Universal Services Select Committee, Monday 19 January 2026 at 10.00am

Universal Services Proposed Capital Programme 2026/27, 2027/28 and 2028/29 and 2025/26 Q3 Update

Decided Committee 2 papers

AI summaryHampshire Universal Services Select Committee backs £1.2 billion capital programme proposals, including new school, transport and waste schemes, for onward approval to the Executive Lead Member and Cabinet.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedSelect Committee backed Executive Lead Member recommendations
Money£1.2 billion total capital programmeOver £536.6 million proposed across next three years
What happens nextExecutive Lead Member decision same dayThen to Cabinet in February 2026 for final approval
Who it affectsHampshire residents and service usersHighways, schools, waste and countryside services

What was decided

The Select Committee supported the recommendations being proposed to the Executive Lead Member for Universal Services regarding the Capital Programme.

Why

The proposals are needed for onward submission to Cabinet in February 2026, with the council aiming to maximise external funding sources given its current financial position and ongoing revenue budget pressures. Report P9, P12

The Medium Term Financial Strategy Update to Cabinet and County Council in November 2025 highlighted ongoing significant financial challenges, requiring careful use of local resources, reserves and borrowing. Report P12

Major project risks include the new Materials Recovery Facility at Chickenhall Lane facing a delayed permanent electricity supply (now potentially 2036), requiring temporary generators for up to eight years. Report P13

What happens next

The Executive Lead Member for Universal Services will consider the recommendations on the same day at 2.00pm, with onward submission to Cabinet in February 2026. Report P3, P9

A draft Local Transport Delivery Plan must be submitted to the Department for Transport by 20 March 2026, with a final document due 18 September 2026. Report P40, P41

A Memorandum of Understanding with the Department for Transport is required as a condition for receipt of consolidated transport grant funding. Report P39, P40

The money

  • £1.2 billion Total Universal Services capital programme value Report P10, P11
  • £536.6 million Proposed capital investment across the next three years Report P11
  • £13.650 million New scheme additions to the capital programme (Table 2) Report P10, P27
  • £5.345 million Net increases to existing capital scheme values (Table 3) Report P10, P32
  • £3.8 million Fleet Town Access Plan value being removed from programme Report P35, P36
  • £7.548 million Department for Transport Bus Service Improvement Plan funding for 2025/26 Report P13, P15
  • £3,000,000 Eastern Andover Walworth Road Corridor improvement scheme Report P18, P27
  • £3,000,000 Samuel Cody School SCOLA refurbishment Report P26, P27
  • £2.2 million Crookhorn College SCOLA refurbishment Report P25, P27
  • £2.5 million Residual elements of Botley, Southern Gateway scheme Report P27, P42
  • £1,208,226 Total financing for revised capital programme (in thousands) Report P52
  • £1.140 million Basingstoke Canal funding removed from capital programme Report P86
  • £800,000 Annual public rights of way capital allocation from 2026/27 Report P86

Options considered

  • Chosen: Add nine new SCA-funded schools schemes and two transport schemes to capital programme. Address schools estate condition and deliver active travel improvements funded by external grants and developer contributions Report P10, P27, P39
  • Chosen: Increase values of six existing transport schemes. Reflect updated cost estimates following feasibility, design and stakeholder engagement work Report P10, P32
  • Chosen: Remove Fleet Town Access Plan from capital programme. Avoid duplication of funding; individual schemes are now being entered separately, with Hitches Lane and Elvetham Roundabout scheme remaining at £3.8 million Report P10, P36
  • Chosen: Delegate authority to Director of Universal Services to prepare and submit Local Transport Delivery Plan. Required to meet Department for Transport deadline of 20 March 2026 Report P10, P40, P41

Implications

  • Financial: Maximising use of external funding sources, with local resources (reserves, borrowing, capital receipts) carefully considered due to revenue budget pressures. Report P12, P44
  • Risk: Chickenhall Lane Materials Recovery Facility faces electricity supply delay from 2028 to potentially 2036, requiring temporary generators for up to eight years and increased costs. Report P13
  • Risk: Difficulties in securing third-party consents and road space for transport infrastructure works continue to affect programme delivery and may increase costs and timelines. Report P13
  • Equalities: Report has neutral impact on groups with protected characteristics as it is a financial report; individual schemes will undertake their own equalities assessments. Report P91, P98, P99
  • Climate: Schools schemes include thermal insulation, rooflight and double-glazed window upgrades to reduce energy costs and carbon emissions; climate change impact assessment tools deemed not applicable at programme level. Report P27, P92
  • Other: Devolution and creation of Hampshire and Solent Mayoral Combined County Authority may affect governance, funding mechanisms and programme delivery, with Government intending to issue consolidated transport funding to the new authority if established by March 2026. Report P13, P37, P38

Who and where

  • Hampshire residents and road users Report P13, P44
  • Hampshire school pupils and staff (school condition schemes) Report P27, P81
  • Bus passengers across Hampshire (BSIP-funded schemes) Report P13, P15
  • Hampshire residents using public rights of way network Report P86
  • M27 motorway users (Junction 10 scheme) Report P42

Timeline

  • 19 January 2026: Universal Services Select Committee pre-scrutiny and Executive Lead Member Decision Day at 2.00pm Report P3
  • February 2026: Cabinet and County Council final approval of revised 2025/26 and 2026/27 capital programmes Report P9, P11
  • 20 March 2026: Draft Local Transport Delivery Plan to be submitted to Department for Transport Report P10, P40
  • Spring 2026: Haven Nursery School refurbishment works due to start Report P27
  • Summer 2026: SCOLA roof and window upgrade works to start on site at five schools Report P27
  • May 2026: Eastern Andover Walworth Road Corridor detailed design expected to commence Report P27
  • Early 2027: Eastern Andover Walworth Road Corridor construction expected to start Report P27
  • Summer 2027: Crookhorn College and Samuel Cody School SCOLA refurbishment works to start Report P27
  • 2027/28: New Odiham Road Parallel Crossing construction expected Report P27
  • End of 2026: Andover Railway Station Placemaking construction expected to commence (subject to approvals) Report P32
  • 18 September 2026: Final Local Transport Delivery Plan to be submitted to Department for Transport Report P40
  • Potentially 2036: Permanent electricity supply expected at Chickenhall Lane Materials Recovery Facility Report P13

Plain English for the jargon

  • SCA grant: School Condition Allocation, government grant used to address the condition of the schools estate on a priority basis.
  • SCOLA: Schools capital refurbishment programme; specific schools blocks receiving major refurbishment.
  • BSIP: Bus Service Improvement Plan, Department for Transport funding for bus infrastructure and services.
  • ITB: Integrated Transport Block, government funding for local transport improvements.
  • LTN 1/20: Local Transport Note 1/20, government guidance on cycling infrastructure design.
  • MCCA: Mayoral Combined County Authority, the proposed Hampshire and Solent devolution body.
  • LMSL: Legal Minimum Service Levels, the minimum level of service the council is legally required to provide.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item132

Resolved

That the Universal Services Select Committee supports the recommendations being proposed to the Executive Lead Member for Universal Services regarding the Capital Programme.
Word for word from the decision Hampshire published for this meeting. Source: democracy.hants.gov.uk

Follow this further

Built from Hampshire's papers

What the report saysPro

Report to Universal Services Select Committee

HAMPSHIRE COUNTY COUNCIL

Decision Report

Decision Maker: Executive Lead Member for Universal Services

Date: 19 January 2026

Title: Universal Services Proposed Capital Programme 2026/27, 2027/28 and 2028/29

Report From: Director of Universal Services

Contact name: Alyssa Vance Payne

Email: [email protected]

Purpose of this Report 1. The purpose of this report is to set out, subject to confirmation of funding, the proposals for the Universal Services Capital programme and to seek approval for their onward submission to Cabinet in February 2026. Appendix 4 is the approved format for the budget book. The report also includes the revised approved capital programme and provides recommendations for changes to the programme.

Recommendations 2. That the Executive Lead Member for Universal Services recommends that the Cabinet and County Council approve the revised 2025/26 capital programme, the 2026/27 and the provisional future years capital programmes totalling £1.2 billion, as set out in Appendix 2. 3. That the Executive Lead Member for Universal Services approves the addition of the schemes in table 2 to the capital programme at a value of £13.650 million. 4. That the Executive Lead Member for Universal Services approves the increase in the capital programme value for the schemes listed in table 3 at a value of £5.345 million. 5. That the Executive Lead Member for Universal Services recommends approval to the Leader and Cabinet of the removal of the Fleet Access Plan from the capital programme with the project replacing the plan, “Hitches Lane and Elvetham Roundabout Cycling and Pedestrian Accessibility”, remaining in the capital programme. 6. That the Executive Member for Universal Services notes that residual elements of the Woodhouse Lane (South) scheme, renamed ‘Botley, Southern Gateway’ within the approved capital programme will be delivered as part of the Botley Bypass project. 7. The authority is delegated to the Director of Universal Services in consultation with the Executive Lead Member for Universal Services and Executive Member for Highways and Transport to prepare a draft Local Transport Delivery Plan for Hampshire County Council based on the Capital Programme as agreed through this report, and to submit this to the Department for Transport by the 20 March 2026, as required by Government. 8. That authority is delegated to the Director of Universal Services in consultation with the Executive Lead Member for Universal Services and Head of Legal Services to enter a Memorandum of Understanding with the Department for Transport as required as a condition for receipt of grant funding. 9. That the Executive Lead Member for Universal Services notes that the complex box slide operation at M27 Junction 10 was successfully completed during the holiday period, under a full motorway closure, representing a significant engineering achievement for the scheme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Universal Services Proposed Capital Programme 2026-27 2027-28 and 2028-29 and 2025-26 Q3 UpdateReport 483 KB DownloadRead as text
PDF
Universal Services Proposed Capital Programme 2026/27, 2027/28 and 2028/29 and 2025/26 Q3 UpdateReport 54 KB Download

At this meeting

Whole meeting
128Minutes of previous meetingOn the agenda 1312026-27 Revenue BudgetDecided
132Universal Services Proposed Capital Programme 2026/27, 2027/28 and 2028/29 and 2025/26 Q3 UpdateThis decision
133Hampshire Lane Rental SchemeDecided 134Work ProgrammeAgreed

Who was there

17 of 18 attended
JB
Councillor Jackie BransonChairman, present
MF
Councillor Michael FordVice-Chairman, present
SB
Councillor Stuart BaileyCommittee Member, present
SB
Councillor Steven BroomfieldCommittee Member, present
PB
Councillor Pamela BryantCommittee Member, present
RC
Councillor Rod CooperCommittee Member, present
DC
Councillor Debbie Curnow-FordCommittee Member, present
TD
Councillor Tim DaviesCommittee Member, present
DD
Councillor David DrewCommittee Member, present
PH
Councillor Pal HayreCommittee Member, present
WI
Councillor Wayne IrishCommittee Member, apologies, sent representative
GJ
Councillor Gavin JamesCommittee Member, absent

All 18 on the meeting page

On this subject at Hampshire

Search all
  1. Universal Services Proposed Capital Programme 2026/27, 2027/28 and 2028/29 and 2025/26 Q3 UpdateThis decision
  2. Report of the Universal Services SP25 Working GroupAgreed
  3. Report of the Universal Services SP25 Working GroupNoted
  4. 2024/25 Revenue Budget Report for Universal ServicesDecided
  5. Universal Services Proposed Capital Programme 2023/24, 2024/25 and 2025/26Decided
  6. 2023/24 Revenue Budget Report for Universal ServicesDecided

More from Hampshire Universal Services Select Committee

All decisions
MeetingDecisionOutcome
22 Jun 2026 An Introduction to ScrutinyThe Committee noted the presentation. Noted Open
22 Jun 2026 Transport Planning and Scheme Development 2026-27 Programme and Local Transport Delivery PlanThat the Universal Services Select Committee supports the recommendations being proposed to the Executive Member ... ... Decided Open
22 Jun 2026 Work ProgrammeThat the Universal Services Select Committee agrees the work programme as presented and authorises the Chairman, in c... Agreed Open
2 Mar 2026 Hampshire Local Authority Bus Grant (BSIP) Investment Programme for 2026/27 to 2029/30RESOLVED That the Universal Services Select Committee supports the recommendations being proposed to the Executive Le... Decided Open
2 Mar 2026 Biodiversity Report 2026RESOLVED That the Universal Services Select Committee supports the recommendations being proposed to Cabinet. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies