That the report and the progress being made against the Council’s 2013/14 budget in respect of revenue and capital expenditure (as set out in Appendices 1 and 2 of the report) be noted; That the budget changes (virements) set out in Appendix 3 of the report be approved; That the transfers to/from earmarked reserves of the following be approved; Ø £135k from reserves to match fund the European Social Fund programme (as detailed in paragraph 6.2 of the report) Ø £160k from reserves to fund 2013/14 commitments against the Jobs Fund (as detailed in paragraph 6.3 of the report) Alternative options considered The report proposes that the Cabinet should consider the overall financial position for 2013/14 in line with existing procedures. A risk-based approach to budget monitoring has been developed in order to manage the Council’s finances in a time of economic and financial uncertainty. At this stage of the financial year the Cabinet needs to understand clearly the projected outturn position and what, if any, action needs to be taken and so no alternative options have been considered at this time. Reasons for decision This report is mainly for noting the Council’s current forecast financial position. However, there are financial management decisions to be taken by Cabinet, in accordance with financial regulations, regarding the approval of transfers from/to reserves and relating to budget virements.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
Revenue 2013/14 - The aggregate revenue projected position in 2013/14 is shown in the following table.
Approved Budget Projected variation
£m £m Adults and Housing 98.554 0.00 Place & Sustainability 56.829 0.00 Public Health 18.268 0.00 Corporate Resources 0.133 0.00 Children and Young People 73.926 0.00 Strategy and Performance 0.522 0.00 Chief Executive (including Legal) 9.735 0.00 Non-service revenue 30.109 (4.00)
Total - General Fund 288.076 (4.00)
Total - Housing Revenue Account (12.473) 0.65 Appendix 2
Capital 2013/14 - The aggregate projected position in 2013/14 is shown in the following table.
Capital Scheme Approved Budget Spend to Date Projected Variance £m £m £m Place and Sustainability Directorate Transport for London 4.3 1.7 (0.9) Parking Plan 0.5 0.0 (0.2) Street Lighting 0.4 0.0 0.0 Road safety improvement 0.1 0.0 0.1 Borough roads and footways 5.9 4.2 0.0 Tottenham Hale Gyratory 0.3 0.3 0.0 Energy Saving Measures (Green Deal) 0.4 0.0 (0.2) Green Lanes 2.0 0.1 (1.3) Tottenham Regeneration 4.4 1.2 (1.8) Corporate Management of Property 0.9 0.5 0.0 Hornsey Town Hall redevelopment 1.1 0.2 (0.6) Accommodation/Smarter Working 6.8 6.1 0.0 Lordship Recreation Ground 0.2 0.1 0.3 Downlane Recreation Ground 0.4 0.0 (0.2) Leisure External Capital Works 3.5 0.7 (1.1) Other Schemes under £1m 1.3 0.3 0.0 Total - Place and Sustainability 32.4 15.5 (5.8) Children's Directorate BSF Schools Capital Programme 1.6 0.8 (0.2) ICT Managed Service Provider 0.6 0.4 (0.2) Primary Capital Programme 16.8 9.1 (3.1) Early Years and Community Access 0.3 0.3 0.1 Planned Asset Maintenance 1.2 0.8 (0.1) Devolved Schools Capital 0.6 0.0 0.0 Carer Home Adaptations 0.2 0.0 (0.1) Total - Children's 21.1 11.3 (3.6) Adults and Housing Directorate Adults Disabled Facilities Grant - Agency 1.1 0.7 (0.4) Housing Aids and Adaptations 1.6 1.0 0.4 Multiple Client Group Schemes 0.8 0.3 0.0 CPO's 0.5 (0.4) 0.0 Private Sector Housing Activities 0.0 0.1 0.0 Lease Enfranchisement 0.0 (0.1) 0.0 Total - Adults 4.0 1.5 0.0 HRA Housing Estate Improvement 0.8 0.2 0.0 Structural Works 0.2 0.2 (0.0) Extensive Void Works 0.3 0.0 (0.2) Boiler Replacement 4.0 2.5 0.0 Capitalised Repairs 4.4 2.0 (0.4) Lift Improvements 2.0 0.8 (0.1) Decent Homes 15.9 7.2 0.6 Major works conversions 0.3 0.0 0.0 Mechanical and Electrical Works 0.7 0.3 0.1 Professional Fees 1.7 1.2 0.0 Affordable housing projects 2.5 0.1 (2.1) Other Schemes 1.0 0.6 (0.2) Total – HRA 33.8 15.1 (2.3) Corporate Resources Directorate IT Capital Programme 0.9 0.2 (0.2) Infrastructure Programme 0.4 0.4 0.0 Customer Services 0.6 0.0 0.0 ERP Replacement – One SAP 2.7 0.1 0.0 Alexandra Palace 1.7 0.0 0.0 Evergreening 0.2 0.1 0.0 Total - Corporate Resources 6.4 0.7 (0.2) Total – Haringey Capital Programme 97.8 44.2 (11.9) Proposed virements are set out in the following table. Appendix 3
Virements Period Service Rev/ Cap Amount Full year Reason for budget changes Description current year Amount (£’000) (£’000) 12 HRA Rev Income Budget reduction Reduction of the HRA rent budget to account on a 365 day rather than 53 week basis 1,366 reduction equivalent to 6 days rent. 12 HRA Rev Income Budget reduction Reduction of the HRA service chargeincome budget to account on a 365 day rather than 164 53 week basis reduction equivalent to 6 days charges. 12 CYPS Rev 1,189 1,189 Budget restructure Transfer of historic premature retirement commitments to Non Service Revenue.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.