RESOLVED I. That the Cabinet Member approves the award of the contract to AJS Ltd for the electrical and security works for the sum of £700,055 and contract period of 30 weeks. II. That the Cabinet Member approves the total professional fees of £60,569, which represents 8.652% of the contract sum. That the total project cost of £760,624 be noted. III. That the Cabinet Member authorises Haringey’s Legal Department to issue a letter of Intent up to and not exceeding 10% of the contract sum as allowed under the Council’s CSO 9.07.3. REASONS FOR DECISION Approval of the successful competitive tendered scheme was required to allow the contract to be awarded and the planned replacement door entry system and electrical works, which include renewal of communal doors/door entry systems, CCTV, landlord electrical services and adaptation to the concierge offices at Northolt and Stapleford, to start. The existing door entry system within this programme has reached the end of its useful life and replacement parts are obsolete. The existing door entry system is not operational at present. ALTERNATIVE OPTIONS CONSIDERED The alternative option to full replacement was to refurbish. However, the system was obsolete and parts were no longer accessible. This has caused increased maintenance costs and an increase in anti social behaviour in the blocks.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
3.1That the Cabinet Member approves the award of the contract to AJS Ltd for the electrical and security works for the sum of £700,055 and contract period of 30 weeks.
3.2That the Cabinet Member approves the total professional fees of £60,569, which represents 8.652% of the contract sum. That the total project cost of £760,624 be noted.
3.3That the Cabinet Member authorises Haringey‟s Legal Department to issue a letter of Intent up to and not exceeding 10% of the contract sum as allowed under the Council‟s CSO 9.07.3.
Reasons for decision
4.1Approval of the successful competitive tendered scheme is required to allow the contract to be awarded and the planned replacement door entry system and electrical works, which include renewal of communal doors/door entry systems,
Page 1 of 7 CCTV, landlord electrical services and adaptation to the concierge offices at Northolt and Stapleford, to start.
4.2The existing door entry system within this programme have reached the end of their useful life and replacement parts are obsolete. The existing door entry system is not operational at present.
Alternative options considered
5.1The alternative option to full replacement is to refurbish. However, the system is obsolete and parts are no longer accessible. This has led to increased maintenance costs and an increase in anti social behaviour in the blocks.
6. Background information
6.1This package of works consists of 190 properties in Northolt (1 – 102) and Stapleford (1 – 88) on the Broadwater Farm Estate within the South Tottenham area.
6.2The project details are as follows:
Number of dwellings in project: 190 Total construction costs: £700,055 Anticipated contract start on site: October 2016 Anticipated contract completion: February 2017 Contract duration: 30 weeks Contractor: AJS Ltd
Proposed Work
6.3The scope of the work includes the renewal of the CCTV cameras and system, adaptations to the concierge suite, entry phone replacement, entrance doors renewal and landlord lighting to the above blocks.
Consultation
6.4Residents and stakeholders have been advised about the scheme in writing and a „drop in‟ consultation meeting was held at the Broadwater Farm Community Centre on 8 June 2016 for residents and key stakeholders. Further consultation will be undertaken by newsletters.
Tender
6.5Competitive E-tenders were invited from five firms from Constructionline (a fully owned and managed by Capita, UK register of pre-qualified construction services database). via the Haringey Council Construction Procurement Group.
6.6Only three (3) contractors returned their tender and their tenders are listed below in Appendix A.
Page 2 of 7 6.7 The successful contractor, AJS Limited, submitted a tender on on 8 January 2016, they are willing to keep their offer open until 8 October 2016.
6.8The pre-tender estimate prepared by the Electrical Engineers in June 2015 was £800,000. The difference between the pre-tender estimate and the £700, 055 lowest tender received is £99,945, which is within 12.49% of the pre tender estimate. This variance is considered to be acceptable for the proposed works overall in spite of the vagaries of the market.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.