RESOLVED : That the Committee note the amendment to the value of the Heywood Contract which had increased by £14,288 to £244,046 for a period of three years, with the option to extend for a further two years, to Heywood for the provision of a managed service, including support, maintenance, and required upgrade.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
That the Pension Committee note the amendment to the value of the Heywood Contract which has increased by £14,288 to £244,046 for a period of three years with the option to extend for a further two years to Heywood for the provision of a managed service, including support, maintenance, and required upgrade.
Alternative options considered
4.1It is not feasible to consider alternative options as this matter arose following a contract award.
5. Background information
5.1At its meeting on 26th November 2013, the Corporate Committee approved the contract award for a new Local Government Pension Scheme (LGPS) IT system called Altair. The costs of the contract provided in the report were an estimate of costs.
5.2Following further discussions with the supplier the final costs were slightly higher than those reported to Committee so on 2nd April 2014 the Chair, acting under delegated authority, approved the revised contract costs. A copy of the record of delegated authority is appended.
6 Costs
The additional costs are £14,288 giving a total contract price for a 3+2 year contract of £244,046
7 Comments of the Chief Finance Officer and financial implications
7.1The Chief Finance Officer has been consulted over the contents of the report and confirms that the annual and one-off costs can legitimately be charged against the pension fund.
7.2The proposed costs of both the standard and fixed term contract are both higher than the existing contract however, given that the current system will fall out of life in December 14, coupled with the fact that the new system must be compliant with the new LGPS regulations leave few options.
7.3The report highlights that there is currently little competition in this field so significant time and effort could be undertaken for potentially little realistic chance of driving out further value.
7.4It is expected that internal effort to migrate onto this new system can be managed within existing resources.
7.5Members will be aware that there is current interest around creating larger pension schemes covering more than one authority. At this stage, there are not clear decisions and it is unlikely that anything tangible will have been concluded before the end of the proposed 3 year contract period. As such, it appears that overall the benefits of a reduced annual fee and one-off costs outweigh the disadvantages of being tied into a longer term contract.
8 Comments of the Assistant Director of Corporate Governance and legal implications
8.1The Assistant Director of Corporate Governance notes the contents of the report.
8.2Approval was obtained at Corporate Committee on 26 November 2013 for award of the contract to Heywood for an IT system to enable the Council to administer the Local Government Pension Scheme. The Council procured the contract using the negotiated procedure without publication of a notice, a process allowed for under the Public Contracts Regulations 2006 (as amended).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.