Resolved
That planning permission be REFUSED due to the following reasons: No additional waste capacity will be generated and no need for the development has been demonstrated to the extent it outweighs the disbenefits of the development (Policy 27 (Capacity for waste management development) of the Hampshire Minerals and Waste Plan (2013)). The development would have an unacceptable adverse amenity impact to residents along the highway route to the site due to noise and dust generation contrary to Policies 10 (Protecting public health, safety and amenity), 12 (Managing traffic) and Policy 25 (Sustainable waste management) of the Hampshire Minerals & Waste Plan (2013)), and Policy LHW4 (Amenity) of the Test Valley Local Plan (2016). The development is, therefore, not considered to be a sustainable development and on balance is not in accordance with Policy 1 (Sustainable minerals and waste development) of the Hampshire Minerals & Waste Plan (2013).