Resolved
RESOLVED to note report.
Alexandra Park and Palace Joint Advisory & Consultative Committee noted this item on Tuesday 9 June 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to note report.
Informal Joint Meeting of the Alexandra Park & Palace Statutory Advisory Committee and Consultative Committee On 9th June 2015
Report Title: Regeneration Report including HLF Update
Report of: Tot Brill, Interim Regeneration Director
1. Purpose 1.1 To inform members of the Statutory Advisory Committee and the Consultative Committee on matters relating to Regeneration, HLF and Fundraising
2. Recommendations 2.1 That the SAC and CC notes the contents of this report.
Report Authorised by: Emma L Dagnes, Interim Chief Executive Alexandra Palace and Park
Contact Officer: Tot Brill; Interim Regeneration Director, Alexandra Palace and Park Contact Telephone np 0208 365 4316
3. Executive Summary 3.1 The report sets out the current build timetable for the HLF project, alerts members of the committees to other potential regeneration opportunities and informs members of the committees to the progress and plans of the fundraising campaign.
4. Reasons for any change in policy or for new policy development (if applicable) 4.1 N/A
5. Local Government (Access to Information) Act 1985 5.1 N/A 6. Background
6.1The Reclaiming the People’s Palace project to restore the former BBC studios, the theatre and the East Court has been awarded £18.8m by the Heritage Lottery Fund (HLF). LB Haringey are providing a funding contribution of £6.8m. The Trust will raise a further £1.04m. We intend to be on site with enabling works in the autumn of this year. The main building contract will start in May 2016 and should complete by the end of autumn 2017.
7. Project Timetable
7.1Table One, below, sets out the project build timetable as of May 2015. Variations from the previously reported timetable are shown in bold. These are due, in main, to the change in procurement route. The timetable is, of course, subject to revision, and departures from the timetable will be reported to future meetings.
Table One Date Phase 1 Mid May 2015 HLF confirms in writing Permission to Proceed Phase 2 Jan – Mar 2015 Surveys
May 2015 Contractors’ Open Day Phase 2 Procurement May 2015 Expressions of Interest preparation May – July 2015 Tender documentation preparation June 2015 Deadline for return of Expressions of Interest June 2015 Shortlist June–September 2015 Clear BBC areas and theatre backstage July Issue Tender July - August Tender period End July Mid tender review August 2015 Tender analysis September 2015 Award of Contract Phase 2 Enabling works October Vacant possession October - November Contractor mobilisation 2015 November 2015 Enabling works start on site Jun 2016 – Sep 2017 Main works on site Phase 2 Main works Sep – Dec 2017 Handover Returned to APPCT Quarter 1 2018 Open to the public
7.2We hope to be able to carry out some further survey work in the theatre in September/October this year before the contractor takes possession of the site. We will be able to report verbally at this meeting on the HLF Permission to Proceed and the Contractor’s Open Day, which had not taken place at the time of writing this update. 7.3 We are currently in a period of preparation, aligning and refining budgets, running the Framework procurement process, archiving, triaging and moving documents and objects from the areas that will be taken over by the contractors in November, putting the communications strategy in place and preparing to launch the public fundraising campaign (see section 9 below).
8. Other Regeneration Projects
8.1As well as the immediate focus on the HLF Reclaiming the People’s Palace project the Regeneration team, in partnership with the London Borough of Haringey, continues to explore the opportunities opened by the possibility of a hotel on site at Alexandra Palace. There is much to understand and determine. Once we have a draft timetable, and a clear sense of the workable options we will return to this Advisory Committee for your views.
9. Fundraising
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
REGENERATION REPORTMinutes | 166 KB | DownloadRead as text |
Follow Alexandra Park and Palace Joint Advisory & Consultative Committee at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Apr 2023 | Minutes and matters arisingThat subject to the above change, the minutes of the meeting held on 9 March 2023 and 17 November 2022 be agreed and ... | Agreed | Open |
| 20 Apr 2023 | Powerpoint presentation on 2022/23 achievements and plans for 2023/24RESOLVED That the presentation be noted. | Noted | Open |
| 9 Mar 2023 | Minutes & matters arisingRESOLVED To approve the minutes of the Joint Meeting of the Advisory and Consultative Committees held on 17 November ... | Approved | Open |
| 9 Mar 2023 | Chief executive officer (ceo) updateThat the contents of the report be noted. | Noted | Open |
| 9 Mar 2023 | Go ape mini-land roversThat proposal by Go Ape for a new mini-Land Rover activity in Alexandra Park be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.