London Borough of Haringey
Housing, Planning and Development Scrutiny Panel, Monday 2 October 2017 at 6.30pm

Minutes - 22 June 2017

Agreed Planning 1 paper

Housing, Planning and Development Scrutiny Panel agreed this item on Monday 2 October 2017. Below is the council's own wording, with the papers it was decided on.

Item21

Resolved

AGREED: That the minutes of the meeting held on 22 June 2017 be approved as a correct record.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Housing, Planning and Development Scrutiny Panel

MINUTES OF THE MEETING OF THE HOUSING AND REGENERATION SCRUTINY PANEL HELD ON THURSDAY, 22ND JUNE, 2017, 6.30 - 8.45 pm Present: Councillors: Emine Ibrahim (Chair), Zena Brabazon, Gail Engert, Martin Newton and Ann Waters

Also Present: Councillors: Vincent Carroll, Clive Carter, and Alan Strickland

1. FILMING AT MEETINGS

The Chair referred Members present to agenda Item 1 as shown on the agenda in respect of filming at this meeting, and Members noted the information contained therein’.

2. APOLOGIES FOR ABSENCE

It was noted that apologies for absence had been received from Cllr John Bevan and Cllr Jennifer Mann.

3. URGENT BUSINESS

In response to the Grenfell Tower tragedy the Chair informed the Panel that an urgent item on fire safety would be considered.

4. DECLARATIONS OF INTEREST

None.

5. DEPUTATIONS/PETITIONS/PRESENTATIONS/QUESTIONS

None.

6. MINUTES - 6 FEBRUARY 2017

AGREED: That the minutes of the meeting held on 6 February 2017 be approved as a correct record.

7. MINUTES - 7 MARCH 2017

It was noted that the minutes of the meeting held on 7 March 2017 would be reported to the next meeting.

8. TERMS OF REFERENCE AND MEMBERSHIP

Christian Scade, Principal Scrutiny Officer, introduced the report as set out. AGREED:

(a) That the terms of reference and protocol for Overview and Scrutiny be noted; and

(b) That the policy areas, remits and memberships for each Scrutiny Panel for 2017/18 be noted.

9. AMENDMENT TO THE ORDER OF BUSINESS

AGREED: That a New Item of Urgent Business, concerning Fire Safety, be taken before agenda item 9, Homelessness – Supply and Demand Update.

Clerks note – the minutes follow the order of the meeting.

10. NEW ITEM OF URGENT BUSINESS - FIRE SAFETY

Following recent events in Kensington, the Chair advised that thoughts and sympathies were with all those who had lost their lives or been affected by the terrible Grenfell Tower tragedy.

It was acknowledged that it was not yet known what had caused the fire or why it had spread in the way that it had. However, the tragedy had understandably raised a number of questions and concerns about fire safety.

In terms of tower block fire safety in Haringey, the Panel was informed that:

- 54 blocks over 6 storeys high were managed by Homes for Haringey.

- None of the blocks managed by Homes for Haringey had the Reynobond aluminium system that had been used on Grenfell Tower.

- All exterior cladding on properties managed by Homes for Haringey had met the specifications for this type of work and complied with building regulations.

- All Homes for Haringey managed tower blocks had valid Fire Risk Assessments with established processes for ongoing monitoring including regular checks with the communal areas and regular servicing of fire-fighting equipment.

- Homes for Haringey employed two full time, appropriately qualified, fire risk assessors.

- Homes for Haringey staff had visited every high rise block and inspected communal areas and access routes to ensure they were clear.

In response to questions, the Panel was informed that the procedures used by Homes for Haringey were in line with the London Fire Brigade’s audit tool for fire safety.

As an additional measure of re-assurance the Panel was informed fire risk assessors would, during the following week, visit every high rise block in order to review fire risk assessments and speak to residents. In terms of non-council owned tower blocks, officers explained work was under way to ensure the Council had a record of all high rise blocks in the borough, and to understand any challenges faced.

A number of questions were raised in relation to Rivers Apartments, a new 22 storey tower situated in Tottenham. In response, officers provided an update from Newlon Housing Trust, who owned the property, with the following points being noted:

- Rivers Apartments completed in the spring of 2015 and had been clad with Reynobond PE. It was confirmed this was the same as the cladding used on Grenfell Tower.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Minutes: 22 June 2017Minutes 181 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 6 attended
EI
Councillor Emine IbrahimChair, present
JB
Councillor John BevanCommittee Member, present
ZB
Councillor Zena BrabazonCommittee Member, present
GE
Councillor Gail EngertCommittee Member, present
MN
Councillor Martin NewtonCommittee Member, present
AW
Councillor Ann WatersCommittee Member, present

On this subject at Haringey

Search all
  1. Minutes - 22 June 2017This decision
  2. Minutes - 29 June 2017Agreed
  3. To approve as a correct record the minutes of the meeting of the Council held on 9 June 2014Decided
  4. Minutes - 13 june 2013Approved
  5. Minutes - to consider the minutes of the area committee held on 27 june 2012 and any matters arisingApproved

More from Haringey Housing, Planning and Development Scrutiny Panel

All decisions
MeetingDecisionOutcome
15 Dec 2025 KPI UpdateRESOLVED Noted Noted Open
15 Dec 2025 Finance Update - Q2 2025/26RESOLVED That the Panel noted the contents of the ... view the full minutes text for item 282. Noted Open
15 Dec 2025 Work Programme UpdateRESOLVED That the Panel noted the work programme and agreed any amendments. Noted Open
17 Nov 2025 Work Programme UpdateRESOLVED That the work programme was noted and any amendments were agreed. Noted Open
23 Sep 2025 Corporate delivery plan q1 2025/26 performance updateRESOLVED That the high level progress made against the delivery of commitments as set out in the CDP 2024-26 at the e... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies