Resolved
RESOLVED to note the report.
Corporate Committee noted this item on Thursday 26 June 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to note the report.
Grant certification work plan for the London Borough of Haringey
Year ended 31 March 2014 June 2014
Paul Dossett Partner T +44 (0)207 728 3180 E [email removed]
Paul Jacklin Manager T +44 (0)207 728 3263 E [email removed]
Richard Bennett Audit Executive T +44 (0)207 728 3241 E [email removed]
© 2014 Grant Thornton UK LLP | Certification work plan | Contents Section Page
1. Our approach to grant certification work 3 Appendix A Summary of expected claims and returns for the year ended 31 March 2014 7
© 2014 Grant Thornton UK LLP | Certification work plan | 2 Our approach to grant certification work
Introduction Various grant-paying bodies require external certification of claims for grant or • for claims and returns over £500,000, we are required to assess the control subsidy and returns of financial information. environment for the preparation of the claim or return and decide whether or not to place reliance on it. Where reliance is placed on the control The Audit Commission makes certification arrangements with grant-paying bodies, environment, we are required to undertake limited tests to agree entries on including confirming which claims and returns require certification and issuing the claim or return to underlying records but not to undertake any testing of certification instructions. These instructions are tailored to each scheme and set the eligibility of expenditure or data. Where reliance is not placed on the out the specific procedures to be applied in examining the claim or return. The control environment, we are required to undertake all the tests in the Audit Commission agrees the deadline for submission of each claim by authorities relevant certification instruction and use our assessment of the control and the deadline for certification by auditors. environment to inform decisions on the level of testing required.
As the Council's appointed external auditor, we undertake grant certification work In determining whether we place reliance on the control environment, we acting as an agent of the Audit Commission. consider other work we have undertaken on the Council's financial ledger and any other relevant systems, and make appropriate use of relevant internal audit Certification arrangements work where possible. The Audit Commission's certification arrangements are designed to be proportionate to the claim or return. The arrangements for 2013-14 are:
• for claims and returns below £125,000, certification by us is not required, regardless of any statutory certification requirement or any certification requirement set out in grant terms and conditions • for claims and returns above £125,000 and below £500,000, we are required to perform limited tests to agree entries on the claim or return to underlying records, but are not required to undertake any testing of the eligibility of expenditure or data
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
6. LBH Certification work plan 2013-14 finalMinutes | 148 KB | DownloadRead as text |
PDF |
Progress Report and the Audit Certification PlanMinutes | 140 KB | Download |
Follow Corporate Committee at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Feb 2023 | Filming at meetingsThat Councillor Charles Adje be elected Chair for the meeting. The Chair referred to the notice of filming at meeting... | Noted | Open |
| 2 Feb 2023 | MINUTESTo confirm and sign the minutes of the Corporate Committee meeting held on 15 November 2022 as a correct record. The ... | Decided | Open |
| 2 Feb 2023 | Polling districts and polling places reviewTo approve the polling scheme describing the polling districts and the polling places for the London Borough of Harin... | Approved | Open |
| 2 Feb 2023 | Treasury strategyTo agree the proposed updated Treasury Management Strategy Statement for 2023/24 and recommend to the Full Council fo... | Agreed | Open |
| 2 Feb 2023 | 2020/21 audit progress reportThat the presentation be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.