HIWFRA Audit and Governance Committee, Friday 5 December 2025 at 2.30pm

Internal Audit Management Actions Progress Report

Noted Finance 1 paper

AI summaryHIWFRA Audit and Governance Committee notes progress on internal audit management actions, with seven medium and high priority actions still overdue and revised target dates.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted progress on management actions and audit plan delivery
MoneyNo specific sum mentioned; managed within current resources
What happens nextContinued monitoringPlanning, Change and Assurance team continues tracking actions
Who it affectsHIWFRS governance and controlsImplementation of internal audit recommendations

What was decided

The Committee noted the progress made towards implementing internal audit management actions and delivering the audit plan. Report P2

Why

The Committee has a key scrutiny role in monitoring implementation of internal audit management actions, and only medium and high overdue actions are reported to it. Report P1, P11

What happens next

Heads of Service remain responsible for delivering management actions in their areas, with outstanding actions referred to the relevant Director. Report P4, P9

The Planning, Change and Assurance team will continue to monitor progress and request evidence that actions have been completed. Report P9, P37

Implications

  • Risk: Failure to implement audit recommendations leaves the Authority vulnerable to identified risks and weaknesses in controls. Report P35
  • Other: The management of internal audit actions is carried out within current resources. Report P30
  • Legal: There are no legal implications arising from the report, though provision of Internal Audit is required by the Accounts and Audit Regulations 2015 and the Public Sector Internal Audit Standards. Report P33
  • Other: Impact assessments have not been required for this report. Report P32

Who and where

  • Hampshire and Isle of Wight Fire and Rescue Service (HIWFRS) Report P4, P24
  • Heads of Service responsible for delivering management actions Report P4
  • The Planning, Change and Assurance team Report P4, P37

Timeline

  • 3December 2025: Revised target for PRI documents review and updated procedures (originally 31 May 2025, high priority) Report P15
  • 3December 2025: Revised target for enhanced Protection inspector training (originally 31 May 2025, high priority) Report P15
  • 3December 2025: Revised target for Risk Based Inspection Programme (RBIP) COU strategy and CFRMIS data alignment (originally 1 July 2025, medium priority) Report P17
  • December 2025: Revised target for updating procedures with legislative importance and reviewing the PPG update process within Protection (originally 1 July and 1 August 2025, medium and high priority) Report P17
  • 3December 2025: Revised target for developing CFRMIS recording systems to enable list migration, dependent on COU Project Report P17

Plain English for the jargon

  • HIWFRS: Hampshire and Isle of Wight Fire and Rescue Service
  • SIAP: Southern Internal Audit Partnership, which provides internal audit services
  • HMICFRS: His Majesty's Inspectorate of Constabulary and Fire and Rescue Services
  • CFRMIS: A recording system used for fire safety and premises data
  • RBIP: Risk Based Inspection Programme
  • COU: Change Only Update, a process for updating premises data
  • PRI: Premises Risk Information, documents reviewed for premises inspected
  • PPG: Policy, Procedure and Guidance, subject of a current review project
  • NFCC: National Fire Chiefs Council, which publishes guidance
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item73

Resolved

RESOLVED The HIWFRA Audit and Governance Committee noted progress made towards the implementation of the internal audit management actions and the delivery of the audit plan.
Word for word from the decision Hampshire published for this meeting. Source: democracy.hants.gov.uk

Follow this further

Built from Hampshire's papers

What the report saysPro

Report to HIWFRA Audit and Governance Committee

Summary

1. The purpose of this report is to provide the Audit and Governance Committee Members with the latest update on the medium and high internal audit management actions that have not been completed within the agreed target date and are now overdue. The Audit and Governance Committee has a key scrutiny role in monitoring the implementation of internal audit management actions

Recommendation

2. That the progress made towards the implementation of the internal audit management actions and the delivery of the audit plan be noted by the HIWFRA Audit and Governance Committee.

Background

3. Internal audit is provided by the Southern Internal Audit Partnership (SIAP) and is one of various assurance mechanisms that the Service utilises as part of our wider assurance programme. Our assurance programme includes internal and external assurance mechanisms with external mechanisms including from His Majesty’s Inspectorate of Constabulary and Fire and Rescue Services (HMICFRS) and ISO certification testing.

4. In terms of internal audit, the Hampshire and Isle of Wight Fire and Rescue Service (HIWFRS) Planning, Change and Assurance Team maintains mechanisms to monitor management actions that are as a result of finalised internal audits. The team records whether management actions are in progress and on target, have been delayed and extended or have been completed. Heads of Service are responsible for the delivery of management actions that fall within their areas of responsibility

5. Once a final audit report has been issued, the agreed management actions are recorded along with:

a) the priority of the recommendation;

b) the target date for implementation; and

c) the person responsible for the action.

6. The Planning, Change and Assurance team will request evidence that an action has been completed, or if it has not been completed when it is expected to be. Any management actions that continue to remain outstanding are referred to the relevant Director. Outstanding audit recommendations are monitored regularly by the Director of Corporate Services and the Head of Corporate Governance and Support

MANAGEMENT ACTIONS

7. Only medium and high overdue management actions are reported to the Committee. There are currently seven overdue actions.

8. The table below lists those recommendations that are currently outstanding beyond their agreed target date and states if they are of medium (M) or high (H) priority. There is a brief commentary against each management action.

Internal Audit Management Actions

Premises Risk

PRI to work closely with 31 May 2025, H Revised target date of 31 Protection team to ensure PRI revised to 31 December 2025 due to the documents are reviewed and December ongoing work between PRI updated for all premises 2025. and Protection Teams to inspected. Protection managers develop strategy for to look at Protection procedures collaborative working to include information. Enhanced training for Protection 31 May 2025, H Revised target date of 31 inspectors to ensure PRI is revised to 31 December 2025 due to the ongoing work reviewed and updated for every December between PRI and premises inspected. 2025. Protection Teams to develop and roll out appropriate training.

Fire Safety Audits & Use of Enforcement Powers

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit Management Actions Progress ReportReport 154 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 6 attended
DH
Councillor David HarrisonChairman, present
DD
Councillor David DrewVice-Chairman, present
SP
Councillor Stephen ParkerCommittee Member, present
SG
Councillor Sally GoodfellowCommittee Member, apologies
LP
Councillor Louise Parker-JonesCommittee Member, present
RP
Councillor Roger PriceLiberal Democrats Deputy, apologies

On this subject at Hampshire

Search all
  1. Internal Audit Management Actions Progress ReportThis decision
  2. Annual Internal Audit Conclusion 2025/26Noted
  3. Internal Audit Management Actions Progress ReportNoted
  4. Governance - Annual Internal Audit Conclusion 2025-26Noted
  5. Annual Internal Audit Conclusion 2025-26Noted
  6. Governance: Internal Audit Progress ReportNoted

More from Hampshire HIWFRA Audit and Governance Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 HIWFRA's Audit and Governance Committee - Annual Report 2025/26The HIWFRA Audit and Governance Committee approved the Audit and Governance Committee Chair’s Annual Report 2025/26, ... Approved Open
9 Sep 2026 Annual Governance Statement 2025-2026 And Local Code Of GovernanceThe HIWFRA Audit and Governance Committee: · approved the Annual Governance Statement 2025/26, as set out in Appendix... Approved Open
9 Sep 2026 2025/26 Annual Assurance StatementThe HIWFRA Audit and Governance Committee approved the and its publication on the Hampshire & Isle of Wight Fire and ... Approved Open
9 Sep 2026 Annual Internal Audit Conclusion 2025/26The HIWFRA Audit and Governance Committee noted the annual conclusion. Noted Open