Tiverton Primary School Roof replacement Works

Decided Executive 1 paper

Cabinet decided this item on Tuesday 16 June 2015. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

RESOLVED i. To appoint Breyer Group Plc in the amount of £539,414.03 for a contract period of 16 weeks. This will allow for completion of the project by 23 rd November 2015. ii. To issue a letter of intent not exceeding 10% of the contract sum as allowed under CSO 9.07.3 whilst formal works contracts are being prepared. Alternative options considered The contractor was procured via the LHC (a not-for-profit consortium set up to provide effective procurement solutions for local authorities, housing associations, schools and other public sector bodies.) Flat Roofing (FR1) Framework Arrangement. We also considered use of Construction line, (a fully owned and managed by Capita, UK register of pre-qualified construction services database). However, upon consideration the LHC framework was considered to be more suitable for this size of project and it offered specialist flat roofing contractors, better suited to this type of project. Reason for Decisions The award the contract to Breyer Group Plc will facilitate the Council to undertake the roof replacement work at Tiverton Primary School. Award will enable the project to move forward to the construction stage within timescales that facilitate the need to address an urgent condition issue to mitigate any future disruption to school service delivery. It will also facilitate the start of the construction works during the school holidays to minimise disruption to the school during term time service delivery.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet

Recommendations

3.1The recommendation is to appoint Breyer Group Plc in the amount of £539,414.03 for a contract period of 16 weeks. This will allow for completion of the project by 23rd November 2015.

3.2To issue a letter of intent not exceeding 10% of the contract sum as allowed under CSO 9.07.3 whilst formal works contracts are being prepared.

Alternative options considered

4.1The contractor was procured via the LHC (a not-for-profit consortium set up to provide effective procurement solutions for local authorities, housing associations, schools and other public sector bodies.) Flat Roofing (FR1) Framework Arrangement. We also considered use of Construction line, (a fully owned and managed by Capita, UK register of pre-qualified construction services database). However, upon consideration the LHC framework was considered to be more suitable for this size of project and it offered specialist flat roofing contractors, better suited to this type of project.

Page 2 of 6 5. Background information

5.1The school is located in the Seven Sisters ward of the Borough and has approximately 450 pupils between the ages of 3-11 years. The school is comprised largely of single storey accommodation, with only a small amount of teaching area at first floor level. The construction is thought to date from circa 1960. External walls to most areas are of brick construction and the roof structure is comprised of wood wool slabs on timber and metal supporting sub-structure. Later additions are partly timber clad with profiled sheet pitch roofs.

5.2Notwithstanding various attempts at patch repair, the school continues to experience ongoing water penetration to a number of the original flat roof areas, including the girls toilet facilities and first floor classrooms, which impacts on daily operations and consumes valuable staff resource in containing the leaks to maintain a safe environment for continued use. At the planning stage review group meeting, the procurement of the

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Tiverton Primary School Roof replacement WorksMinutes 168 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 17 attended
AP
Anji PhillipsCouncil Staff, expected
AK
Angela KawaCouncil Staff, expected
CK
Councillor Claire KoberChair, present
JA
Councillor Jason ArthurCommittee Member, present
AD
Councillor Ali DemirciCommittee Member, present
JG
Councillor Joe GoldbergCommittee Member, present
SM
Councillor Stuart McNamaraCommittee Member, present
PM
Councillor Peter MortonCommittee Member, present
AS
Councillor Alan StricklandCommittee Member, present
BV
Councillor Bernice VanierCommittee Member, present
AW
Councillor Ann WatersCommittee Member, present
LG
Lyn GarnerOfficer, expected

All 17 on the meeting page

On this subject at Haringey

Search all
  1. Tiverton Primary School Roof replacement WorksThis decision
  2. Determination of the statutory notice proposing the closure of Tiverton Primary SchoolApproved
  3. Results of the non-statutory consultation on the options for the future of Stamford Hill Primary School and its possible amalgamation with Tiverton Primary SchoolAgreed

More from Haringey Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None Decided Open
10 Nov 2026 Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies