Item748
Resolved
That approval be given to an award of contract for lift replacement works to Express Lifts Alliance (in the ward for St Ann’s, Bounds Green, Noel Park, Northumberland Park and Woodside) for the tender sum of £1,388,954.64 in accordance with Contract Standing Order 9.06.1 c; and That approval be given to the issuing of a letter of intent for up to 10% of the contract value to enable pre-construction processes to take place in accordance with Contract Standing Order 9.07.03. Alternative options considered The alternative option to full replacement is to refurbish lifts/ However, this option has been rejected on the grounds that it could lead to increasing maintenance costs, increased risk of breakdowns and health and safety concerns in relation to the lifts being out of service for long periods. Reasons for decision A decision is required to enable the approval of the contract to replace lifts in the areas outlined in the report.
Word for word from the decision Haringey published for this meeting.
Source: www.minutes.haringey.gov.uk