Resolved
That the progress against the Corporate Programmes and status at the end of reporting period, as shown in Appendix 1 to the interleaved report be noted.
Cabinet noted this item on Tuesday 17 June 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
That the progress against the Corporate Programmes and status at the end of reporting period, as shown in Appendix 1 to the interleaved report be noted.
Page 1 of 2
Corporate Programme Highlight Report Status of Projects as at: End of 2007/08 Appendix 1
Resources Timescale
Budget Provisional Total project
Issues
Risks Overall Current year Year to date Total project Project Project Sponsor Start Date End Date variance for the projected Comments RAG Status budget variance budget year variance
(Note RAG status - Red if projected over by +/- 5%, amber if between zero and +/- 5% over, green if on target.) Regeneration Programme Board RGN01 Haringey Heartlands Niall Bolger G G G G G N/A Apr-07 Apr-08
RGN02 Tottenham Hale Urban Centre Niall Bolger G G G G G N/A Oct-06 2016
RGN03 Wood Green Town Centre David Hennings G G G G G G Apr-06 Jul-08 71,800 0 0 71,800 0 Tottenham High Road Strategy Grant savings and revenue budgets identified to meet RGN04 Implementation David Hennings G G G G G A Jan-05 2010 2,698,400 (268,000) (268,000) 6,916,000 100,000 overspend. Lack of contingency going into construction key RGN05-2 Mortuary Niall Bolger G G G G R G Apr-06 Dec-08 1,311,000 18,000 18,000 3,149,000 0 project risk.
RGN05-3 Hale Village Niall Bolger G G G G G G Apr-06 Mar-08 2,131,000 (1,000) (1,000) 2,502,000 0 Project closed. Late handover of site by third party; validating final RGN05-4 Spine Road Niall Bolger R A G R A R Apr-06 Apr-08 5,009,400 (17,000) (17,000) 5,400,000 500,000 cost prior to pursuing compensation. Council Owned Land RGN06 Regeneration Julie Parker A A G A A G 2006 2012 350,000 0 0 765,000 0 Profiled budget from next year brought forward to RGN07 Wards Corner Niall Bolger G G G A A G Mar-07 2012 1,226,255 0 0 2,000,000 0 alleviate under spend in other NDC schemes. Working with PfS on: Design & affordability; Choice, CYP01 Building Schools for the Future Ita O'Donovan R A G R R G Apr-06 Mar-11 15,378,200 (13,000) (13,000) 199,600,139 0 diversity & access & PFI / DOV
CYP02 Primary Capital Programme Ian Bailey G G G G A G May-06 Apr-09 9,051,000 (2,392,000) (1,942,000) 37,034,000 0
CYP03 Children's Centres: Phase II Ian Bailey A A G A A G Apr-06 Sep-08 4,846,000 (1,653,000) (1,653,000) 6,106,000 0 Regeneration Programme Board Total 42,073,055 (4,400,000) (3,876,000) 263,543,939 600,000
Better Haringey Programme Board Estates Improvement 95% final budget spend agreed at Mar-08 Programme BH01 Programme Bob Watts G G A G G G Apr-07 Mar-08 1,209,000 (36,000) (36,000) 1,209,000 0 Board; project closed. Raising Awareness & Muswell Hill Clean Sweep taking place Apr-08; BH02 Involvement Joanna David G G G G G A Apr-07 Apr-08 245,400 (9,000) (9,000) 245,400 0 revenue project: not included in the total figures. Environmental Cleanliness & BH03 Enforcement Beverley Taylor G G G G G G Mar-06 Mar-08 280,000 0 0 280,000 0 Project closed. Open Space Improvement Snagging and Making the Difference projects to be BH04-1 Programme John Morris G A G G G G Apr-07 Mar-08 488,000 0 0 1,723,000 0 completed in Apr-08. Sports & Leisure Services - BH04-2 Strategic Renewals John Morris G G G G G G Sep-05 Mar-08 660,000 (39,000) (39,000) 4,338,000 200,000 Overspend occurred in 2006/07; project closed.
BH04-3 Chestnuts John Morris G G G G G G Apr-06 Jun-08 560,000 (50,000) (50,000) 560,000 0 Pollution of surface water drainage key risk; working RGN05-1 Markfield John Morris G G G A R G Apr-06 Mar-10 1,032,000 (156,000) (156,000) 3,613,000 0 with Environment Agency to mitigate. End date updated to reflect target date for BH04-4 Parkforce Resource Review John Morris G G G G A G Jul-06 Mar-09 0 0 0 implementation of efficiency savings.
BH05 Recycling Beverley Taylor G G G G G G Apr-07 Mar-08 215,000 0 0 215,000 0 Project closed. Better Haringey Programme Board Total 4,689,400 (200,000) (281,000) 12,183,400 200,000 Total 46,762,455 (4,600,000) (4,157,000) 275,727,339 800,000
Cabinet20080617Item08QuarterlyProgrammeReportAppendix0.xls Page 2 of 2
Corporate Programme Highlight Report Status of Projects as at: End of 2007/08 Appendix 1
Resources Timescale
Budget Provisional Total project
Issues
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Cabinet_2008.06.17_Item 08_Quarterly Programme Report: AppendixMinutes | 29 KB | DownloadRead as text |
PDF |
Quarterly Programme ReportMinutes | 149 KB | Download |
Follow Cabinet at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Nov 2026 | Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None | Decided | Open |
| 10 Nov 2026 | Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None | Decided | Open |
| 10 Nov 2026 | Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None | Decided | Open |
| 10 Nov 2026 | Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None | Decided | Open |
| 10 Nov 2026 | Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.