HERITAGE LOTTERY FUNDED LANDSCAPE DEVELOPMENT PROJECT UPDATE (Report of the development manger) To update on progress made towards the programme of works for this year's project items.
NotedCommittee1 paper
Alexandra Park and Palace Consultative Committee noted this item on Tuesday 27 June 2006. Below is the council's own wording, with the papers it was decided on.
RESOLVED i. that the contents of the report and the comments expressed during discussions be noted; ii. that a report be brought to the meeting of the Consultative Committee on 5 September 2006 detailing an overall update ... view the full minutes text for item 47.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
Report to Alexandra Park and Palace Consultative Committee
Agenda item:
Alexandra Park & Palace Consultative Committee On 27th June 2006
Report Title: Heritage Lottery Funded Landscape Development Project update
Report of: Matthew Baker, Development Manager – Parks
1. Purpose 1.1 To update the Committee of progress towards the items outlined in the HLF refurbishment of the Park.
2. Recommendations 2.1 That the Committee notes the report.
Report Authorised by: Matthew Baker, Development Manager:
Contact Officer: Matthew Baker, Development Manager
3. Executive Summary 3.1
4. Reasons for any change in policy or for new policy development (if applicable) 4.1 N/A
5. Local Government (Access to Information) Act 1985 5.1 No specific background papers were used in compiling this report. Further information about this report can be obtained from Matthew Baker, Development Manager – Parks, Alexandra Palace & Park, Alexandra Palace Way, Wood Green, London, N22 7AY. Telephone number 0208 365 2121
1 6. Background 6.1 Blakedowns Southeast are making good progress with the phase two package of works as specified by Land Use Consultants in accordance with the approved purposes of the Heritage Lottery Grant.
The contractor had previously prepared a programme of works with the intention of completing all the works by July 2006, leaving a six month period between August 2006 – January 2007 for any additional works and to attend to defects. Unfortunately due to the early announcement of a national hose pipe ban and potential water restrictions a decision has been taken to postpone the majority of the planting phase until the end of the summer 2006 to ensure the best conditions for establishment of new stock.
In addition to this all tree work has been suspended until the autumn in order to prevent disturbance during the nesting season.
Please note general tree maintenance/Emergency works will be still be carried out in order to reduce the risk to visitors.
6.2Blakedowns are contracted to complete the improvements to the main road as part of the Civil engineering package of works. Work commenced in February following the Motorcycle show and has been phased over a seven month period. Colin Buchanan and Partners who were responsible for this aspect of the project have continued to liaise with Highways Authority and Transport for London to ensure the design proposal satisfies all of the requirements.
Due to changes in the regulations for new bus stops introduced in January 2006 it has not been possible to reduce the number of Bus stops to the West of the Palace as previously reported. Transport for London have stated that they would not support the removal of the existing stops as they are networked to there electronic timetable system. In addition to this the location which had been identified for the single stop has does not comply with their new regulations.
For reasons of Health & Safety it will be necessary to operate temporary traffic lights during much of the Civils works. Blakedowns have contracted ‘A-Plant’ Traffic Systems assist with all traffic management issues to ensure that the works are in accordance with the regulations for highways work.
In broad terms these improvements are focused at reducing the speed of vehicles within the park, increasing the number of pedestrian links between the Palace and Park and improving the general road layout.
The improvements which fall outside of the Park Boundary will be completed by the highway authority and LUC will liaise to ensure that these works are carefully phased with Blakedowns programme.
6.2.1 Bedford Road Entrance The Gantry will be removed and the main entrance realigned with a speed table constructed to slow vehicles when entering and exiting the
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
HERITAGE LOTTERY FUNDED LANDSCAPE DEVELOPMENT PROJECT UPDATE (Report of the development manger) To update on progress made towards the programme of works for this year's project items.Minutes
47HERITAGE LOTTERY FUNDED LANDSCAPE DEVELOPMENT PROJECT UPDATE (Report of the development manger) To update on progress made towards the programme of works for this year's project items.This decision
HERITAGE LOTTERY FUNDED LANDSCAPE DEVELOPMENT PROJECT UPDATE (Report of the development manger) To update on progress made towards the programme of works for this year's project items.This decision
Follow Alexandra Park and Palace Consultative Committee at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.