Alexandra Park and Palace Joint Advisory & Consultative Committee agreed this item on Tuesday 8 July 2014. Below is the council's own wording, with the papers it was decided on.
i) That the new position of the proposed climbing frame associated with the Little Dinosaurs Playgroup, as shown on the tabled site plan, was acceptable to the Joint Committee. ii) That in regard to the ‘Go Ape’ adventure course the Joint-Committee agree ... view the full minutes text for item 6.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
Report to Alexandra Park and Palace Joint Advisory & Consultative Committee
Recommendations
2.1That the SAC and CC Board express views and advise the main Board on these matters as appropriate, in particular on the Park Development Activities set out in Section 9.
Report Authorised by: Duncan Wilson, Chief Executive Alexandra Palace and Park
Contact Officer: Duncan Wilson, Chief Executive Alexandra Palace and Park
3. Executive Summary 3.1 HLF Project Progress 3.2 Fabric Conservation 3.3 Park Update 3.4 Update from Regeneration Working Group (RWG)
4. Reasons for any change in policy or for new policy development (if applicable) 4.1 N/A
5. Local Government (Access to Information) Act 1985 5.1 N/A
6. HLF Project Progress
Key Stakeholder Relationships
6.1Following discussions, it has been agreed that AP’s relationship with the BBC now needs to be formalised by way of a Memorandum of Understanding due to the extent of interrelationship between the HLF project and the BBC. This is being progressed currently with senior staff within the BBC. 6.2 Relationships with other key stakeholders such as the Science Museum Group (including National Media Museum) and the BFI remain positive. At this stage these relationships do not require formalisation, but this does not rule out the possibility and/or need to do so in the future.
Design and Consultation
6.3A number of surveys and investigative works - essential to fill gaps in existing available data and knowledge - have been procured, completed and/or are underway. The outputs have been used and will continue to be used to guide design development and associated cost testing over the next few months.
6.4The design is currently at the end of RIBA workstage 2 - concept design (previously known as RIBA Stage C). A full presentation on the current iteration of the design of the HLF project will be given at the meeting under a separate agenda item.
HLF Professional Team
6.5The final two appointments to the professional team have now been made:-
i) Tricolor has been appointed as the external experts to assist the AP Community & Learning team and Barker Langham with the delivery of the required Activity Plan.
ii) James White from the British Film Institute (BFI) has been appointed to lead the delivery of a Collections Management strategy and plan
The work programme for each of these appointments has been dove-tailed into the existing HLF project programme.
HLF Project Programme
The key milestones within the HLF programme are as follows:-
up to July 2014 development & testing of design (incl formal HLF Stage C review) consultation and preparation of Activity Plan
up to Sept 2014 stakeholder consultation on design NB. where possible consultation on the design and the activity plan will be delivered together
late-Sept 2014 2-week statutory public consultation (req’d for planning application) completion of RIBA Stage D design; formal Board sign-off; submission Nov 2014 of Planning / Listed Building / Conservation Area applications Dec 2014 submission of Round 2 HLF funding application decisions on Planning / Listed Building / Conservation Area March 2015 applications
March/April 2015 HLF Stage 2 funding decision (NB. decision on consents req’d before HLF decision can be made)
technical design & tender package production (part 1) spring 2015 contractor OJEU procurement part 1 (pre-qualification) technical design & tender package production (part 2) spring – autumn 2015 final contractor OJEU procurement & appointment winter 2015 construction commences onsite autumn 2017 construction complete
7. Fabric Conservation
Surveyor to the Fabric
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Alexandra Park and Palace Joint Advisory & Consultative Committee at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.