RESOLVED I. That the validation list be updated, as set out in appendix 1 of the report, to bring it in line with current Local and London Plan Policies. II. That that consultation should take place from 21 November 2016 -16 January 2017. III. That following the consultation, the comments will be summarised and analysed. Officers will consider all comments and where relevant, appropriate make amendments to the validation checklist to reflect these comments. A summary of responses and any changes will be presented to the Cabinet Member for final sign off. Reasons for decision Updating the validation list is essential to ensure that all the necessary information is submitted with planning applications so that the LPA can consider applications in an efficient and consistent way while ensuring policy compliant developments. Alternative options considered No other options were considered because there is an obligation to have up to date validation list.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
LOCAL REQUIREMENTS FOR INFORMATION TO BE SUBMITTED WITH PLANNING APPLICATIONS
Context
The Town and Country Planning (Development Management Procedure) (England) Order 2015 requires that unless there is a list of information requirements published within the last two years of the date of submission of the application, the local planning authority cannot require information as part of its validation process. The information below and on attached links shows what we will expect all applicants to submit the following information to be submitted.
The current statutory national requirements for all applications are:
1. Standard application form (three copies plus original unless submitted electronically) 2. Location plan on an up to date map at an identified standard metric scale (typically 1:1250 or 1:2500 to fit onto A4 or A3 paper) with the red line including all land necessary to carry out the proposed development and blue line for any other land owned by the applicant 3. Site plan – direction of North, proposed development in relation to the site boundaries with written dimensions (and public rights of way, trees, hard surfacing and boundary treatment where relevant) typically 1:500 or 1:200 4. Ownership certificate and notices 5. Agricultural land declaration 6. Fee 7. Design and access statement - where required by law in accordance with the Town and Country Planning (General Development Procedure) Order (England) 2015) and The Planning (Listed Buildings and Conservation Areas) Regulations 1990 (as amended)
Asdefined by Article 9. of the Town and Country Planning ( Development Management Procedure)Order 2015 Design and Access Statements are required for the following planning applications:
Major developments ( those which involve the creation of 10 or more residential units; residential development of on a site of 0.5 hectares or more; development on a site of at least 1 hectare; or the provision of a building or buildings where the floor space to be created by the development is 1,000 square metres or more;). Proposals where any part of the development is in a Conservation Area and consists of— o the provision of one or more dwellinghouses; or 1
June 2016 o the provision of a building or buildings where the floor space created by the development is 100 square metres or more.
A design and access statement shall— (a) explain the design principles and concepts that have been applied to the development; (b) demonstrate the steps taken to consider the context of the development and how the design of the development takes that context into account; (c) explain the policy adopted as to access, and how policies relating to access in relevant local development documents have been taken into account; (d) state what, if any, consultation has been undertaken on issues relating to access to the development and what account has been taken of the outcome of any such consultation; and (e) explain how any specific issues which might affect access to the development have been addressed
Further guidance can be found at http://www.planningportal.gov.uk/planning/applications/howtoapply/whattosubmit/designaccess
Design and Access statements are also requied with all applications for Listed Building Consent.
CIL
All developments generating a floorspace of more than 100 square metres or an additional residential unit are CIL liable and will be obliged to submit a ‗determining whether an application is CIL liable‘ form and plan or drawing showing any chargeable development and gross internal area in square metres on each plan.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.