LONDON BOROUGH OF HARINGEY
AUDIT PROGRESS REPORT
JUNE 2010
Work Progress
Audit Plan Our full audit plan and updated audit fee was agreed with management and 2009/10 presented to the February 2010 Audit Committee.
2009/10 As part of our 2009/10 plan, we have begun work with the Council to help accounts audit prepare for the 2009/10 accounts audit, including the Head of Corporate Finance attending a half day accounts workshop on 10 February at our offices. Interim - our interim audit work is underway and there are no issues to report to the Audit Committee. We will present our accounts audit strategy document to the July meeting. Final - we will audit the year end accounts between July and September 2010 and report our results to members as part of the Report to those charged with governance (ISA260).
International In 2009, we held a workshop with the Council and issued an IFRS Financial conversion report planner to management which highlighted the areas of Reporting greatest likely impact for the Council and proposes a number of actions for Standards the Council. We are continuing to work with management as preparations (IFRS) for IFRS continue and had a positive meeting with officers on 29 March to review the good progress being made to date.
Use of Our work on the main phase of the use of resources assessment, was resources and completed by the deadline and we submitted our draft scores to the Audit data quality Commission. At a theme level, the scores remained as for last year, with the 2010 Council managing some improvements in KLoEs within the themes. We regard this as a good result for the Council. On data quality, our provisional assessment was that the Council's arrangements were now adequate overall but that this would need to be confirmed through data quality spotcheck work that we will carry out over the summer. Work Progress
Use of Following the change of government, the Audit Commission has withdrawn resources and the UoR scored assessment, although we are still required to reach a data quality statutory VFM conclusion which is substantially fed from our assessments in 2010 the former UoR KLoE areas. (continued) We will issue a Value for Money report in September 2010 and key messages will be presented to the October 2010 Audit Committee. Our local UoR projects on leaseholder service charges and partnership working were completed by March and we will present these reports to this Audit Committee. Our workforce management review findings and conclusions were also communicated to management in March and we gave a positive assessment in our UoR submission to the Audit Commission.
Grants 2008/09 We presented our report of summary findings to the February 2010 Audit Committee.
Indicative fees We have agreed our indicative fee for 2010/11 with the Chief Financial letter 2010/11 Officer. This letter is prepared in advance of the audit year in order to provide the Audit Commission will details of indicative fees nationally. Our risk assessment and, if required, our audit fee will be updated and further detail provided in our full 2010/11 Audit Plan, which will be presented to the Audit Committee in early 2011.
Grant Thornton UK LLP June 2010
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Audit Committee update from Grant ThorntonMinutes | 65 KB | DownloadRead as text |
Follow Audit Committee (old) at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Nov 2010 | Audit Progress reportRESOLVED That the content of the report be noted. | Noted | Open |
| 2 Nov 2010 | Annual Statement of Accounts - outcome of the annual audit for 2009/10 and Review of the Annual Governance StatementRESOLVED That the management responses contained in the action plan be agreed, and that the Committee receive an upda... | Agreed | Open |
| 2 Nov 2010 | Treasury Management Practices DocumentRESOLVED That the Treasury Management Practices document be approved. | Approved | Open |
| 2 Nov 2010 | Housing Benefits - 2nd quarter progress report on counter fraud activityRESOLVED That the content of the report and the work being carried out by the Benefits and Local Taxation Service in ... | Noted | Open |
| 2 Nov 2010 | Internal Audit - 2nd quarter progress reportRESOLVED i) That the audit coverage and progress during the second quarter 2010/11. ii) That progress and responses r... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.