Resolved

It was agreed that details of the case at 60 St Paul’s Road, N17 would be emailed to Cllrs Peacock and Christophides. Tony Michael, Legal Advisor, advised the Committee that the administering of a caution was an efficient way of dealing with cases as it ensured that enforcement notices were complied with. [name removed] explained that a warrant case was where someone had failed to appear in court, as a result of which a warrant for their arrest had been issued and they had yet to be located. Such cases were unusual, and were reviewed periodically. In response to a question regarding POCA, it was reported that following a conviction, the Council had the opportunity to apply for a confiscation order for the repayment of benefit accrued, where money had been made as a result of the breach. It was advised that this amounted to significantly more money being repaid to the Council than would be recovered by a fine being issued, as the Council would receive 18.75% of the amount agreed, to be used for planning enforcement. It was confirmed that, were the Council to be the initiating authority as well, they would receive a further 18.75% (37.5% in total) and that this was an incentive to train staff up as investigators, as was the model in other local authorities. It was confirmed that existing staff were receiving training, following the receipt by the Council of the first funds as a result of POCA. In response to a question regarding the issue of recovering housing benefit paid for unlicensed HMOs , it was reported that this was an issue the Council was currently looking into, with the support of Legal Services. Where the owner of a property could not be identified, [name removed] confirmed that the local authority did have powers to enforce the terms of the enforcement notice, but that use of such powers was extremely rare. Efforts tended to be concentrated on locating the owner, and the level of action taken would depend on the level of the breach and expediency. An example was given of a recent planning application where details of the enforcement history on the site had not been incorporated into the planning details given on the website, and the Committee asked how enforcement history fed into to the planning application process. [name removed] advised that enforcement and planning data were held on separate databases, although these were cross-referenced; it was now happening that enforcement history should appear as a section within the template for planning decisions and would therefore be visible on the website in relation to planning applications. In response to a request for ... view the full minutes text for item 61.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Regulatory Committee

Reason for recommendation

4.1Good progress continues with maintaining the number of open cases at a manageable level, which were 280 at 1st April 2012. This year has seen a significant increase in the enforcement notices issued (84 up from 68) and Appeal lodged 43 up from 32).

5. Other options considered 5.1. Not applicable

Summary

6.1This report advises members on service performance for 2011/12 and the teams’ incorporation into Development Management within the Planning regeneration and Economy Business Unit from 16 May 2011 and the incorporation of the management of the appeal service from September 2011

7. Chief Financial Officer Comments

7.1Planning Enforcement now forms part of the Planning, Regeneration and Economy business unit within Place and Sustainability and the staffing budget for the posts in this team is £193,100. The costs of preparing this report have been contained within existing budgets.

8. Head of Legal Services Comments

8.1The Head of Legal Services notes the contents of this report

9. Equalities & Community Cohesion Comments

9.1There are no equalities, and community cohesion issues raised by this report as it updates members on Planning Enforcement’s performance April-June 2011 inclusive. 10. Consultation

10.1The report identifies steps to consult service users.

11. Service Financial Comments

11.1The service will continue to ensure that the Planning Enforcement and Appeals caseload remains manageable and seeks to maintain the good performance of both services. The Appeal services involves all Planning Officers and the planning enforcement team has currently three dedicated Planning Officers and a Team Leader. Since late March 2012 a planner involved in the enforcement of issues along Tottenham High Road and its surrounds has been appointed as part of the Tottenham Project. The workload has remains consistently high throughout 2011-12.

12. Use of appendices /Tables and photographs Appendix 1 - The number of open cases by the year received Appendix 2 – April-March 2011-12 Breakdown of Cases by Breach Appendix 3 - April-March 2011-12- Enforcement action and Appeals by Type of Breach Appendix 4-Planning and Enforcement Appeals Received and Determined 2011-12 Appendix 5-Planning and Enforcement Appeal by type 2011-12 Appendix 6- Planning and Enforcement Appeals by way of determination 2011-12 Appendix 7 – April-March 2011-12 Planning Enforcement Performance indicators Appendix 8 - April-Sept 2011 Outcomes of Planning Enforcement Closed Cases Appendix 9 – Table showing planning enforcement prosecution & caution outcomes

13. Local Government (Access to Information) Act 1985

13.1Planning Enforcement Case files held by the Team Leader for Planning Enforcement, and Appeal case files by the Head of DMPE

14. Planning Enforcement Performance

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Planning Enforcement Update: Year Report 2011-12Minutes 101 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 13 attended
DB
Councillor Dhiren BasuCommittee Member, present
DB
Councillor David BeachamCommittee Member, present
ZB
Councillor Zena BrabazonCommittee Member, apologies
JC
Councillor Joanna ChristophidesCommittee Member, present
AD
Councillor Ali DemirciCommittee Member, present
JE
Councillor Joseph EjioforCommittee Member, present
TM
Councillor Toni MallettCommittee Member, present
SM
Councillor Stuart McNamaraCommittee Member, present
SP
Councillor Sheila PeacockCommittee Member, present
ER
Councillor Errol ReidCommittee Member, present
DS
Councillor David SchmitzCommittee Member, present
NS
Councillor Nigel ScottCommittee Member, present

All 13 on the meeting page

On this subject at Haringey

Search all
  1. Planning Enforcement Update - Year Report 2011-12This decision
  2. Development Management and Planning Enforcement Work Report for 2015/16Noted
  3. Development Management and Planning Enforcement workNoted
  4. Planning Enforcement Annual Update ReportNoted
  5. Planning Enforcement and Appeals Quarter One Update ReportNoted
  6. Planning Enforcement and Appeals Update- Half Year Report 2013-14Noted

More from Haringey Regulatory Committee

All decisions
MeetingDecisionOutcome
14 Jan 2021 Urgent businessRESOLVED 1. To a gree the appointment of Councillor Sheila Peacock to the Planning Sub-Committee , replacing Councill... Agreed Open
5 Oct 2020 Recent Government Announcements on PlanningRESOLVED that: A) The response to the changes to the current planning system consultation, which was submitted on 1 O... Noted Open
2 Oct 2020 Establishment of Planning and Licensing Sub Committees 2020/21RESOLVED that: 1. The terms of reference of the Regulatory Committee as set out within the Council’s Constitution, at... Noted Open
31 Jul 2020 Business and Planning Act 2020 - Pavement Licence conditions and fees as part of the Covid 19 recovery measuresRESOLVED to i. Agree the p avement licence conditions as outlined in Appendix A which will be the Council’s published... Agreed Open
14 Jul 2020 Amendment to Committee MembershipsRESOLVED that i. Councillor Sarah Williams be appointed as Chair of the Planning Sub Committee, and Licensing Sub Com... Noted Open