Consultative Committee Meeting On 16th November 2010
Report Title: External Fabric Condition Update
Report of: Andrew Gill, Interim General Manager, Alexandra Palace & Park Charitable Trust
1. Purpose 1.1 To update the Consultative Committee on the external fabric condition of Alexandra Palace.
2. Recommendations 2.1 The Consultative Committee is asked to note the progress report on the external fabric condition and the action being taken by the Trust to address the high priority items.
Report Authorised by: Andrew Gill, Interim General Manager
Contact Officer: John Barnett, Interim Facilities Management Consultant, Alexandra Palace & Park, Alexandra Palace Way, Wood Green N22 7AY Tel No. 020 8365 4334
3. Executive Summary 3.1 An asset management survey of the external fabric has been completed, which identifies high priority works that need to be undertaken.
3.2A sum of £138k has been allocated during this financial year to address some of these items, notably the South Elevation adjacent to the Panorama Room.
3.3A further bid of £500k has been made to the Council for capital funding during 2011/12 to further address the external fabric of the building and replace the Fire Alarm and Evacuation systems
4. Reasons for any change in policy or for new policy development (if applicable N.A.
5. Local Government (Access to Information) Act 1985 5.1 No specific background papers were used in compiling this report.
1 6 Progress Report
6 In 2005 a detailed condition audit of the site was commissioned by APPCT with King Sturge LLP as part of the proposal to let the Palace on a long term repairing lease. Inflating the reports findings by the RPI index (12%, Appendix 2) it was estimated that a sum in excess of £30 million would be required to put the buildings into a weather proof, structurally sound condition with the primary mechanical and electrical systems being fit for purpose. Thereafter the ongoing annual average maintenance cost would be on average £568k. Since this time few works have taken place to arrest the continuing deterioration of the Palace and the General Managers Facilities Manager team believe that the site now has less that two years in which to address these issues before it has a serious impact on the sites operation. During 2009/10 the Interim General Manager FM team struggled financially to address the basic areas of compliance within its allotted R&M budget and was forced to adopt a “Fix & Patch” policy when systems failed.
6.1A capital grant from the Council was granted in 2010/11 of £500,000 to start addressing some of these issues. A contract has now been commissioned through the Council’s Framework Consultants to produce a detailed Asset Management Survey of the building external fabric. It was recognised that at the current time an investment such as that identified in the 2005 King Sturge survey was un-realistic. The objectives of this recent report were therefore to identify key areas of:-
Ø Health and Safety Risk. (Falling brickwork and masonry) Ø Security/Fire Risk (gaps in structure allowing access into the internal fabric) Ø Actions to arrest further deterioration of the fabric. (i.e. water ingress, weed growth)
6.2The report which has recently been received prioritises and budget costs the minimum works that need to be undertaken to ensure the deterioration of the fabric is arrested. It is estimated a sum of £756k needs to be invested over the next 10 years with much of this expenditure within the next 2 to 3 years (Appendix 1). The priority 1 actions at a cost of £138k are currently being addressed and this sum has been allocated during this financial year. This will provide a minimal investment on the structure to keep it safe and water proof; these monies will not however address the severe fabric dilapidations in areas of the East wing (e.g. Theatre).
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
General Report on Palace buildingMinutes | 845 KB | DownloadRead as text |
Follow Alexandra Park and Palace Consultative Committee at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Jun 2026 | Response to traffic-related anti-social behaviour on alexandra palace wayThe update was noted and the ongoing partnership work to address traffic-related anti-social behaviour. | Noted | Open |
| 18 Jun 2026 | Alexandra park outdoor events reportThe report was noted. | Noted | Open |
| 18 Jun 2026 | Charitable trust - progress reportThe report was noted. | Noted | Open |
| 9 Mar 2026 | MINUTESAgreed the minutes of the Consultative Committee held on 2nd February 2026 as correct record. Noted the minutes of th... | Agreed | Open |
| 2 Feb 2026 | MINUTESAgreed. the minutes of the Consultative Committee held on 6th October 2025. Noted the minutes of the Statutory Adviso... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.