Resolved
RESOLVED to note the report.
Alexandra Park and Palace Joint Advisory & Consultative Committee noted this item on Tuesday 10 January 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to note the report.
Alexandra Park & Palace Informal Joint Meeting of the Advisory Committee and Consultative Committee on 10 January 2012
Report Title: Regeneration Programme Update
Report of: Mark Hopson, Head of Regeneration and Development, Alexandra Palace
1. Purpose 1.1 To update and consult with the Committees on progress in relation to the regeneration programme at Alexandra Palace.
2. Recommendations 2.1 That the Committees note the content of the report.
Report Authorised by: Duncan Wilson, Chief Executive…………………………
Contact Officer: Mark Hopson, Head of Regeneration and Development, Alexandra Palace, Alexandra Palace Way, Wood Green N22 7AY Tel No. 020 8365 4399
3. Executive Summary 3.1 The report outlines the key activities in relation to the on-going regeneration programme, in the current phase of work – Stage 2 – Concept Planning. Concisely:
- A specialist conservation architect has been appointed to lead on all conservation related work at Alexandra Palace including the development of a Conservation Masterplan (CMP) and management of conservation repairs. Both of these items are the subject of an on-going English Heritage grant proposal. - The existing English Heritage grant application is still under evaluation with a decision expected imminently - Preparatory scoping work is underway for the procurement of strategic design and master-planning services that will be required to begin work in February 2012. - Key documents such as the Business Plan and Procurement Strategy continue to be progressed
3.2The report outlines the draft strategic aims and regeneration development objectives that were approved by Trust Board on the 29th November 2011. These are intended to form the basis for on-going market research with potential Live Operators and, be the foundation for public consultation.
3.3The report highlights forthcoming milestones for the regeneration programme. These include:
- concluding market research - updating financial models, business plan and the procurement strategy - Procuring specialist design and masterplanning services
3.4A formal public consultation is now planned for May 2012 and will seek to engage broadly with stakeholders on regeneration plans.
4. Reasons for any change in policy or for new policy development (if applicable) 4.1 N/A
5. Local Government (Access to Information) Act 1985 5.1 N/A
6. Progress Update
6.1Regeneration work continues to progress broadly in line with the programme of work for the current period.
6.2Following a recent tender exercise for a specialist conservation architect, Donald Insall Associates have now been appointed on a term basis to develop a Heritage Management Plan and advise on specialist repairs to the historic fabric of the building. Both of these items are the subject of a current funding application to English Heritage.
6.3A decision is currently being awaited from English Heritage on the possibility of a grant award to part fund the development of a Conservation Management Plan (CMP) and key emergency repairs to the historic fabric of the building. The proposed repairs include:
- Render and brickwork repair/treatment to the South Terrace elevation directly in front of the Panorama Room - Reinstating permanent roofs to the east end buildings adjacent to the ice rink foyer and making these areas wind and water tight - Repairing the Theatre roof/gullies/gutters to remedy existing leaks
6.4In addition to the emergency repairs listed above, development funding is also sought to enable:
- Adequate surveys and investigation work to be carried out where necessary - Appropriate repair work specifications to be drawn up - Accurate job cost estimates to be calculated
6.5The Trust has been liaising closely with English Heritage officers in relation to the application and a decision on funding is expected imminently.
7. Strategic aims and objectives
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
REGENERATION UPDATEMinutes | 200 KB | DownloadRead as text |
PDF |
Regen App scannedMinutes | 33 KB | Download |
Follow Alexandra Park and Palace Joint Advisory & Consultative Committee at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Apr 2023 | Minutes and matters arisingThat subject to the above change, the minutes of the meeting held on 9 March 2023 and 17 November 2022 be agreed and ... | Agreed | Open |
| 20 Apr 2023 | Powerpoint presentation on 2022/23 achievements and plans for 2023/24RESOLVED That the presentation be noted. | Noted | Open |
| 9 Mar 2023 | Minutes & matters arisingRESOLVED To approve the minutes of the Joint Meeting of the Advisory and Consultative Committees held on 17 November ... | Approved | Open |
| 9 Mar 2023 | Chief executive officer (ceo) updateThat the contents of the report be noted. | Noted | Open |
| 9 Mar 2023 | Go ape mini-land roversThat proposal by Go Ape for a new mini-Land Rover activity in Alexandra Park be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.