1) That, in accordance with Contract Standing Order 7, approval be granted to a waiver of Contract Standing Order (Requirement to Tender) in connection with the Energy Efficiency Scheme.. 2) That, in accordance with Part H.2 of the Constitution (Executive Procedure Rules), Section 1.02, Sub-delegation of Executive Functions, the award of the contract be delegated to the Director of Social Services in consultation with our Chair. That officers review the arrangement which required separate reports in relation to waivers of Contract Standing Orders and awards of contracts and advise our Committee of whether or not this practice should be discontinued
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
6.1In 2003 Haringey Council with Haringey Homes & Building services leading entered a contract with British Gas Trading Ltd (BG) to deliver energy efficiency measures to public housing residents. In so doing Haringey became a ‘flagship Local Authority’, delivering the BG “Home Essentials for Living Programme” (HELP scheme).
6.2BG’s HELP scheme is designed to help residents out of ‘fuel poverty’. The programme consisted of subsidised draft proofing, cavity wall and loft insulation, radiator panels and thermostatic valves etc. HELP also provided advice to residents on securing benefits while providing subsidised, or free, home security measures including chains and peepholes for the vulnerable and elderly.
6.3Haringey’s Environmental Services entered a parallel contract with BG to provide a similar range of services to the private sector, including Haringey Leaseholders.
6.4Environmental Services selected qualifying occupiers by identifying geographical areas and writing to occupiers inviting them to sign up to the scheme. This method of identification proved successful and is proposed to continue to 2008. This will be augmented with road show publicity events.
6.5Between September 2005 and June 2006 over five thousand public sector housing properties were surveyed, and seven hundred and fifty four properties (equivalent to 15% of the surveyed stock) received the range of energy conservation measures.
th Procurement Committee Report for 18 July ‘06 2 6.6 This relatively low ratio is in part due to the fact that Haringey consistently insulated cavities and lofts under the annual Housing Capital Programme (funded via the MRA and SCE) and hence few cavities and lofts remain to be insulated.
6.7Energy conservation measures undertaken via the BG contract and Housing capital works programme over 2004/05 financial year yielded a sample of properties achieving a draft energy SAP rating of 66.07. This is equivalent to 2 points above Haringey’s LPSA target. This ‘SAP report’ will be reviewed and issued in due course to advice on BVPI 63.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Award of coroners' removals contractRESOLVED · That approval be granted for the award of contract for a Coroners’ removal service to Dignity Funeral Ltd ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.