Housing, Planning and Development Scrutiny Panel agreed this item on Tuesday 7 March 2017. Below is the council's own wording, with the papers it was decided on.
AGREED: (a) That the progress made in achieving the recommendations from the Community Infrastructure Levy Scrutiny Project, agreed by Cabinet on 17 May 2016, be noted. (b) That further information on the methodology used by BNP Paribas, to identify what Community Infrastructure Levy rates would be viable in Haringey, be circulated to Panel Members by the Assistant Director for Planning.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
Report to Housing, Planning and Development Scrutiny Panel
Report for: Housing and Regeneration Scrutiny Panel – 7th March 2017
Title: Community Infrastructure Levy – Governance Arrangements
Report authorised by: Emma Williamson Assistant Director – Planning
Lead Officer: Matthew Patterson, Head of Strategic Planning & Policy
Ward(s) affected: ALL
Report for Key/ Non Key Decision: N/A
1. Describe the issue under consideration 1.1 On 3rd December 2015, the Housing and Regeneration Scrutiny Panel (HRSP) conducted a review of the Haringey Community Infrastructure Levy, with a specific focus on governance arrangements needed to support allocation of receipts from the Community Infrastructure Levy to local neighbourhoods (the neighbourhood CIL). The panel conducted this review through a ‘scrutiny in a day’ format at a session with local stakeholders, including representatives from the development industry and members of the Highgate and Crouch End neighbourhood forums.
1.2This report provides an update on actions that were agreed by Cabinet on 17th May 2016 (attached at Appendix 1) in response to implementing the recommendations of the HRSP.
2. Recommendations 2.1 The Housing and Regeneration Scrutiny Panel is asked to note the progress made to date in achieving the recommendations agreed by Cabinet (attached at Appendix 1).
3. Reasons for decision 3.1 N/A
4. Alternative options considered 4.1 N/A
5. Background information 5.1 Haringey’s Community Infrastructure Levy (CIL) was introduced in November 2014. As at December 2015, the Council had collected almost £1.4m in CIL and had issued liability notices for £11.4m. By 2017/18, it is expected that CIL income will average around £2m per annum. Receipts from CIL are to be used to support wider community infrastructure needs in the locality of the new development.
5.2Whilst there is guidance to support the disbursement of funds from the strategic element of CIL income (approximately 80% of receipts), guidance for the distribution of
Page 1 of 12 the neighbourhood element (15%) is much less defined. The HRSP review of CIL was established to identify the principles and practices that the Council should consider for the governance and administration of the neighbourhood proportion of CIL. This included:
Assessing the national and local policy framework for the collection and allocation of CIL receipts: Assessing policy and practice at early CIL adopter London Boroughs to help identify good practice; Identifying key principles and practice that should underpin governance arrangements for distribution of neighbourhood element of the CIL, particularly in relation to how community infrastructure projects are identified, prioritised and authorised; Assessing what arrangements should be in place to further support the distribution of CIL receipts in areas where Neighbourhood Forums are present; Assessing how the allocation neighbourhood CIL receipts can maximise opportunities for improving local infrastructure through alignment with other funding programmes both internal and external to the Council.
5.3In responding to these objectives the panel collated evidence from a wide range of interests including: Local council officers (Planning, Finance) The Planning Officers Society Other local authorities Local Neighbourhood Forums A developer.
5.4On the evidence received, the panel made 13 recommendations, all of which were either agreed or partially agreed by Cabinet (see Appendix 1).
6. Update on recommendations
6.1Work has commenced on reviewing the Haringey CIL charging schedule in accordance with recommendation 1. A report to Cabinet (24th January 2017) presented viability evidence that supported only an increase in CIL rates in certain parts of the Borough, namely, Seven Sisters, St. Ann’s, West Green, Bruce Grove, Tottenham Green, and Tottenham Hale wards. A partial review of the CIL Charging Schedule has therefore been agreed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Housing, Planning and Development Scrutiny Panel at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.