Resolved
That the minutes of the following meetings be noted: a) Corporate Parenting Advisory Committee – 3 October 2013 b) Decision by the Leader – 5 December 2013
Cabinet noted this item on Tuesday 17 December 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
That the minutes of the following meetings be noted: a) Corporate Parenting Advisory Committee – 3 October 2013 b) Decision by the Leader – 5 December 2013
MINUTES OF THE CABINET MEMBER SIGNING THURSDAY, 5 DECEMBER 2013
Present: Councillor Claire Kober, Leader of the Council.
In Xanthe Barker, Principal Committee Officer, Graham Beattie, Interim Assistant Attendance: Director of Single Frontline, Anne Woods, Head of Audit & Risk Management.
MINUTE ACTION NO. SUBJECT/DECISION BY
HSP37. URGENT BUSINESS
There were no items of Urgent Business.
HSP38. DEVELOPMENT OF WESTERN ROAD DEPOT
The Leader of the Council considered a report that sought approval to changes in contractual arrangements for the purposes of designing and delivering the engineering phase of the development. The report also sought approval to establish a capital budget of £1m for the delivery of the Reuse and Recycling Centre.
RESOLVED:
i. That the use of the Council’s existing LoHAC contract, for the purposes of delivering the engineering and design construction works required Dir P&S for the replacement Reuse and Recycling Centre at Western Road Depot, be approved, and that the call-off contract be awarded to Ringway Jacobs.
ii. That it be agreed that authority be delegated to the Director of Place and Sustainability to finalise the contract for these works, in a sum not Dir P&S
exceeding £675k, after consultation with the Cabinet Member for Environment.
iii. That the establishment of a capital budget of £1m for the initial delivery of the Reuse and Recycling Centre be approved, with all costs properly accounted to this project subsequently to be effectively recovered from Dir P&S
the North London Waste Authority on the purchase of the site by them.
iv. That it be approved that any necessary subsequent revision to the capital budget be delegated to the Director of Place and Sustainability, Dir P&S
in association with the Chief Financial Officer, and reported to Cabinet via budget monitoring.
Alternative options considered The Council could undertake a new procurement for the delivery of the MINUTES OF THE CABINET MEMBER SIGNING THURSDAY, 5 DECEMBER 2013
required works. A new procurement would add a period of around two months to the timetable. This option therefore carries a very significant risk of extending timescales beyond the target completion date (end-March 2014) and therefore would prejudice the Council’s disposal of the Hornsey Depot site.
In contrast the recently awarded LoHAC contract allows call-offs to be made for engineering design and construction works for all Council services, without the need to tender. Given the very significant timescale pressures for delivery of Western Road Depot and the availability of appropriately procured contract arrangements for the type of works in question, new procurement has not been considered further.
The Cabinet report, which considered the procurement process for the LoHAC contract (18 June 2013 Cabinet, as detailed in Section 5 of the report) has demonstrated the contract is capable of delivering competitive pricing for a wide range of engineering works. As such, it can be assumed that call-off from the LoHAC contract schedule of rates, with the flexibility to negotiate additional discounts for fixed price work, will deliver competitive pricing. There would in addition be a saving from not having to run a fresh procurement.
As noted in paragraph 1.4 of the report, the price is subject to the completion of the final design. Due to the timescale pressure, the report recommends authority is delegated to the Director of Place and Sustainability to finalise the contract in a sum not exceeding £675k after consultation with the Cabinet Member for the Environment. In preparation for this stage, a due process will have been followed involving verification of the costing by the appointed Quantity Surveyor.
The use of the LoHAC contract has been agreed with NLWA officers who will ultimately be meeting the design and construction costs as part of their purchase of this site.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Draft Decision by Leader Minutes: 5 December 2013Minutes | 67 KB | DownloadRead as text |
PDF |
Minutes of Other BodiesMinutes | 109 KB | Download |
Follow Cabinet at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Nov 2026 | Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None | Decided | Open |
| 10 Nov 2026 | Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None | Decided | Open |
| 10 Nov 2026 | Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None | Decided | Open |
| 10 Nov 2026 | Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None | Decided | Open |
| 10 Nov 2026 | Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.