That the original decision, made by Cabinet on 14 October 2008 that Apex House N15 is surplus to service requirements, be re-confirmed; That it be noted that the Customer Service Centre at Apex House could be moved to Tottenham Green and that a report on this would be presented to Cabinet in due course; That approval be given to the appropriation of the Apex House site for planning purposes pursuant to Section 122 Local Government Act 1972 and subject to the powers provided by Section 237 Town and Country Planning Act 1990 for the reasons outlined in paragraphs 5.15-5.24 of the report; That approval be given to sell, pursuant to Section 233 Town and Country Planning Act 1990, a long leasehold interest in Apex House, N15 to a wholly owned subsidiary of Grainger plc (to be incorporated prior to exchange of contracts) based on the Heads of Terms set out in the exempt Appendix 3 to the report and authorises the Assistant Director Corporate Property and Major Projects to approve the detailed terms and conditions of sale (consistent with the terms set out in the exempt Appendix 3 to this report) after consultation with the Assistant Director of Corporate Governance and the Cabinet Member for Housing and Regeneration ; That approval ... view the full minutes text for item 684.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
Seven Sisters Regeneration, Tottenham – Apex House & Wards Title: Corner
Report Lyn Garner - Director of Regeneration, Planning & Development Authorised by:
Malcolm Smith – Interim Director, Tottenham Regeneration Lead Officers: Programme Jon McGrath – Assistant Director, Property and Capital Projects
Ward(s) affected: Tottenham Green & Report for Key Decision Seven Sisters
1. Issue under consideration
1.1The Tottenham Strategic Regeneration Framework approved by Cabinet in March 2014 confirms that Seven Sisters is a key part of the regeneration vision. Two sites are key within Seven Sisters – Apex House (edged with a pecked black line on the plan in Appendix 1) and Wards Corner (edged with a solid black line on the same plan). Sitting adjacent to and above Seven Sisters Station, the redevelopment of these two sites will play a major part in transforming this important part of Tottenham with new retail space, new homes and improved public realm.
1.2This report recommends approval to the next steps in securing the necessary investment in both sites to realise the regeneration potential.
1.3In summary, these are to: a) declare Apex House as surplus to the Council’s service requirements; b) move the Customer Service Centre (currently in Apex House) to Tottenham Green (subject to a future detailed report); c) appropriate the Apex House site for planning purposes to support its redevelopment & regeneration potential; d) promote the co-ordinated development of the Apex House and Wards Corner sites by disposing of a long lease in the Council’s Apex House site to a wholly owned subsidiary company of Grainger plc (the developer of Wards Corner);
Page 1 of 17 Final: 5 July 2014 e) agree ‘in principle’ the use of the Council’s compulsory purchase powers, if required, to complete land assembly for the Wards Corner development; f) discuss with stallholders the possibility of a redeveloped Apex House site providing a relocation site for the Wards Corner market just yards from its current position; and g) approve changes to the 2007 Development Agreement with Grainger (Seven Sisters) Ltd. for the Wards Corner development.
2. Introduction by the Cabinet Member for Housing & Regeneration
2.1Seven Sisters forms a key part of the Tottenham Regeneration Programme. At the area’s heart, the Wards Corner and Apex House sites (at the junction of High Road with Seven Sisters & West Green Roads and next to Seven Sisters Underground Station - with the possibility of a Crossrail 2 connection in years to come), provide the opportunity for major new investment to improve the area and act as a catalyst for further transformational investment in surrounding sites.
2.2Our 2012 Strategic Property Review has shown that Apex House is no longer needed for service delivery. Improved services can be delivered by creating a new Customer Service Centre at Tottenham Green. Selling Apex House will reduce the impact on residents of public sector funding cuts by leveraging this asset to generate funds that will contribute to achieving Council priorities and act as a catalyst for regeneration.
2.3The disposal accords with the Council’s Corporate Asset Policy. It will release latent value, reduce running costs and generate a capital receipt that can support the capital programme and wider Council priorities including regeneration of the area.
2.4Crucially, too, the recommended sale of Apex House to Grainger is consistent with the delivery of the residential-led Wards Corner scheme (for which planning permission has been granted) – though, with land still to be acquired, it is unlikely that construction at Wards Corner will be able to start before 2017. By selling the site to Grainger, Apex House, on the other hand, could be redeveloped much sooner (subject to planning permission) so we can start to see the area’s transformation in line with our regeneration vision.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.