CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Haringey
Cabinet, Tuesday 16 April 2013 at 6.30pm

Rhodes Avenue School Expansion Project - Re-Procurement of Phase 3

Approved Executive 1 paper

Cabinet approved this item on Tuesday 16 April 2013. Below is the council's own wording, with the papers it was decided on.

Item395

Resolved

That the variation of Phase 3 of the contract with Balfour Beatty Scottish and Southern Ltd in the sum of £3,699,118, which is fully funded from the Capital Programme, be approved. That the issuing of a letter of variation in respect of the variation, prior to formal contract signature for 10% of the variation value in the sum of £369,911, be approved. That it be noted that the total cost of Phase 3, including all fees and other associated costs, as defined in the exempt part of the report, in the sum of £4,360,000 and to approve this value as the cash limit budget for this phase of the project. That it be noted that the current provision within the CYPS capital programme for Phase 3 of Rhodes Avenue Expansion was £2,700,000 and agree therefore that a virement was approved from the CYPS capital programme contingency in the sum of £1,600,00 to support the cash limit budget recommended above. Alternative Options Considered The following alternative options were considered: Ø Do nothing – this option would not achieve the authority’s key responsibility in providing sufficient primary school places Ø Reduce Scope – This failed to address existing condition and suitability issues contained within the project brief To continue with existing contractual arrangements (traditional contract) – This did not provide the Council with cost and time certainty Reasons for Decision To complete the expansion of Rhodes Avenue Primary School to service the increased pupil numbers in the area and to minimise the Council’s exposure to costs and further delays to the programme by varying the final phase of work as a Design and Build project.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet

Cabinet Item Report for: 16th April 2013 Number:

Title: Rhodes Avenue School Expansion Project Phase 3

Report Authorised by:

Libby Blake, Director of Children’s Services

Claire Barnes. Tel: 0208 489 1962 Lead Officer: [email protected]

Ward affected: Alexandra Ward Report for: Key Decision

1. Describe the issue under consideration

1.1To seek approval from Cabinet to vary the third phase of the contract with Balfour Beatty Scottish & Southern Ltd to deliver Rhodes Avenue Phase 3 Expansion Project in the sum of £3,699,118.20 which is fully funded from the Capital Programme

1.2Seek Cabinet approval to issue a letter of variation in respect of the variation prior to the formal contract signature for 10% of the variation value in the sum of £369,911.

2. Cabinet Member introduction

2.1The expansion of Rhodes Avenue Primary school from two form to three form entry is designed to meet the local authority’s statutory duty to provide sufficient school places. We have worked closely with the school throughout the work and need to press ahead to complete as school demand rises. This variation has been subject to detailed negotiations and I am content that the decision made offers best value for Haringey. 3. Recommendations

3.1Cabinet to approve the variation of Phase 3 of the contract with Balfour Beatty Scottish & Southern Ltd in the sum of £3,699,118 which is fully funded from the Capital Programme.

3.2Cabinet to approve the issuing of a letter of variation in respect of the variation prior to formal contract signature for 10% of the variation value in the sum of £369,911.

3.3Cabinet to note the total cost of Phase 3 including all fees and other associated costs as defined in Part B Exempt Information in the sum of £4,360,000 and to approve this value as the cash limit budget for this phase of the project.

3.4Cabinet to note the current provision within the CYPS capital programme for Phase 3 of Rhodes Avenue Expansion is £2,700,000 and agree therefore that a virement is approved from CYPS capital programme contingency in the sum of £1,660,000 to support the cash limit budget recommended above.

4 Background Information

4.1The London Borough of Haringey identified Rhodes Avenue Primary School as requiring expansion to service the increased pupil numbers in the area.

4.2The school will expand from a 2 form of entry to 3 form of entry offering an increase in pupil places from 420 to 630.

4.3Nursery places will remain at 26.

4.4The project is being carried out in 3 phases aimed to minimise disruption to the school and provide additional accommodation for each additional cohort from September 2011 onwards:

• Phase 1: New foundation building (nursery and reception) • Phase 2: Demolition of the existing Key Stage 1 (KS) building (reception, year 1, year 2), new 12 classroom building for KS2 (years 3-6), extension to the existing office accommodation, extension to the infant hall. • Phase 3: Extensive refurbishment of the existing KS2 wing and junior hall and provision of a new block accommodating 3 additional classrooms. • External spaces will be progressively developed during each phase.

4.5The overall scope of the project aims to improve existing suitability and condition issues. 4.6 Planning was granted for all 3 phases in April 2010. An amendment to extend the infant hall was further approved in May 2010. These approvals remain current.

4.7Building control application has been approved for all 3 phases. This application remains current.

4.8An equalities impact assessment was completed in November 2010. This remains a live document to be monitored through the life of the project.

5 Procurement Process

5.1An award of contact for enabling work was procured independently to the main contract and approved by the Director of Children and Young People’s Services under contract standing orders CSO 11:02. This work was completed in August 2010.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Rhodes Avenue School Expansion Project: Re-Procurement of Phase 3Minutes 115 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 17 attended
AK
Angela KawaCouncil Staff, expected
CK
Councillor Claire KoberChair, present
JB
Councillor John BevanCommittee Member, present
NC
Councillor Nilgun CanverCommittee Member, present
JG
Councillor Joe GoldbergCommittee Member, present
BV
Councillor Bernice VanierCommittee Member, apologies
AW
Councillor Ann WatersCommittee Member, present
RW
Councillor Richard WatsonCommittee Member, present
JP
Julie ParkerOfficer, expected
MT
Mun Thong PhungOfficer, expected
SY
Stuart YoungOfficer, expected
LG
Lyn GarnerOfficer, expected

All 17 on the meeting page

On this subject at Haringey

Search all
  1. Rhodes Avenue School Expansion Project - Re-Procurement of Phase 3This decision
  2. Rhodes Avenue Primary School, Rhodes Avenue, N22 7UTApproved
  3. Rhodes Avenue Primary School Expansion - Procurement of Design ConsultancyApproved
  4. OUR LADY OF MUSWELL HILL TENNIS CLUB, Adj 51 Rhodes Avenue N22Agreed

More from Haringey Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None Decided Open
10 Nov 2026 Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies