Hampshire Prosperity Partnership Board - LEP Legacy Reserves

Decided Executive 2 papers

AI summaryHampshire Cabinet considered £22m of capital grants from LEP legacy reserves for 14 economic growth projects, with conditions on three. Two shortlisted projects were not recommended.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeRecommendedTwo shortlisted projects not recommended; conditional on three
Money£22,002,321Total capital grant awards from LEP legacy reserves
What happens nextGrant funding agreements to be signedEstimated 5 to 6 weeks after Cabinet
Who it affectsHampshire businesses, workers and residentsAcross skills, workspace, transport and innovation projects

What was decided

Cabinet considered the Hampshire Prosperity Partnership Board's recommendation to approve £22,002,321 of capital grant funding from the LEP legacy reserves across 14 shortlisted projects set out in Table 1, fully using the £22.3m allocation within the Universal Services Capital Programme approved by Full Council in February 2026. Report P9, P10, P26, P27

Approval of three projects is recommended to be conditional: Project 26 (Bacteriophage facility) on a legally-binding partner agreement within three months of Cabinet approval; Projects 37 and 47 (Havant Maths and English Hub and Alton Adult Learning Hub) on removal of HSDC's enhanced supervision status by the Department for Education. Report P27, P38

Two shortlisted projects (No. 28 BRIDGE Workforce and Innovation Centre and No. 39 Seascape Restoration and Innovation Centre) were not recommended for funding because they were not affordable within the £22.3m budget constraint. Report P28, P29, P30, P31

Why

HPPB's recommendation followed a call for projects from 27 November 2025 to 16 January 2026 that received 53 eligible applications requesting £120.85 million, more than five times the £22.3 million available. Report P23, P24, P34

Initial assessment by a Hampshire County Council officer panel on 26 and 27 January 2026 shortlisted 16 projects, which then went through financial and legal due diligence and HPPB review on 9 March and 1 June 2026. Report P25, P35, P36, P37, P38

The Chief Financial Officer advised that, although the LEP legacy reserves are not legally ringfenced and could in principle support the 2027/28 budget (forecast deficit of £179.7m), using them in that way would conflict with the previous Administration's decision to apply them to economic development and the original Government purpose of the funding. Report P40, P46, P47, P48, P62, P63, P64, P65

What happens next

Following Cabinet approval, Hampshire County Council will finalise and sign grant funding agreements with each applicant, a process expected to take 5 to 6 weeks, with monitoring and payment processing handled by the Economy and Skills team within Universal Services. Report P39, P43, P44, P45

A subsidy control assessment must be completed for the New Forest Tour award before information is uploaded to the subsidy database. Report P41, P42

For Project 26, a legally-binding agreement between project partners must be in place no later than 7 October 2026 before Hampshire County Council signs a funding agreement with the applicant. Report P27, P38

The money

  • £22,002,321 Total LEP legacy reserve capital grant funding recommended across 14 projects Report P26
  • £22.3 million Total LEP reserve balance for future projects within Universal Services Capital Programme Report P10, P27, P31
  • £13 million Share of available funding from the former Solent LEP, 58% Report P9
  • £9.3 million Share of available funding from the former Enterprise M3 (EM3) LEP, 42% Report P9
  • £120.85 million Total LLR funding requested across 53 eligible applications, over five times the available total Report P24
  • £25.92 million 2024/25 year-end LEP legacy reserves balance (£22.30m capital and £3.62m revenue) Report P18
  • £101.9m Draw from reserves to balance the 2026/27 budget Report P53
  • £329.7m Total draw from reserves across 2022/23 to 2026/27 Report P53
  • £179.7m Forecast budget deficit for 2027/28 Report P54, P55, P60
  • £108.1m Assessed available reserves to support the 2027/28 budget shortfall (excluding LEP reserves) Report P55, P58
  • £71.6m Shortfall of available reserves against the forecast 2027/28 deficit of £179.7m Report P55
  • £2.37m per annum Cost of borrowing £22.3m over 20 years (MRP of £1.1m and interest of £1.27m) at 5.78% PWLB rate including -0.2% certainty rate Report P61, P64
  • £47.4m Total 20-year cost of borrowing £22.3m at 5.78% PWLB rate Report P61, P64

Options considered

  • Recommended: Approve capital grant funding from LEP legacy reserves for the 14 shortlisted projects in Table 1, subject to conditions on Projects 26, 37 and 47, and enter into grant funding agreements. Recommended by HPPB on 1 June 2026 following due diligence; uses the full £22.3m allocation for economic development in line with the strategic principles agreed in December 2024 Report P3, P10, P27, P36, P37, P38
  • Rejected: Do not approve award of capital grant funding from the LEP legacy reserves for the 14 shortlisted projects Report P10
  • Rejected: Repurpose the £22.3m LEP legacy reserves to help balance the 2027/28 budget instead of funding the projects. The Chief Financial Officer noted the option but the recommendation retains the reserves for economic development consistent with previous Administration decision and original Government purpose, even though the CFO considered repurposing for the budget was a valid use Report P62, P63, P64, P65

Implications

  • Financial: Using the full £22.3m of LEP legacy reserves for these projects removes them from reserves available to help balance the 2027/28 budget deficit of £179.7m, where assessed available reserves are £108.1m (a £71.6m shortfall). The CFO's Section 25 report already concluded reserves were 'not adequate' for 2027/28 without including these funds. Report P53, P54, P55, P58, P59, P65
  • Legal: The award to New Forest National Park Authority for new low-emission open-top buses amounts to a subsidy under the Subsidy Control Act 2022 and requires an assessment and upload to the subsidy database before the funding agreement is concluded. Report P41, P42
  • Equalities: The decision has been assessed as having a positive impact on the protected characteristics of age, race and sex, and on the characteristics of poverty and rurality, with neutral impact on all other protected characteristics. Report P41, P54
  • Climate: Projects are expected to deliver decarbonisation benefits including reduced emissions from digitisation, green construction skills, lower carbon energy, pedestrian and cycle links, increased EV uptake and new electric buses, and innovations supporting net zero. The County Council's standard climate change tools were not applied because the projects are delivered by other organisations. Report P42, P43, P44
  • Risk: A Section 24 Direction is expected to apply from May 2027 once shadow authorities are elected; this could require the consent of relevant shadow authorities for certain material decisions on four projects promoted by Borough Councils (Projects 13, 23, 38 and 42), but is not expected to affect the current signing of funding agreements in 2026. Report P38, P40, P66, P67, P68, P69, P70, P71, P72
  • Risk: Havant and South Downs College (applicant for Projects 37 and 47) has a Department for Education Financial Notice to Improve and a post-moderated Financial Health grade of 'Inadequate' for the year ending July 2024; approval is conditional on its enhanced supervision status being removed. Report P27, P38, P68

Who and where

  • Hampshire businesses, particularly in aerospace, defence, security, creative industries, food, drink, farming and hospitality Report P9, P12, P13, P18
  • Hampshire residents, including NEETs and those at risk of becoming NEET, over-50s returning to work, and residents in deprived communities such as Leigh Park Report P16, P19, P24
  • Construction, retrofit, green skills, digital and advanced manufacturing training providers and trainees in Hampshire Report P14, P12, P15
  • Public transport users in Romsey and visitors to the New Forest National Park Report P21, P23
  • Start-ups and small and medium-sized enterprises seeking workspace in Fareham, Rushmoor, Havant and the Solent Enterprise Zone at Daedalus Report P15, P20
  • Future unitary (shadow) authorities in Hampshire from May 2027, who may need to consent to certain project decisions under a Section 24 Direction Report P38, P66, P67, P68, P69, P70, P71, P72

Timeline

  • 1 April 2024: Responsibility for Local Enterprise Partnership functions transferred to upper tier local authorities following a change in Government policy Report P12
  • 11 June 2024: Hampshire Prosperity Partnership Board held its first meeting Report P13
  • 5 December 2024: Executive Member Decision Day agreed principles and governance for use of LEP legacy reserves for economic development functions Report P16, P47
  • 27 June 2025: Executive Member Decision Day set out 2024/25 year-end LLR position of £25.92 million available balance Report P18, P48
  • 27 November 2025: Hampshire County Council, with HPPB, opened a call for projects seeking LEP legacy reserve capital funding Report P19, P34
  • 16 January 2026: Call for projects closed: 55 applications received, two withdrawn, 53 eligible applications requesting £120.85 million Report P23, P24
  • 26 to 27 January 2026: Officer panel carried out initial assessment and shortlisting of applications Report P25
  • 10 to 12 February 2026: Shortlisted applicants presented to the officer panel face-to-face Report P25
  • 9 March 2026: HPPB discussed the call for projects and agreed all 16 shortlisted projects should proceed to due diligence Report P29, P30, P31, P32, P36
  • 1 June 2026: HPPB agreed to recommend 14 of the 16 shortlisted projects for funding, with conditions on Projects 26, 37 and 47 Report P10, P36, P37, P38
  • 16 June 2026: Note to HPPB confirmed Project 42 now has an estimated BCR of at least 1.7 and that Local Government Reorganisation should not affect the HPPB recommendations Report P38, P39, P40, P65, P66, P67, P68, P69, P70, P71, P72
  • 7 July 2026: Hampshire County Council Cabinet considered HPPB recommendations on LEP legacy reserves Report P3, P4
  • No later than 7 October 2026: Deadline for legally-binding partner agreement for Project 26 (Bacteriophage facility) before Hampshire County Council signs a funding agreement Report P27, P38
  • May 2027: Shadow authority elections expected; a Section 24 Direction is then expected to apply to predecessor councils Report P68, P69

Plain English for the jargon

  • LEP legacy reserves (LLR): Financial assets transferred to Hampshire County Council from the former Solent LEP and Enterprise M3 (EM3) LEP following the transfer of LEP functions to upper tier local authorities on 1 April 2024
  • HPPB: Hampshire Prosperity Partnership Board, the Hampshire County Council-chaired economic growth board that recommends use of LEP legacy reserves
  • NEET: Not in Education, Employment or Training, used in relation to young people and post-16 learners
  • BCR: Benefit-Cost Ratio, used in the financial due diligence to assess value-for-money of projects
  • Section 24 Direction: A legal mechanism issued by the Secretary of State that prevents outgoing (predecessor) councils from making certain significant financial commitments without consent of the incoming shadow authority during local government reorganisation
  • MRP: Minimum Revenue Provision, the annual amount set aside to repay borrowing
  • PWLB: Public Works Loan Board, a government body that lends to local authorities
  • HSDC: Havant and South Downs College, a Hampshire further education college that currently has a Department for Education Financial Notice to Improve
  • GMP-certified: Good Manufacturing Practice certified, a quality standard for manufacturing facilities in regulated industries such as pharmaceuticals
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13

Resolved

Decision Record is attached to these minutes.
Word for word from the decision Hampshire published for this meeting. Source: democracy.hants.gov.uk

Follow this further

Built from Hampshire's papers

What the report saysPro

Report to Cabinet

HAMPSHIRE COUNTY COUNCIL

Decision Report

Decision Maker: Cabinet

Date: 7 July 2026

Title: Hampshire Prosperity Partnership Board – LEP legacy reserves

Report From: Director of Universal Services

Contact name: Stephen Martin

Email: [email protected]

Purpose of this Report 1. The purpose of this report is to ask Cabinet to consider the recommendations by the Hampshire Prosperity Partnership Board (HPPB) that Hampshire County Council should approve capital grant funding from the LEP legacy reserves (LLR) for the projects set out in Table 1, and to determine whether Cabinet approval is given. The overall aim of these projects is to contribute to sustainable and inclusive economic growth in Hampshire.

Recommendation(s) 2. That Cabinet notes: • the information set out in this report regarding the HPPB, the LLR, and the process followed by Hampshire County Council and the HPPB to invite and assess applications from partners for capital grant funding from the LLR; • the recommendations made by HPPB at its meeting on 1 June; • the advice of the Chief Financial Officer as set out in the finance section of this report at paragraphs 46 to 65 on Hampshire County Council's financial position, particularly in relation to the use of LEP Legacy Reserves. 3. That, taking into consideration all of the above, Cabinet: either gives its approval to the award of capital grant funding from the LLR, and to entering into contractual arrangements with the applicants, for the shortlisted projects shown in Table 1, as recommended by HPPB on 1 June 2026; or decides not to do so. Please note that following Cabinet approval, if given, funding for these projects will still be subject to concluding a grant funding agreement between Hampshire County Council and the applicant. Table 1 – Shortlisted projects recommended for funding by HPPB

Amount of Brief project No. Project Applicant LLR description funding

Delivering digital platforms to improve Hampshire productivity, Fare Digital Hampshire connectivity and 2 £57,300 Futures Fare market access, for Programme over 350 food, drink, farming and hospitality businesses.

Developing industry- validated Aerospace, apprenticeship and Defence and training curricula in 6 Security ADS £450,000 aerospace, defence Curricula and security, and Development licensing this to Hampshire FE and HE institutions.

A mezzanine extension to the existing Future Test Valley Skills Construction Community Sparsholt Centre at the Andover 12 £1,056,000 Construction College College campus, with Academy multi-trade, electrical, and retrofit and green skills bays.

Refurbishment of The Meads Business Rushmoor Centre to create IncuHive 13 Borough £1,445,000 19,000 sq ft of Farnborough Council affordable, flexible workspace for start- ups and SMEs. Amount of Brief project No. Project Applicant LLR description funding

Building a construction training centre in Leigh Park, providing skills development Havant opportunities for Leigh Park 23 Borough £6,681,080 individuals at risk of Skills Centre Council becoming Not in Education of Employment (NEET), and acting as a community hub.

Building the UK’s first GMP-certified University Bacteriophage bacteriophage and Hospital and Biologics biologics Southampton 26 Manufacturing £3,000,000 manufacturing facility, NHS and R&D to supply the NHS and Foundation Facility global private industry, Trust and boost leading- edge research.

Creating an online platform that will Hampshire Hampshire connect creative Creative 31 Chamber of £325,000 businesses with the Business Commerce people, advice and Escalator resources required to fuel their growth.

Creating a hub from which to deliver roll on Havant Maths / roll off, modular 37 and English HSDC £400,000 Maths and English Hub provision, to re-engage post 16 NEETs. Amount of Brief project No. Project Applicant LLR description funding

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Decision Record: LEP legacy reservesDecisions 122 KB Download
PDF
Hampshire Prosperity Partnership Board: LEP Legacy ReservesReport 290 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 9 attended
NA
Councillor Nick Adams-King Leader and Executive Member for Corporate ServicesChairman, present
KN
Councillor Kirsty North Deputy Leader and Executive Lead Member for Universal ServicesVice-Chairman, present
JB
Councillor Joanne Burton Executive Member for Health and WellbeingCommittee Member, present
RC
Councillor Roz Chadd Executive Lead Member for Children's ServicesCommittee Member, present
SF
Councillor Steve Forster Executive Member for Highways and Passenger TransportCommittee Member, present
JH
Councillor Juliet Henderson Executive Member for EducationCommittee Member, present
ZH
Councillor Zoe Huggins BEM Executive Lead Member for Adult Social Care and Public HealthCommittee Member, present
SR
Councillor Stephen Reid Executive Member for Corporate Services - FinanceCommittee Member, present
AT
Councillor Andy Tree Executive Member for Corporate Services - People and Local Government ReorganisationCommittee Member, present

More from Hampshire Cabinet

All decisions
MeetingDecisionOutcome
9 Jun 2026 Local Government Re-organisation – Potential Legal ChallengeIt was agreed that all group leaders would be kept informed of developments. The Chairman indicated that the reason f... Agreed Open
11 Nov 2025 Your Hampshire, today and for tomorrow: Hampshire County Council Strategic Plan 2025-2028 (Key)Decision Record is attached to these minutes. Decided Open
11 Nov 2025 Exclusion of press and publicThat the public be excluded from the meeting during the following item of business, as it was likely, in view of the ... Decided Open
21 Mar 2025 English Devolution White Paper - Response to Government’s Devolution ConsultationCabinet agrees to submit the County Council’s response to the consultation launched by the Government on 17 February ... Agreed Open
21 Mar 2025 English Devolution White Paper - Local Government ReorganisationThat Cabinet: Notes the emerging journey for Local Government Reorganisation in Hampshire and the Solent including th... Agreed Open