RESOLVED That in accordance with Contract Standing Order 9.07.1(d) Cabinet approves the award of the contract for Phase 1 of the North Tottenham THI to Cuttle Construction Limited for the contract sum of £673,845. Reasons for decision To enable the implementation and completion of repair and restoration works as part of the THI. In accordance with the grant agreement between the Council and HLF and the approved programme, Phase 1 works are required to start in July 2017 and be completed by December 2017. Alternative options considered To not appoint a contractor would mean the terms of the grant agreement between the Council and HLF not being met and potentially result in the loss of external investment in North Tottenham of over £1,468,000 from HLF and £304,000 from local property owners. The HLF grant must be spent by March 2020.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
Title: North Tottenham Townscape Heritage Initiative - Appointment of Principal Contractor (Phase 1) Report authorised by: Lyn Garner, Director of Regeneration, Planning and Development
Lead Officer: Catherine Cavanagh, Project Officer, Tottenham Regeneration T x3648, E [email protected]
Ward(s) affected: Northumberland Park
Report for Key Decision
1. Describe the issue under consideration 1.1 This report seeks approval to enter into contract with the preferred bidder for Phase 1 of the North Tottenham Townscape Heritage Initiative (THI), Cuttle Construction Limited (Cuttle). As principal contractor, they would undertake conservation works to building elevations including the shopfronts at 791, 797- 805 (odd) and 816-822 (even) High Road and 1-7 White Hart Lane (odd). 1.2 The contract is to be awarded on the basis of the highest quality and best value for money. Cuttle’s tendered price was £673,845 for Phase 1 works lasting 25 weeks. 1.3 The THI is a £2.3m project to restore up to 28 historic buildings in North Tottenham funded by the Heritage Lottery Fund (HLF) £1.5m, Haringey Council £0.5m and property owners £0.3m. It aims to improve the appearance of the North Tottenham Conservation Area and encourage people to shop locally.
2. Cabinet Member Introduction 2.1 Tottenham High Road is home to some fantastic historic buildings and shopfronts. For too long though, some of this important local heritage has been unloved, or covered up and unseen. 2.2 I’m delighted that the Council, Heritage Lottery fund and property owners are investing £2.3m to restore up to 28 historic shopfronts. It’s been fascinating to chair the board overseeing this project and to work with officers, ward councillors and local residents to agree restoration plans. I’d like to thank the many local residents who have sent in old photographs of Tottenham High Street, which have been invaluable in helping us agree plans faithful to the original designs. 2.3 Following this work, I’m pleased to recommend, in this report, awarding the contract for Phase 1 of the improvements. 2.4 The North Tottenham Conservation Area is on Historic England’s At Risk register. Repair and restoration of historic properties will improve the physical
Page 1 of 21 appearance of the conservation area and contribute to the wider regeneration of the area. 2.5 The benefits of this project will go well beyond heritage improvements. We hope that this project will be important in: creating a better experience for visitors, residents and traders through improved shopfronts and buildings contributing positively to the environment and townscape of North Tottenham. providing better accommodation for traders and residents. encouraging awareness of its historical significance and greater participation in its management via a programme of heritage activities. bringing building facades up to an acceptable standard for a conservation area and to facilitate future planning and enforcement.
3. Recommendations 3.1 That in accordance with Contract Standing Order 9.07.1(d) Cabinet approves the award of the contract for Phase 1 of the North Tottenham THI to Cuttle Construction Limited for the contract sum of £673,845.
4. Reasons for decision 4.1 To enable the implementation and completion of repair and restoration works as part of the THI. In accordance with the grant agreement between the Council and HLF and the approved programme, Phase 1 works are required to start in July 2017 and be completed by December 2017.
5. Alternative options considered 5.1 To not appoint a contractor would mean the terms of the grant agreement between the Council and HLF not being met and potentially result in the loss of external investment in North Tottenham of over £1,468,000 from HLF and £304,000 from local property owners. The HLF grant must be spent by March 2020.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.