That the Cabinet Member for Resources write to the committee setting out the timetable for and the scope of a post-implementation review of the Council’s Tech Refresh project. 2. That the recommendations of the Scrutiny Review Panel be endorsed and be referred to Cabinet.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
2.1That the Scrutiny Panel agree this report and the recommendations summarised below and refers the report to Overview and Scrutiny Committee for endorsement and refers it to the Cabinet Committee.
2.2That the Cabinet notes the finding by SOCITM, the external reviewer, that on the basis of the projects examined, the quality of Haringey IT Services project management processes are in the top ten percent when compared with similarly sized public sector bodies that SOCITM has worked in the past. The Cabinet further notes that the IT Services project management failings identified by the Audit Commission in the Tech Refresh project were either, not found by SOCITM in the other contemporary projects examined, or have been seen to be rectified in the subsequent projects examined.
Nevertheless, the review highlighted areas needing improvement in the wider management of IT projects, priorities and use across the Council, which are reflected in the following recommendations:
2.3That the Cabinet ensures that Project Sponsors, Project Boards and Project Managers have the skills, knowledge and access to information to allow them to work effectively in order that projects are managed better in their totality.
1 2.4 The Cabinet adopts and allocates 5% of total budget, as a ‘norm’, for project governance and that this only be exceeded when it can be justified.
2.5That the Cabinet ensures that Post Implementation Reviews are carried out on all appropriately sized Council programmes/projects and that they be carried out independently, by personnel unconnected with the project board/team, (a suggestion being the Improvement Team in Policy and Performance), and that they be carried out 9/12 months, or longer if appropriate, post full implementation, to allow benefits to be more accurately measured and reported to the Cabinet. PIR should cover changes in the tangible and measurable metrics used in the original business case or justification for the projects.
2.6That the Cabinet ensures greater consistency in the budget monitoring of all Council programmes/projects, by implementing the SAP Project Systems and Investment Management Modules.
2.7That the Cabinet, while recognising that addressing the issues identified with supplier management in the review is about more than just the procurement process, implements additional measures in the procurement process to ensure that:
• Claims made by suppliers are challenged and verified.
• Payment schedules are linked to key milestones.
• Penalties for non delivery and poor performance are part of supply contracts, whenever feasible.
• Penalties are consistently imposed, where it is justified.
Contact Officer: Trevor Cripps - Overview and Scrutiny Manager
Telephone: 020 8489 6922
Executive summary
3.1The Overview and Scrutiny Committee (O&SC) decided to scrutinise the effectiveness of the management of key projects by the Council’s IT Services department over the period 2003 – 2006, with a view to learning lessons from the past and agreeing any possible improvements for the future.
3.2To undertake this scrutiny the O&SC commissioned and convened an IT Scrutiny Review Panel made up of Members, which in turn appointed SOCITM Consulting as external reviewer. Their role was to carry out a review of selected projects via detailed discovery and analysis, as required to produce an evidence-based report to the Panel on past performance and recommendations for the future.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Press and PublicRESOLVED To exclude the press and public from the meeting to consider exempt information as defined under paragraph 3...
Committee Membership Update ReportRESOLVED – That Cllr Anne Gray be appointed as the Chair of the Adults & Health Scrutiny Panel. That Cllr Anne Gray b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.