and emerging risks, ensuring that the risk profile and proposed changes remain well-informed, and evidence based.
Page 1 of 7 7. The annual planning objectives will align all team efforts with the five strategic objectives, ensuring a clearly defined golden thread throughout the directorate Delivery Plans. The service planning cycle will prioritise cross-directorate collaboration, ongoing engagement, and individual accountability.
8. The delivery, management, and assurance of the plan will adhere to HIWFRA policies, the Service Corporate Governance Framework, and established change and risk management policy and procedures. Quarterly progress updates will be provided to the Executive Group, with six-monthly updates to the Fire Authority via Performance Reports.
Recommendation
9. That the Hampshire and Isle of Wight Fire Authority approves the HIWFRS Safety Plan for 2025–2030.
10. That the Hampshire and Isle of Wight Fire Authority approves the proposed implementation and reporting framework for the Safety Plan 2025–2030.
Background
11. All UK Fire and Rescue Services are required to produce a Community Risk Management Plan (CRMP). Locally referred to as the "Safety Plan," this document will cover the period 2025–2030. HIWFRS's two-stage approach complies fully with the CRMP National Fire Standard.
STAGE 1: ASSESSMENT OF RISK
12. The Stage 1 outcome, approved by the Fire Authority in October 2023, outlines the external risk profile. This community risk profile incorporates National Operational Guidance (NOG) hazard groups for fire related risks and other risks relevant to Local Resilience Forum partners. The document assesses the likelihood and impact of each risk, highlighting any specific geographical areas of prevalence. It also includes supplementary data analysis beyond NOG hazard groups to provide a comprehensive risk overview.
STAGE 2: PRODUCTION OF THE SAFETY PLAN
13. Stage 2 focused on developing and consulting on the draft Safety Plan 2025- 30, incorporating proposed mitigations for risks identified in Stage 1 as well as internal risks.
14. A public consultation on the draft Safety Plan and proposed measures was conducted over a 10-week period, concluding on 18 December 2024. The consultation included the following elements:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.