London Borough of Haringey
Cabinet Member Signing, Thursday 10 December 2015 at 12.00pm

Bounds Green Primary School - 3 Form of Entry Reinstatement Project

Approved Executive 2 papers

Cabinet Member Signing approved this item on Thursday 10 December 2015. Below is the council's own wording, with the papers it was decided on.

Item119

Resolved

RESOLVED i) Provide approval to enter into contract with Lakehouse Contracts Ltd at the agreed contract value of £2,171,634.88 for a contract period of 38.5 weeks. ii) For the issuance of formal contracts based on the satisfactory completion of supporting Contractors Proposals. iii) Provide approval to instruct Haringey Council’s Legal Services to issue a Letter of Intent permitting orders to be raised by Lakehouse Contracts Ltd with their supply chain; up to and not exceeding 10% of the contract sum as allowed under CSP 9.07.3 whilst formal works contracts are being prepared.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing

Recommendations

3.1Provide approval to enter into contract with Lakehouse Contracts Ltd at the agreed contract value of £2,171,634.88 for a contract period of 38.5 weeks.

3.2For the issuance of formal contracts based on the satisfactory completion of supporting Contractors Proposals.

3.3Provide approval to instruct Haringey Council’s Legal Services to issue a Letter of Intent permitting orders to be raised by Lakehouse Contracts Ltd with their supply chain; up to and not exceeding 10% of the contract sum as allowed under CSO 9.07.3 whilst formal works contracts are being prepared.

Page 1 of 5 4. Reasons for decision

4.1To award a contract which will enable the timely mobilisation and construction of works to Bounds Green Primary School which, aims to support the Councils requirement for additional school places from September 2016.

Alternative options considered

5.1The proposed expansion of Bounds Green Primary School is expected to support additional cohorts from September 2016. A do nothing option would not support local demand for additional pupil places.

5.2The feasibility report considered 3 design options, with emphasis on flexibility, programme, impact on the school and financial viability. The Cabinet Report presented in July 2015 outlined reasons for discounting options 1 and 3 and the Councils preference to proceed based on design option 2.

5.5A Pre Construction Services Agreement was awarded by Cabinet Committee in July 2015. It would not be beneficial in terms of time and cost to initiate a new tender exercise.

6. Background information

6.1The principle of expanding Bounds Green Primary School was agreed by Cabinet Committee in March 2015 based on previous school roll projections that showed a borough wide deficit of reception places from 2015.

6.2Based on a two stage Design and Build procurement exercise, the stage one tender process concluded with an award by Cabinet Committee in July 2015 for the issuance of a Pre Construction Services Agreement to Lakehouse Contracts Ltd.

6.3This award was based on a Pre Construction Services Agreement contract sum of £53,760.82 and a stage two tender target price of £2,167,693.71.

6.4The second stage tender exercise aimed to develop initial design proposals and undertaken open book tendering on work packages which would conclude with an agreed contract sum.

6.5A stage two tender price of £2,171,634.88 was received from Lakehouse Contracts Ltd on 3rd November 2015.

6.6Sweett Group completed a mathematical check of the Stage 2 tender which was found to be correct.

6.7When comparing the Pre-Tender Estimate with the Stage 2 tender, it can be seen that whilst there are obvious significant differences between some individual items, the difference between the two totals is in the region of 3%, which shows the two figures to be very close. The value of the pre tender estimated was noted in the July 2015 Cabinet Committee Report, Pre Construction Agreement Section 3.0 Exempt Information.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Bounds Green Primary School: 3 Form of Entry Reinstatement ProjectMinutes 193 KB DownloadRead as text
PDF
Signed EQIA: Bounds Green: 10th DecemberMinutes 1.4 MB Download

At this meeting

Whole meeting
119Bounds Green Primary School - 3 Form of Entry Reinstatement ProjectThis decision

Who was there

1 of 4 attended
CB
Claire BarnesOfficer, in attendance
JM
Jon McGrathOfficer, in attendance
PS
Philip SlawtherSecretary, expected
AW
Councillor Ann WatersChair, present

On this subject at Haringey

Search all
  1. Bounds Green Primary School - 3 Form of Entry Reinstatement ProjectThis decision
  2. Review of Bounds Green Low Traffic Neighbourhood trialApproved
  3. Approve extension (and variation where it applies) of the Bounds Green, Bruce Grove, Harringay, Noel Park, Northumberland Park, Seven Sisters, St Anns, Tottenham Green, Tottenham Hale, West Green and Woodside Wards Alcohol Control PSPO'sDecided
  4. Ratification of the decision to go out to consultation on the extension of the Bounds Green Alcohol Control PSPONoted
  5. Proposed Cycling Improvements along Bounds Green Road N22Approved
  6. Bounds Green Low Traffic NeighbourhoodApproved

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies