RESOLVED That, subject to regulations being made in substantially the same form as the draft Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits)(England) (Amendment) Regulations 2017 (“the Draft Regulations”) to: a) increase all planning fees by up to 20%; and b) amend and introduce all planning fees as proposed in the Draft Regulations; in accordance with and immediately on any such regulations coming into force. Reasons for decision The acceptance of the 20% increase in planning fees and introduction of new fees will allow the Planning Service to increase its capacity and drive further efficiencies in the Planning Service and ensure compliance with staturoty requirements. Alternative options considered To reject the offer of a 20% increase in planning fees and the option to charge fees for permission in principle applications and application where permitted development rights have been removed. This option was rejected as the Council does not have discretion under the 2012 Regulations to vary or waive the fees. Further, it would only represent a modest rise in planning fees and would be unlikely to discourage development given that planning fees are a very small proportion of the overall cost of a building/development project.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
Report authorised by : Lyn Garner, Strategic Director for Regeneration, Planning and Development
Lead Officer: Emma Williamson, Assistant Director Planning x 5507
Ward(s) affected: All
Report for Key/ Non Key Decision: Key
1. Describe the issue under consideration The Government has published draft regulations to be laid before Parliament shortly to allow Local Planning Authorities to charge increased planning fees- 20% more than the current fees. This report proposes that the Council charges the increased fees immediately once the regulations have been made and come into force.
2. Cabinet Member Introduction The proper resourcing of planning departments is key to maintaining good performance and the Government‟s offer of increased planning fees is welcomed. This funding will be used to bring additional capacity to, and drive further efficiencies in, Haringey‟s already excellent service through a combination of additional staffing and IT improvements.
3. Recommendations That, subject to regulations being made in substantially the same form as the draft Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits)(England) (Amendment) Regulations 2017 (“the Draft Regulations”) to:
a) increase all planning fees by up to 20%; and b) amend and introduce all planning fees as proposed in the Draft Regulations;
in accordance with and immediately on any such regulations coming into force.
4. Reasons for decision The acceptance of the 20% increase in planning fees and introduction of new fees will allow the Planning Service to increase its capacity and drive further efficiencies in the Planning Service and ensure compliance with staturoty requirements.
5. Alternative options considered To reject the offer of a 20% increase in planning fees and the option to charge fees for permission in principle applications and application where permitted development rights have been removed. This option was rejected as the Council does not have discretion under the 2012 Regulations to vary or waive the fees.. Further, it would only represent a modest rise in planning fees and would be unlikely to discourage development given that planning fees are a very small proportion of the overall cost of a building/development project.
6. Background information In February 2017 the „Fixing our broken housing market/ White Paper‟ set out in paragraph 2.13 that the Government will increase nationally set planning fees. This was proposed in response to developers raising that the lack of capability and capacity in planning departments is restricting their ability to get on site and build. In addition local authorities have reported difficulties in recruiting and retaining planners and others with specialist skills. In order to accept the 20% rise in fees local authorities were asked to confirm that they commit to invest the additional fee income in their planning department. It is intended that existing baseline and income assumptions will not be revised down as a result.
To that end the Council‟s Section 151 Officer, under s230 of the Local Government Act 1972, was asked to provide a commitment and submit information of the 2017/18 budget that demonstrates the additional fee income being spent on planning services. Haringey, alongside all other local planning authorities, returned this form in March 2017. At that time it was envisaged that the fee raise would be in place in July 2017.
This is the information that was submitted:
2016/17 2017/18 Estimated Expenditure £2,355,124 £2,700,000 on development management Estimated income from £1,358,000 £1,314,000 planning application fees Estimated additional N/A £159,000 income generated from higher planning fees
This information was based on the fee raise taking place in July 2017. Unfortunately this was delayed because of the General Election.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.