That the following recommendations, set out below, be agreed: The Haven Day Centre for Older People That this would not be closed, as previously proposed, but that the service model would be adjusted to provide a new and more flexible service for all adults providing care and support to both older people and people with mental health issues who live in the east of the Borough. With the rolling out of personal budgets, older people using the centre to purchase their care via a personal budget and look to an appropriate voluntary or independent sector provider to provide the service in the future, subject to market testing. Grange/Hayes Centres for Older Adults with Dementia That this would not be combined on one site, as previously proposed, but to continue as separate units under a combined staff and management structure and the day opportunities support there would be purchased via a personal budget as above. 684 Centre for People with Mental Health Issues This would be closed no later than 31 March 2012, as originally proposed, with eligible users of the service being offered an alternative service in The Clarendon Centre and on an outreach basis for two days in The Haven; care from The Haven to be purchased via a personal budget given to people to gain increased choice and control of their support packages. Woodside Day Centre for Older People That this would closed by no later than 31 March 2012 as originally proposed, with eligible service users offered a service in The Grange, The Hayes Centre or The Haven and their care to be purchased via a personal budget.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
Title of Proposal: Setting the strategic direction for Adult services: Proposed closure of council-run day services for Older People and people with Mental Health issues.
Lead Officer: Mun Thong Phung
Names of other Officers involved: Len Weir, Barbara Nicholls
Step 1 - Identify the aims of the policy, service or function
1. Introduction
1.1The proposals in this EqIA cover four older people’s day services and one mental health day service.
1.2The 2010 Comprehensive Spending Review and the subsequent local government settlement require Haringey Council to make savings of up to £81m or approximately 30% over the next four years. It is in the context of severe budget pressure that Haringey’s Adult Social Care service is setting the strategic direction and priorities for the next three years. This has placed the Council in an unprecedented position and it is seeking to reduce spending and make savings where possible. This comes alongside the need to transform adult social care services in line with the Putting People First programme which aims to deliver personalised care through self-directed support, with the aim of ensuring that vulnerable adults have greater choice, control over their care, and over their lives. The proposed changes are designed to respond to the changing needs of older people, people with learning disabilities and those with mental health needs by providing more cost effective, individualised care and support packages, with the aim of ensuring they are able to live more independently in the community.
1.3As part of the transformation of adult social care there is a need to shift focus to a more ‘personalised’ approach and offer all people assessed as requiring social care a personal budget (PPF-Putting People First and the updated policy: Think Local, Act Personal. The council needs to offer re-ablement, early intervention and extra care services. The cost of running our own services, partly as a consequence of higher administration and labour costs, is about 40% more than that for those owned by other sectors.
EQIA – 21/9/2011 1 1.4 In January 2009, the Care Quality Commission (CQC) Inspection said that whilst our services for older, vulnerable people were good, they commented that they were rather ‘traditional’ in outlook. While we regret that severe budget restraint makes it necessary, we welcome the opportunity to modernise our service provision. As a result of the pressures we face, we’re proposing to make a number of changes that are designed to:
Develop a programme of change that better meets the current and expected future needs of the people of Haringey. Increasing levels of service within a restricted budget envelope to meet increased levels of need associated with living longer. Create services that are more flexible. Create care and support that people can access close to where they live. Have better long term outcomes for people at lower costs. Be ready for the changes of an ageing population.
1.4Proposed changes
The original proposals in relation to the day centres for older people were as follows: • Close The Woodside Day Centre no later than 1 April, 2012. • Close The Haven no later than 1 April, 2012. • Merge the services at The Grange and the Haynes Centre, to come into effect no later than 1 April, 2012. • Close 684 Day Centre no later than 1 April 2012.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies