Resolved
AGREED: That the report be noted.
Housing, Planning and Development Scrutiny Panel agreed this item on Thursday 15 November 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
AGREED: That the report be noted.
3.1That the Panel note the contents of this report.
4.1The report is for information only and relates to the quarter one budget monitoring position as reported to Cabinet on 11 September 2018.
5. Background Information
5.1At Appendix 1 is a summary of the Quarter 1 budget monitoring for Priority 4 and 5.
5.2As at 30th June 2018 (Quarter 1) of the financial year ending 2018/19, Priority 4 and 5 are at break even. The HRA is projecting an overspend of £0.23m.
5.3Table 1 below sets out financial performance at priority level. A detailed analysis at directorate level is attached at Appendix 1. Table 1 – Revenue Budget Monitoring Forecast for Quarter 1 2018/19 Revised Quarter 1 Quarter 1 Priority 2018/19 Outturn Forecast to Budget Forecast Budget Variance £'000 £'000 £'000 PR4 Growth & Employment 7,733 7,713 (20) PR5 Homes & Communities 15,823 15,823 General Revenue Total 23,556 23,536 (20) PR5 Homes & Communities 231 231 (HRA) HRA Total 0 231 231
6. Revenue Finance Overview
PRIORITY 4 Break Even 6.1. There are no issues to report in this priority.
PRIORITY 5 (General Fund) Break Even 6.2. Housing and Growth’s full year forecast is showing a breakeven position. The temporary accommodation (TA) budget is currently under pressure. This is primarily due to the number of clients and the forecast level of compensation payment costs. Currently it is assumed that this can be offset by unbudgeted income from TA lodges hostels and reduced expenditure in some other areas along with the use of the flexible homelessness grant.
6.3As acknowledged in the June 2018 Cabinet report on Broadwater Farm estate, the impact of temporarily re-housing tenants is forecast to create a pressure of about £202k on the TA budgets in 2018/19. These costs are yet to materialise but will need to be covered. Further clarity will be available for the quarter two report.
. PRIORITY 5 (HRA) Overspend £0.23m 6.4. The HRA budget is projecting an overspend of £0.23m for the year ending March 2019. The HRA outturn summary is set out in Table 2 below.
Table 2 – HRA Budget Forecast (Quarter 1)
Quarter Revised 1 Forecast 2018/19 Outturn to Budget Total for HRA Budget Forecast Variance £'000 £'000 £'000 Managed Services Income -107,554 -107,178 375 Managed Services Expenditure 14,025 13,854 (170) Retained Services Expenditure 93,529 93,555 26 Total for HRA 0 231 231
6.5Appendix 2 provides a breakdown of the income and expenditure for the HRA budget.
6.6The main drivers of the variance are the under recovery of dwelling income, as properties are being held back from letting due to the need to rehouse residents from the Tangmere block on Broadwater Farm, and a higher than anticipated number of garage voids which is impacting on income streams. HfH have undertaken a review of garages so work is underway to resolve the latter pressure. The income shortfall is being offset by a number of small underspends on the managed services expenditure.
7. Capital Expenditure Forecast at Quarter 1
7.1At Q1, the capital programme is forecasting for priority 4 and 5 (General Fund) an underspend of £10.9m and Priority 5 HRA an underspend of £3.7m (HRA) shown in Table 3 below. It is essential to the delivery of the Council’s longer term objectives that capital expenditure takes place in a timely fashion to ensure the Council has the ability to deliver service improvements and longer term revenue savings.
7.2Further scrutiny will take place to ensure that any capital proposals are capable of being delivered and that resources are allocated to their delivery.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Priorities 4 & 5 Budget Position (Quarter 1: 2018/19)Minutes | 10 pages | DownloadRead as text |
Follow Housing, Planning and Development Scrutiny Panel at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Dec 2025 | KPI UpdateRESOLVED Noted | Noted | Open |
| 15 Dec 2025 | Finance Update - Q2 2025/26RESOLVED That the Panel noted the contents of the ... view the full minutes text for item 282. | Noted | Open |
| 15 Dec 2025 | Work Programme UpdateRESOLVED That the Panel noted the work programme and agreed any amendments. | Noted | Open |
| 17 Nov 2025 | Work Programme UpdateRESOLVED That the work programme was noted and any amendments were agreed. | Noted | Open |
| 23 Sep 2025 | Corporate delivery plan q1 2025/26 performance updateRESOLVED That the high level progress made against the delivery of commitments as set out in the CDP 2024-26 at the e... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.