Resolved
RESOLVED That the report be noted.
Pre-2011 Planning Committee noted this item on Monday 9 June 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the report be noted.
Planning Committee 9 June 2008
DEVELOPMENT CONTROL PERFORMANCE STATISTICS
BEST VALUE INDICATOR NI 157 (FORMERLY BV 109) - DETERMINING PLANNING APPLICATIONS
April 2008 Performance
In April 2008 there were 194 planning applications determined, with performance in each category as follows -
100% of major applications were determined within 13 weeks (3 out of 3)
83% of minor applications were determined within 8 weeks (44 out of 53 cases)
91% of other applications were determined within 8 weeks (125 out of 138 cases)
For an explanation of the categories see Appendix I
Year Performance – 2008/09
In 2008/09 up to the end of April there were 194 planning applications determined, with performance in each category as follows -
100% of major applications were determined within 13 weeks (3 out of 3 cases)
83% of minor applications were determined within 8 weeks (44 out of 53 cases)
91% of other applications were determined within 8 weeks (125 out of 138 cases)
The monthly performance for each of the categories is shown in the following graphs:
DC Statistics – Planning Committee 09.06.08 1 Major Applications 2008/09
Percentage of major applications Performance Haringey target determined within 13 weeks DCLG target
100% 90% 80% 70% Percentage
60% 50% 40% 30% 20% 10% 0%
Nov June
Jan July
Mar Aug
Feb April
Sept
Oct May
Dec 2008-09
Minor Applications 2008/09
Percentage of minor applications Performance Haringey target determined within 8 weeks DCLG target
100% 90% 80% 70% Percentage
60% 50% 40% 30% 20% 10% 0% May
July
Nov
Mar Aug April
Sept
Oct
Dec June
Jan
Feb
2008-09
DC Statistics – Planning Committee 09.06.08 2 Other applications 2008/09
Performance Percentage of other applications Haringey target determined within 8 weeks DCLG target 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% May
July
Nov
Mar April
Aug
Sept
Oct
Dec June
Jan
Feb 2008-09
Background/Targets
NI 157 (formerly BV 109) is one of the Department for Communities and Local Government (DCLG) National Indicators for 2008/09.
It sets the following targets for determining planning applications:
a. 60% of major applications within 13 weeks b. 65% of minor applications within 8 weeks c. 80% of other applications within 8 weeks
Haringey has set its own challenging targets for 2008/09 in relation to NI 157. These are set out in Planning Policy & Development (PPD) Business Plan 2008-11 and are to determine:
a. 82% of major applications within 13 weeks b. 85% of minor applications within 8 weeks c. 90% of other applications within 8 weeks
DC Statistics – Planning Committee 09.06.08 3 Appendix I
Explanation of categories
The NI 157 indicator covers planning applications included in the DCLG PS1/2 statutory return.
It excludes the following types of applications - TPO's, Telecommunications, Reserve Matters and Observations.
The definition for each of the category of applications is as follows:
Major applications -
For dwellings, where the number of dwellings to be constructed is 10 or more For all other uses, where the floorspace to be built is 1,000 sq.m. or more, or where the site area is 1 hectare or more.
Minor application -
Where the development does not meet the requirement for a major application nor the definitions of Change of Use or Householder Development.
Other applications -
All other applications, excluding TPO's, Telecommunications, Reserve Matters and Observations.
DEVELOPMENT CONTROL PERFORMANCE STATISTICS
GRANTED / REFUSAL RATES FOR DECISIONS
April 2008 Performance
In April 2008, excluding Certificate of Lawfulness applications, there were 164 applications determined of which:
79% were granted (129 out of 164)
21% were refused (35 out of 164)
Year Performance – 2008/09
In 2008/09 up to the end of April, excluding Certificate of Lawfulness applications, there were 164 applications determined of which:
79% were granted (129 out of 164)
21% were refused (35 out of 164)
DC Statistics – Planning Committee 09.06.08 4 The monthly refusal rate is shown on the following graph:
Percentage of planning applications refused 2008-2009
100%
90% 80% 70% 60%
50%
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
DC Stats Rept ~ 9 JuneMinutes | 43 KB | DownloadRead as text |
PDF |
Perf Stats Rept ~ 9 JuneMinutes | 18 KB | Download |
PDF |
Performance StatisticsFrontsheet | 22 KB | Download |
Follow Pre-2011 Planning Committee at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 May 2011 | Tree Preservation OrdersRESOLVED That the at land to east side of Plevna Crescent and land to the rear of Ermine Road, N15 and at 67 Alexandr... | Decided | Open |
| 16 May 2011 | 19A Thorold Road, N22RESOLVED That the planning permission be granted in accordance with Planning application no. HGY/2010/2066, subject t... | Agreed | Open |
| 16 May 2011 | L/A 110 Broad Lane N15RESOLVED That application HGY/2011/0551 be approved granted permission subject to conditions and subject to a Section... | Approved | Open |
| 11 Apr 2011 | Tree Preservation OrdersRESOLVED That the Tree Preservation Order upon the tree located at 35 Stanhope Gardens, N6, be confirmed. | Decided | Open |
| 11 Apr 2011 | 225 Archway Road, N6RESOLVED That application HGY/2011/0194 be refused on the grounds that the proposed development to the rear of the si... | Refused | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.