Agreed details of the collision map are provided in writing and details on how the injuries will be reduced. RESOLVED 1. To approve the Annual Spending Submission for 2017/18 as set out in Appendix 2 of this report. 2. To note the progress to date on delivering against our LIP and Corporate Plan targets. Reasons for decision The LIP submission provides a major source of funding to deliver transport projects and programmes. Alternative options considered The Annual Spending Submission supports our approved LIP covering 2011 to 2031. It is, therefore, not considered necessary to consider other options.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
Title: Local Implementation Plan Annual Spending Submission for Transport 2017/18
Report authorised by: Lyn Garner, Director of Regeneration, Planning and Development
Lead Officer: Malcolm Smith, Team Manager, Transportation Planning
Ward(s) affected: ALL
Report for Key/ Non Key Decision: N/A
1. Describe the issue under consideration
1.1Investment in transport infrastructure is a key part of the Council’s Corporate Plan to support economic growth and improve the health and wellbeing of our residents and businesses.
1.2The Council is legally required to prepare a Local Implementation Plan (LIP) containing proposals for the delivery of the Mayors Transport Strategy (MTS). Haringey’s second Local Implementation Plan was adopted in 2010 and set out the proposed transport strategy and projects for the period 2011-2031. It also included a detailed set of delivery proposals for the period 2011-2014.
1.3The Local Implementation Plan [LIP] therefore represents a significant annual investment programme that specifically supports Priority 3 and Priority 4 of the Corporate Plan. Details of the linkage between the LIP and Corporate Plan are shown in Appendix 3. TfL give Boroughs the opportunity to bid for money annually to deliver projects in their LIP. In September 2013 the Council approved an outline three year Delivery Plan for the period 2014/15 to 2016/17. Progress on the projects agreed in 2013 is provided in appendix 1.
1.4The plan covers both physical renewal and improvement of the Borough’s transport infrastructure alongside softer measures to promote behaviour change and engage with wider safety, health and environmental objectives including air quality through support for more walking and cycling. The full detail of the submission can be found in Appendix 2.
1.5Generally TfL produce guidance setting out their funding priorities. However given that there is now a new Mayor guidance for 2017/18 has been issued as interim Page 1 of 22 LIP annual spending submission guidance for 2017/18. This is in essence unchanged from that issued for 2016/17. TfL advise boroughs to submit their spending submission for 2017/18 on the assumption that funding is at the same level as 2016/17 but boroughs should prioritise their projects and programmes in the event less funding is made available. In this instance we would prioritise based on meeting our road safety, walking and cycling targets. It is likely that LIP guidance will also be interim for 2018/19 due to the time required for preparation and approval of the Mayor’s Transport Strategy [MTS]. All boroughs will be required to prepare a 3rd LIP which will need to reflect the new Mayor’s Transport Strategy. As shown below TfL has indicated guidance for boroughs will be issued in October 2017 which will spell out the requirements for boroughs.
1.6TfL usefully provide a summary of the expected MTS/LIP activity over the next two years as below:
Milestone Date TfL issues high level LIP ASS guidance for 2017/18 June 2016 “Towards….” Mayoral direction of travel document published September 2016 Boroughs submit 2017/18 LIP ASS October 2016 Draft Mayor’s Transport Strategy published, alongside: March 2017 - TfL Business Plan - Mayor’s Environment Strategy - Mayor’s Economic Development Strategy - Mayor’s Housing Strategy TfL issues draft LIP3 guidance to the boroughs TfL issues 2018/19 ASS guidance [if appropriate] May 2017 Draft London Plan published July 2017 Final MTS published October 2017 Final LIP3 guidance published Boroughs submit 2018/19 LIP ASS Boroughs begin preparing LIP3 documents November 2017 Borough elections – until the outcomes are known TfL May 2018 acknowledges boroughs may be reluctant to engage fully with the LIP 3 process
1.7As we are expected to prepare a new LIP the funding submission for 2017/18 is an interim submission with no requirement for a new three year Delivery Plan for 2017/18 onwards.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.