Best Start Family Hubs

Noted Committee 3 papers

AI summaryHampshire's children committee noted progress on the Best Start Family Hubs programme, with the first hub at Leigh Park opening 21st March 2026 and 30 hubs planned over three years, backed by £6.2 million in grant funding.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedFirst hub opening 21st March 2026
Money£6.2 million grantFor 2026/27 to 2028/29
What happens nextScale to 30 hubsOver next three years
Who it affectsFamilies with young childrenAcross Hampshire districts

What was decided

The Children and Young People Select Committee noted the progress of the Best Start Family Hubs programme.

The committee noted the alignment with Neighbourhood Working and other programmes actively involved and engaged with this programme. Report P2

The committee noted progress towards setting up Hampshire Best Start Family Hubs, including the opening of the first hub in March 2026 and the ambition for 30 hubs. Report P1, P8, P19

Why

Best Start Family Hubs is a national Department for Education initiative designed to improve outcomes for babies, children and families by creating accessible services in local communities. Report P4, P6

Hampshire was not among the 75 local authorities funded in 2021, so must work quickly to catch up and ensure the programme meets national standards and delivers the same level of support as those authorities that started earlier. Report P9

The programme aims to address challenges early, reduce inequalities, and promote school readiness and family resilience by bringing health, education, social care and voluntary sector support together in one accessible location. Report P10, P35

What happens next

The Leigh Park hub will become fully operational in March 2026 and then transition to business as usual, with the next ten proposed locations being Gosport, Alton, Hythe and Dibden, Fareham, Aldershot, Farnborough, Andover, Winchester, Basingstoke and Eastleigh. Report P19

The programme team will await further Department for Education guidance on funding and resourcing for the dedicated SEND practitioner required in every hub from April 2026. Report P13

The team will develop detailed implementation plans for the next ten locations scheduled to open in 2026/27, with Corporate Land and Asset colleagues identifying suitable site options for Board approval. Report P19

The money

  • £6.2 million Grant funding for 2026/27 to 2028/29 to support rollout and operation of the Hubs Report P21
  • £370k Initial development grant for 2025/26 Report P21
  • £1.5 billion National investment over 3 years for the Best Start in Life strategy Report P5

Options considered

  • Chosen: Deliver 30 Family Hubs across Hampshire within 3 years. To meet the national ambition of 1,000 Family Hubs by 2029, informed by local needs analysis including deprivation indices, early years development gaps and SEND prevalence Report P8
  • Chosen: Request exemptions from specific Department for Education menu programmes. To tailor the offer to the unique needs of Hampshire communities where there are valid local reasons Report P12
  • Chosen: Use existing community assets as hub sites, with no new building required. In depth scoping is identifying the most appropriate existing locations for each hub roll out Report P47

Implications

  • Financial: Hampshire secured £6.2 million grant funding for 2026/27 to 2028/29, plus an initial £370k development grant for 2025/26. Funding after 2028/29 is not yet determined and ongoing sustainability is a critical consideration when setting up Hubs. Report P21
  • Legal: Where hubs are located within existing Hampshire libraries, the council must continue to deliver a comprehensive and efficient service under the Public Libraries and Museums Act 1964, and the council has a duty under Section 149 of the Equality Act 2010. Report P27, P43
  • Equalities: Positive equality impacts have been identified in the Equality Impact Assessment. From April 2026, every hub must have a dedicated SEND practitioner, though further guidance on funding and resourcing is awaited. Report P13, P29
  • Climate: Sites will be existing community assets with no new building required. Climate assessments are integral to scoping, considering heat, sea level rise, heavy rainfall, and storm and wind events. Active travel features such as walking and wheeling routes, inclusive access and cycle, mobility scooter and buggy parking are planned. Report P47, P48, P49, P50, P51, P53
  • Risk: Local Government Reorganisation is likely to have a significant impact on the roll out, potentially affecting governance arrangements, resource allocation, partnership working, and the pace of implementation, though it may also present opportunities to streamline services. Report P11
  • Staffing: Every hub must have a dedicated SEND practitioner from April 2026. A Research and Engagement Manager is being onboarded to lead on insights and support co production with families. Report P13, P26

Who and where

  • Families with babies and young children across Hampshire Report P5, P6
  • Residents in the next ten proposed hub locations: Gosport, Alton, Hythe and Dibden, Fareham, Aldershot, Farnborough, Andover, Winchester, Basingstoke and Eastleigh Report P19
  • Families in the 30% most disadvantaged communities nationally, where 70% of hubs are prioritised Report P7
  • Users of Hampshire libraries where hubs may be co located, under the Public Libraries and Museums Act 1964 Report P27

Timeline

  • July 2025: Government published 'Giving Every Child the Best Start in Life' strategy Report P5
  • November 2025 to early March 2026: Programme team achieved key milestones including leadership set up and submission of the DfE Readiness Survey Report P14
  • 28th of January: CMT confirmed Best Start Family Hubs as a priority programme for Hampshire Report P23
  • February 2026: Research and Engagement Manager to be in post Report P26
  • March 2026: Leigh Park Hub to become fully operational Report P19
  • 21st March 2026: Leigh Park Hub ready to open as the first hub in Hampshire, with extensive family activities planned Report P15
  • April 2026: Every hub must have a dedicated SEND practitioner under new Department for Education guidance Report P13
  • 2026/27: Next ten hub locations scheduled to open Report P19
  • April 2028: National target of 75% of children achieving a Good Level of Development Report P5
  • 2029: National ambition to establish 1,000 Family Hubs Report P8

Plain English for the jargon

  • DfE: Department for Education
  • GLD: Good Level of Development, a measure of early years school readiness
  • HLE: Home Learning Environment, a programme type for families with young children
  • EBI: Evidence Based Interventions from the Department for Education menu
  • IDACI: Income Deprivation Affecting Children Index, a measure of child area deprivation
  • LCP: Local Children's Partnerships, district level multi agency bodies
  • LGR: Local Government Reorganisation, structural changes to council arrangements
  • SEND: Special Educational Needs and Disabilities
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item242

Resolved

That the Children and Young People Select Committee note the progress of the programme.
Word for word from the decision Hampshire published for this meeting. Source: democracy.hants.gov.uk

Follow this further

Built from Hampshire's papers

What the report saysPro

Report to Children and Young People Select Committee

Recommendation

2. To note the contents of this report and the progress towards setting up Hampshire Best Start Family Hubs across Hampshire including the opening of the first Hub in March 2026.

3. Note the alignment with Neighbourhood Working and other programmes actively involved and engaged with this programme.

Executive summary

4. This report seeks to:

• Set out the background to the Best Start Family Hubs programme. This is a national DfE initiative designed to improve outcomes for babies, children, and families by creating accessible services in local communities. • Brief the Children and Young People Select Committee on the progress in Hampshire and the next steps of the programme. Contextual information

5. Best Start in Life is part of the government’s wider “Giving Every Child the Best Start in Life” strategy, published in July 2025. The aim of the strategy is to ensure that every child has the best start in life, from conception to starting school. With an overall national target that 75% of children achieve a Good Level of Development (GLD) by April 2028 (the target for Hampshire is “Greater than 80%”, with national investment of £1.5 billion over 3 years.

6. Best Start Family Hubs are part of this strategy and will be physical or virtual environments where families can get friendly, practical support. Services include parenting help, early learning, health visiting, infant feeding support and signposting.

7. When considering sites, Local authorities must prioritise neighbourhoods facing the greatest barriers to accessing support, with an ambition for 70% of all hubs to be in the 30% most disadvantaged communities nationally.

8. The national ambition to establish 1,000 Family Hubs by 2029 sets a clear framework for early years transformation. Hampshire’s commitment to delivering 30 hubs within the same timeframe is informed by a comprehensive local needs analysis, including deprivation indices, early years development gaps, and SEND prevalence.

9. In 2021, 75 local authorities across England received government funding to establish Family Hubs, but Hampshire was not among those receiving funding. As expectations remain the same for all areas, Hampshire must therefore work quickly to catch up and ensure our programme meets national standards and delivers the same level of support as those authorities that started earlier.

10. Best Start Family Hubs will play a crucial role in creating thriving children, improving health outcomes, preventing children from entering care, and improving educational outcome. By bringing together health, education, social care, and voluntary sector support in one accessible location, these hubs ensure families receive the right help at the right time. This integrated approach addresses challenges early, such as parenting, mental ill health, or financial hardship, before they escalate to crisis point. As a result, more families are supported to stay together safely, reducing the need for statutory interventions and care proceedings. The focus on early years development, school readiness, and targeted support for those most at risk helps break cycles of disadvantage and keeps children within their family networks whenever possible.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Agenda Item 6: presentation: Best Start Family HubsAgenda 1.6 MB Download
PDF
Best Start Family HubsReport 270 KB DownloadRead as text
PDF
EIA0980: Best Start Family HubsReport 222 KB Download

At this meeting

Whole meeting

Who was there

16 of 22 attended
JH
Councillor Juliet HendersonChairman, present
PN
Councillor Phil NorthVice-Chairman, apologies
PB
Councillor Prad BainsLiberal Democrats Spokesperson, present
JB
Councillor Jackie BransonCommittee Member, apologies, sent representative
AB
Councillor Ann BriggsCommittee Member, apologies
PB
Councillor Pamela BryantCommittee Member, present
JB
Councillor Joanne BurtonCommittee Member, present
DD
Councillor David DrewCommittee Member, present
PF
Councillor Paula FergusonCommittee Member, present
MF
Councillor Michael FordCommittee Member, present
JG
Councillor Jonathan GlenCommittee Member, present
LM
Councillor Lesley MeenaghanCommittee Member, present

All 22 on the meeting page

On this subject at Hampshire

Search all
  1. Best Start Family HubsThis decision
  2. Best Start Family HubsNoted
  3. Best Start and Community Hubs, Families First Early Prevention work and the Local Offer LiveDecided

More from Hampshire Children and Young People Select Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 NHS - Briefing on the Hampshire Child and Adolescent Mental Health ServiceThat the Children and Young People Select Committee: i) Notes the progress made in reducing the numbers of children a... Decided Open
8 Sep 2026 NHS - Children and Young People's Mental Health and Wellbeing: Update on Commissioning IntentionsThat the Children and Young People Select Committee: i) Notes the progress made in improving children and young peopl... Decided Open
8 Sep 2026 SEND Reform Task and Finish Working GroupThat the Children and Young People Select Committee: That the Committee: i) establishes a Task and Finish Working Gro... Agreed Open
8 Sep 2026 Hampshire Youth Justice Service Plan 2026- 2028That the Children and Young People Select Committee recommends that the Executive Lead Member for Children’s Services... Approved Open
8 Sep 2026 Adopt South - Annual Report 2025-2026 with Hampshire County Council HighlightsThat the Children and Young People Committee notes the contents of the Adopt South Annual Report 2025-2026. Approved Open