RESOLVED 1. To approve the award of a contract to Kind Diamond Build Consortium for construction works on the Muswell Hill Primary School in the contract sum of £696,103.45. 2. To approve the issuance of a Letter of Intent not exceeding £100,000 to allow the contractor to mobilise their resources whilst formal contracts are prepared and executed, ensuring the required start on site date can be met. Reasons for decision To award a contract which will enable the timely mobilisation and construction works to Muswell Hill Primary School which aims to address identified building condition issues. Alternative options considered A do nothing option was not considered appropriate. The construction works are required to address a number of identified issues within the existing buildings which will have a negative impact on educational provision, should they not be addressed. Four contractors were invited to tender and therefore considered to undertake the required construction works. The tenderers proposals were evaluated using a 60% quality and 40% price weighting and on this basis the recommended contractor is deemed to be the most economically advantageous tender representing the best value option to deliver the required works.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
3.1.2 Approve the award of a contract to Kind Diamond Build Consortium for construction works on the Muswell Hill Primary School in the contract sum of £696,103.45.
3.1.3 Approve the issuance of a Letter of Intent not exceeding £100,000 to allow the contractor to mobilise their resources whilst formal contracts are prepared and executed, ensuring the required start on site date can be met.
Page 1 of 6 4. Reasons for decision
4.1To award a contract which will enable the timely mobilisation and construction works to Muswell Hill Primary School which aims to address identified building condition issues.
Alternative options considered
5.1A do nothing option is not considered appropriate. The construction works are required to address a number of identified issues within the existing buildings which will have a negative impact on educational provision, should they not be addressed.
5.2Four contractors were invited to tender and therefore considered to undertake the required construction works. The tenderers proposals were evaluated using a 60% quality and 40% price weighting and on this basis the recommended contractor is deemed to be the most economically advantageous tender representing the best value option to deliver the required works.
6. Background information
6.1Muswell Hill Primary school is a 2 Form of Entry school located within the Muswell Hill ward of the London Borough of Haringey.
6.2Following a Council Review, Muswell Hill Primary School was identified as a priority case for condition improvement. As a result a comprehensive feasibility survey was undertaken to determine the full extent of the works required.
6.3The Feasibility report presented the proposed list of works to be undertaken as part of this project, these were explored in consultation with the Corporate Landlord, End User (School), Project Sponsor and Stakeholders to obtain the most appropriate solution in terms of brief and vision. The works were split into two distinct packages:
6.3.1 Phase 1 - works considered to be of highest priority relating to the fire alarm system, wifi and compliance works to the gas system within the kitchen. These works were completed over the 2016 school summer holidays.
6.3.2 Phase 2 – The main body of works which addresses the remaining condition works throughout the building during the design stages deemed to be of a lesser priority than phase 1, the works relate predominately to the installation of new lighting and mechanical systems throughout the school. These proposed works are to be undertaken over the summer term and holidays in 2017.
6.4This report relates to contract award for a construction contractor to undertake the phase two works package.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.