CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Haringey
Cabinet Member Signing, Thursday 19 April 2018 at 3.30pm

Maya Angelou Family Contact Centre Relocation (39 Winkfield Road) - Contract Variation to Mulalley & Company Ltd

Approved Executive 1 paper

Cabinet Member Signing approved this item on Thursday 19 April 2018. Below is the council's own wording, with the papers it was decided on.

Item69

Resolved

RESOLVED that the request for an extension of the value of the contract with Mulalley & Company Ltd for the fit-out of 39 Winkfield Road for use as Haringey’s Family Contact Centre, known as the Maya Angelou Family Contact Centre be approved. The total value of the contract was £538,000, including the extension of £120,375. Reasons for decision To ensure Haringey Council can adhere to its contractual obligations and make payment of contract valuations and settlement of final account. The project recently completed, at the beginning of April, and the final account is currently being agreed between the Independent Project Cost Consultant and Mulalley & Company Ltd. The Project Cost Consultant estimates the final account will be no greater than £583,000 Alternative options considered A do nothing option would mean that the council would be unable to make payment of the latest contract valuation and would mean it would be in breach of its contractual obligations and be at risk of incurring additional interest costs on unpaid amounts.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing, 3 pages

Recommendations

3.1For the Cabinet Member for Children and Families pursuant to Contract Standing Order 16.02 to approve an extension of the value of the contract to Mulalley & Company Ltd for the fit-out of 39 Winkfield Road for use as Haringey’s Family Contact Centre known as the Maya Angelou Family Contact Centre. The value of the extension is £120,375. The total value of the contract including the extension is £583,000.

Reasons for decision

4.1To ensure Haringey Council can adhere to its contractual obligations and make payment of contract valuations and settlement of final account.

4.2The project recently completed, at the beginning of April, and the final account is currently being agreed between the Independent Project Cost Consultant and Mulalley & Company Ltd. The Project Cost Consultant estimates the final account will be no greater than £583,000

Alternative options considered

5.1A do nothing option would mean that the council would be unable to make payment of the latest contract valuation and would mean it would be in breach of its contractual obligations and be at risk of incurring additional interest costs on unpaid amounts.

6. Background information

6.1The project was to fit-out 39 Winkfield Road (a former Greek Parents Association sports hall) so it can be used as a Family Contact Centre and replace the one currently at Keston Road (This site has been sold to a developer for residential properties and as part of the sale the Contact Centre had to relocate.)

6.2The project was competitively tendered under the under the LCP Major Works Framework (LCP Lot 4 MW 14 Framework Agreement). The tender response from Mulalley & Company Ltd represented the best value for money offer under the pre- determined tender evaluation criteria.

Contractors Total Fixed Price Price Quality Total Tendering for the submitted Score score evaluation works 70% 30% score 100%

Mulalley & £462,625 70.00% 15.60% 85.60% Company Ltd

6.3On this basis, an award of contract was recommended and approved by the Strategic Director of Regeneration, Planning and Development in October 2017 for £462,625.

6.4The fit-out at 39 Winkfield Road commenced in November 2017 this was originally a 16 week contract period with completion in Mid March 2018.

6.5After the project had started on site, it was recognised that given there was a new roof being installed, which required scaffolding, an opportunity arose to allow Photovoltaic Panels to be installed at the site at a reduced cost than installation at a later date. This supports Haringey’s Priority 4 objective to be carbon neutral by 2050. Therefore, a variation was agreed by the Project Sponsor, to be funded by the Carbon Management fund to supply and install Photovoltaic Panels. This also extended the contract period to completion on 23rd March 2018. In addition to this a number of other minor variations have been agreed, which were reviewed and approved by a Change Control Board and are within the overall project contingency allowance.

6.6Settlement of the final account will result in a variation which is not able to be approved under delegated authority as the total contract value (original award plus variation) exceeds £500,000.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Maya Angelou Family Contact Centre Relocation (39 Winkfield Road): Contract Variation to Mulalley & Company LtdMinutes 3 pages DownloadRead as text

At this meeting

Whole meeting
68Highgate Wood Secondary School Roof Replacement - Contract Variation to Vinci Construction UK LimitedApproved
69Maya Angelou Family Contact Centre Relocation (39 Winkfield Road) - Contract Variation to Mulalley & Company LtdThis decision

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies