DEVELOPMENT CONTROL PERFORMANCE STATISTICS
BEST VALUE INDICATOR BV109 - DETERMINING PLANNING APPLICATIONS
November 2007 Performance
In November 2007 there were 186 planning applications determined, with performance in each category as follows -
100% of major applications were determined within 13 weeks (1 out of 1)
79% of minor applications were determined within 8 weeks (30 out of 38 cases)
92% of other applications were determined within 8 weeks (135 out of 147 cases)
For an explanation of the categories see Appendix I
Year Performance – 2007/08
In 2007/08 up to the end of November there were 1445 planning applications determined, with performance in each category as follows -
67% of major applications were determined within 13 weeks (10 out of 15 cases)
76% of minor applications were determined within 8 weeks (285 out of 374 cases)
87% of other applications were determined within 8 weeks (920 out of 1056 cases)
The monthly performance for each of the categories is shown in the following graphs:
DC Statistics – Planning Committee 07.01.08 1 Major Applications 2007/08
Percentage of major applications Performance Haringey target determined within 13 weeks DCLG target
100% 90% 80% 70% Percentage
60% 50% 40% 30% 20% 10% 0%
Nov June
Jan July
Mar Aug
Feb April
Sept
Oct May
Dec 2007-08
Minor Applications 2007/08
Percentage of minor applications Performance Haringey target determined within 8 weeks DCLG target
100% 90% 80% 70% Percentage
60% 50% 40% 30% 20% 10% 0% May
July
Nov
Mar Aug April
Sept
Oct
Dec June
Jan
Feb
2007-08
DC Statistics – Planning Committee 07.01.08 2 Other applications 2007/08
Performance Percentage of other applications Haringey target determined within 8 weeks DCLG target 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% May
July
Nov
Mar April
Aug
Sept
Oct
Dec June
Jan
Feb 2007-08
Background/Targets
BV109 is one of the Department for Communities and Local Government (DCLG) Best Value indicators for 2007/08.
It sets the following targets for determining planning applications:
a. 60% of major applications within 13 weeks b. 65% of minor applications within 8 weeks c. 80% of other applications within 8 weeks
Haringey has set its own challenging targets for 2007/08 in relation to BV109. These are set out in Planning Policy & Development (PPD) Business Plan 2007-10 and are to determine:
a. 82% of major applications within 13 weeks b. 85% of minor applications within 8 weeks c. 90% of other applications within 8 weeks
DC Statistics – Planning Committee 07.01.08 3 Appendix I
Explanation of categories
The BV109 indicator covers planning applications included in the DCLG PS1/2 statutory return.
It excludes the following types of applications - TPO's, Telecommunications, Reserve Matters and Observations.
The definition for each of the category of applications is as follows:
Major applications -
For dwellings, where the number of dwellings to be constructed is 10 or more For all other uses, where the floorspace to be built is 1,000 sq.m. or more, or where the site area is 1 hectare or more.
Minor application -
Where the development does not meet the requirement for a major application nor the definitions of Change of Use or Householder Development.
Other applications -
All other applications, excluding TPO's, Telecommunications, Reserve Matters and Observations.
DC Statistics – Planning Committee 07.01.08 4 DEVELOPMENT CONTROL PERFORMANCE STATISTICS
GRANTED / REFUSAL RATES FOR DECISIONS
November 2007 Performance
In November 2007, excluding Certificate of Lawfulness applications, there were 154 applications determined of which:
69% were granted (107 out of 154)
31% were refused (47 out of 154)
Year Performance – 2007/08
In 2007/08 up to the end of November excluding Certificate of Lawfulness applications, there were 1179 applications determined of which:
67% were granted (794 out of 1179)
33% were refused (385 out of 1179)
The monthly refusal rate is shown on the following graph:
Percentage of planning applications refused 2007-2008
100%
90% 80% 70% 60%
50%
40% 30% 20% 10%
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
07 01 08 Planning Ctt: DC StatsMinutes | 87 KB | DownloadRead as text |
PDF |
PE Stats for Planning Committee Meeting January 08Minutes | 54 KB | Download |
PDF |
Performance StatisticsMinutes | 26 KB | Download |
Follow Pre-2011 Planning Committee at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 May 2011 | Tree Preservation OrdersRESOLVED That the at land to east side of Plevna Crescent and land to the rear of Ermine Road, N15 and at 67 Alexandr... | Decided | Open |
| 16 May 2011 | 19A Thorold Road, N22RESOLVED That the planning permission be granted in accordance with Planning application no. HGY/2010/2066, subject t... | Agreed | Open |
| 16 May 2011 | L/A 110 Broad Lane N15RESOLVED That application HGY/2011/0551 be approved granted permission subject to conditions and subject to a Section... | Approved | Open |
| 11 Apr 2011 | Tree Preservation OrdersRESOLVED That the Tree Preservation Order upon the tree located at 35 Stanhope Gardens, N6, be confirmed. | Decided | Open |
| 11 Apr 2011 | 225 Archway Road, N6RESOLVED That application HGY/2011/0194 be refused on the grounds that the proposed development to the rear of the si... | Refused | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.