Resolved
RESOLVED That a further report be brought back to the Planning Committee in January 2008.
Pre-2011 Planning Committee decided this item on Tuesday 4 December 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That a further report be brought back to the Planning Committee in January 2008.
Agenda item: 10 Planning Committee On 4th December 2007
Report Title: Planning Enforcement Project Update
Forward Plan reference number (no applicable):
Report of: Eubert Malcolm Service Manager Enforcement Response
Wards(s) affected: All Report for: Non Key Decision
1. Purpose To update committee Members on the progress of the planning enforcement Project
2. Introduction by Cabinet Member (not necessary)
3. Recommendations To note progress of the planning enforcement project
Report Authorised by: Robin Payne Assistant Director Urban Environment
Contact Officer: Brian Ellick Interim Team Leader Planning Enforcement
4. Director of Finance Comments
5. Head of Legal Services Comments
6. Local Government (Access to Information) Act 1985 7. Strategic Implications 7.1 To reduce the historical backlog of planning enforcement open cases and enable an improvement in planning enforcement performance.
8. Financial Implications 8.1 The project is currently being funded by salary under spends across the business unit. Recruitment following restructuring of the enforcement service is expected to allow continued funding until the end of December 2007.
9. Legal Implications 9.1 It should be noted that the Council may face the potential of having abuse of process arguments raised on behalf of defendant’s for undue delay in the Council bringing prosecution action against land owners and occupiers especially when many years have lapsed after the initial Enforcement Notice was served without any particularly persuasive reason. It has been suggested in leading case law however that this argument should only be successful in exceptional circumstances. Since the implementation of the Human Rights Act 1998, direct regard should also be had to Article 6(1) of the European Convention for the Protection of Human Rights and the related Strasbourg jurisprudence which states, in broad terms that in the determination of a person’s obligations or of any criminal charge against him, everyone is entitled to a fair and public hearing within a reasonable time and Article 6(3) sets out a list of what are described as minimum rights which must be afforded to any one charged with a criminal offence. These include the following: (a) to be informed promptly, in a language he understands and in detail, of the nature and cause of the accusation against him; (b) to have adequate time and facilities for the preparation of his defence.
10. Equalities Implications 10.1 Providing an effective planning enforcement service will help ensure fair and equal outcomes for all service users.
11. Consultation 11.1 No consultation apart from head of finance and legal services
12. Background 12.1 The Planning Enforcement Project commenced in January 2007 and has been running for nine months. The Project was the result of a proposal put forward to Planning Application Committee (PAC) to reduce and manage the open planning enforcement cases by two thirds within four to six months.
12.2In order to better manage the open cases the project was broken into three phases. At the start of the project there were a reported 1531 open cases. At the end of October 2007 there were a reported 711 open cases.
12.3The process for closing any case within the project requires authorisation from either one of the two heads DC. It was agreed by Development control (DC) that in the first
Report Template: Formal Bodies / Member Only Exec 2 phase project 20 cases per week could be referred over to the two heads of DC for closure.
PHASE 1 FOUR YEAR RULE
12.4Under the four year rule, any case where work was carried out over four years ago is immune from legal action.
12.5In the first phase of the project 489 cases were originally deemed to fall within the four year rule, however after close examination of each case a percentage of the cases were deemed not suitable to close under this rule and as a result required further investigation.
• 495 cases received • 311 cases closed (immune) • 178 requiring further enforcement investigation
PHASE 2
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Planning Enforcement Project UpdateMinutes | 92 KB | DownloadRead as text |
Follow Pre-2011 Planning Committee at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 May 2011 | Tree Preservation OrdersRESOLVED That the at land to east side of Plevna Crescent and land to the rear of Ermine Road, N15 and at 67 Alexandr... | Decided | Open |
| 16 May 2011 | 19A Thorold Road, N22RESOLVED That the planning permission be granted in accordance with Planning application no. HGY/2010/2066, subject t... | Agreed | Open |
| 16 May 2011 | L/A 110 Broad Lane N15RESOLVED That application HGY/2011/0551 be approved granted permission subject to conditions and subject to a Section... | Approved | Open |
| 11 Apr 2011 | Tree Preservation OrdersRESOLVED That the Tree Preservation Order upon the tree located at 35 Stanhope Gardens, N6, be confirmed. | Decided | Open |
| 11 Apr 2011 | 225 Archway Road, N6RESOLVED That application HGY/2011/0194 be refused on the grounds that the proposed development to the rear of the si... | Refused | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.