Resolved
That the minutes of the following meetings be noted and any necessary action approved – a) Corporate Parenting Committee – 12 April 2010; b) Procurement Committee – 27 April 2010;
Cabinet noted this item on Tuesday 15 June 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
That the minutes of the following meetings be noted and any necessary action approved – a) Corporate Parenting Committee – 12 April 2010; b) Procurement Committee – 27 April 2010;
MINUTES OF THE CABINET PROCUREMENT COMMITTEE TUESDAY, 27 APRIL 2010 Councillors *Bob Harris (Chair), *Bevan, Kober and *Reith.
*Present
MINUTE ACTION NO. SUBJECT/DECISION BY
PROC95. APOLOGIES FOR ABSENCE (Agenda Item 1)
An apology for absence was submitted by Councillor Kober.
PROC96. DECLARATIONS OF INTEREST (Agenda Item 3)
Councillor Bevan declared a personal interest by virtue of being Chair of the London Housing Consortium.
PROC97. MINUTES (Agenda Item 4)
RESOLVED
That the minutes of the meeting held on 30 March 2010 be HLDMS approved and signed.
PROC98. CORPORATE LEARNING AND DEVELOPMENT PROGRAMME - SHORT COURSES AND IT TRAINING: FRAMEWORK AGREEMENTS (Report of the Assistant Chief Executive – People and Organisational Development - Agenda Item 6)
The Appendix to the interleaved report was the subject of a motion to exclude the press and public from the meeting as it contained exempt information relating to the business or financial affairs of any particular person.
We noted that the report sought approval of framework agreements with suppliers for the provision of the Council’s competency based corporate learning and development programmes.
RESOLVED
1. That in accordance with Contract Standing Order 11 ACE- approval be granted to framework agreements with the POD following suppliers for the provision of the Council’s competency based corporate learning and development programmes -
Lot 1 – Short Courses to Support the Council’s Competency
Deborah West Eliesha Public Sector Providers MINUTES OF THE CABINET PROCUREMENT COMMITTEE TUESDAY, 27 APRIL 2010
Redhill Group
Lot 2 – IT Training for Standard MS Office Based Applications or Upgraded Equivalents College of Haringey, Enfield and North East London
2. That the agreement be awarded for a period of two years ACE- with an option to extend for two further periods of one year POD on the basis detailed in the report.
PROC99. HARINGEY PUBLIC MORTUARY (Report of the Director of Urban Environment - Agenda Item 7)
The Appendix to the interleaved report was the subject of a motion to exclude the press and public from the meeting as it contained exempt information relating to the business or financial affairs of any particular person.
We noted that the report advised the final costs involved in the construction of the new mortuary for the Borough and sought approval for variations in the construction and consultancy contracts to accommodate increased costs. We were advised of the increase in the cost from the original to the final figure.
RESOLVED
1. That in accordance with Contract Standing Order 13.02 DUE approval be granted to final variations in the construction and consultancy contract sums for construction of the new public mortuary to accommodate increased costs over the amounts approved on 19 February 2009.
2. That it be noted that the final total project sum was £3,775,000 which was an overspend of £17,000 on the revised budget carried over from 2008/9.
PROC100. EXTENSION OF SUPPORTING PEOPLE CONTRACT - SIXTY PLUS (Report of the Director of Adult, Culture and Community Services - Agenda Item 8)
Our Chair agreed to admit the report as urgent business. The report was late because of the need to complete necessary consultations. The report was too urgent to await the next meeting because the new contract was scheduled to start on 1 June 2010.
The Appendix to the interleaved report was the subject of a motion to exclude the press and public from the meeting as it contained exempt information relating to the business or financial affairs of any particular person. MINUTES OF THE CABINET PROCUREMENT COMMITTEE TUESDAY, 27 APRIL 2010
We noted that the report sought agreement to a one year extension to the existing contract for the supporting people sixty plus service.
RESOLVED
That in accordance with Contract Standing Order 13.02 approval DACCS be granted to the extension of the Contract (60 Plus) to the current Provider, Metropolitan Support Trust for a fixed term of 12 months.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2010.06.15_Item 18b_ Proc Cttee MinutesMinutes | 96 KB | DownloadRead as text |
PDF |
Minutes of Other BodiesMinutes | 71 KB | Download |
Follow Cabinet at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Nov 2026 | Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None | Decided | Open |
| 10 Nov 2026 | Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None | Decided | Open |
| 10 Nov 2026 | Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None | Decided | Open |
| 10 Nov 2026 | Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None | Decided | Open |
| 10 Nov 2026 | Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.