Resolved
RESOLVED 1. To approve the procurement strategy endorsed by the SD Management Board for the procurement of data centre services through a third party supplier via a framework agreement; and, 2. To award a contract for the provision of data centre services to Crown Hosting Data Centre Limited. 3. That the Chief Digital and Information Officer provide a report to the Shared Digital Management Board once the final contract value has been ascertained setting out the year on year savings. 4. To note that the five year total contract value will be in the region of £4.5m, apportioned across all three councils based on services that each council consume and the final contract cost to be confirmed once the actual level of provision and data migration has been confirmed . Reasons for decision The councils each have in-house provision for data centres currently. There are issues with maintaining the hardware for the data centres with hardware coming to end of life, and needing replaced. These costs are duplicated across all three councils and can be reduced through consolidating data centre provision. By moving to third party provision of data centres, the councils can expect to see a drop in cost of service based on the 2015/16 operating costs of approximately £400,000 per year whilst improving business continuity through improved resilience and better disaster recovery. The savings will be realised through a reduction in the number of staff required to manage the service, which will be subject to consultation and also lower hosting costs as the councils will only pay for services used. By co-locating services, and moving to a new data centre provider will reduce the councils’ environmental impact. Existing hardware is end of life, consumes more power, and emits more heat. Using new data centre technology the power consumption and levels of heat emitted will be reduced. Additionally, a standard set of facilities across all three councils would enable better control of each data centre’s set-up and design. This is particularly relevant when considering the security design, ensuring that the councils can keep up to date with new security requirements, building on the recent penetration testing ... view the full minutes text for item 101.