Haringey Self-Build and Custom-Build Register - Eligibility Criteria and Charging Fees

Agreed Licensing 2 papers

Regulatory Committee agreed this item on Monday 1 July 2019. Below is the council's own wording, with the papers it was decided on.

Item67

Resolved

RESOLVED that the Committee recommends i. Cabinet to agree the introduction of the local connection test (see section 6) to qualify for inclusion on Part 1 of the Haringey Self-build Register; ii. Cabinet agrees the introduction of the financial resources test (see section 6) to qualify for inclusion on Part 1 and Part 2 of the Haringey Self-build Register; iii. Cabinet agrees to charging a £144 (inclusive of VAT) fee for registration of valid applications to the Haringey Self-build Register; and an annual re-registration fee of £144 (inclusive of VAT) to remain on Part 1 of the register thereafter.; iv. Cabinet agrees to maintain the existing entries on the register until 30 October 2019 after which date they will be re-assessed against the new eligibility criteria and subject to payment of the £144 annual fee for Part 1 registrations.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Regulatory Committee, 10 pages

Report for: Regulatory Committee, 1st July 2019

Title: Haringey Self-Build and Custom-Build Register – Eligibility Criteria and Charging Fees

Report authorised by : Dan Hawthorn, Director of Housing, Regeneration and Planning

Lead Officer: Rob Krzyszowski, Head of Planning Policy, Transport and Infrastructure. Ext 3213

Ward(s) affected: All

Report for Key/ Non Key Decision: Key Decision

1. Describe the issue under consideration 1.1 The Self-build and Custom Housebuilding Act 2015 imposes a duty upon the Council to maintain a register (the “self-build register”) of individuals and associations of individuals who are seeking to acquire serviced plots of land in the borough to build a house for their own occupation. Initially, the regulations simply required the Council to have regard to the self-build register in carrying out existing functions (including planning, housing, regeneration and land acquisitions and disposal), but the legislation was amended to impose a duty on authorities to grant sufficient suitable 'development permissions' (planning permissions or permissions in principle) for self-build homes to meet the demand indicated by the register. Haringey’s existing self-build register currently contains 344 entries.

1.2The regulations on Self-build and Custom Housebuilding published in October 20161 enabled local authorities to set local eligibility requirements (in addition to the general national requirements) and to charge a fee for entries on to the self- build register (and an annual fee to remain on the register) to cover the cost of the administration involved in checking evidence submitted by potential entrants and maintaining the register.

1.3This report seeks Regulatory Committee endorsement to introduce two local eligibility criteria - a location connection test and a financial resources test - to qualify for inclusion on Haringey’s self-build register, as well as the introduction of a registration and renewal fee.

2. Cabinet Member Introduction N/A

3. Recommendations 3.1 That the Regulatory Committee recommends:

A. Cabinet agrees the introduction of the local connection test (see section 6) to qualify for inclusion on Part 1 of the Haringey Self-build Register;

1 The Self-build and Custom Housebuilding Regulations 2016 and Self-build and Custom Housebuilding (Time for Compliance and Fees) Regulations 2016

Page 1 of 10 B. Cabinet agrees the introduction of the financial resources test (see section 6) to qualify for inclusion on Part 1 and Part 2 of the Haringey Self-build Register; C. Cabinet agrees to charging a £144 (inclusive of VAT) fee for registration of valid applications to the Haringey Self-build Register; and an annual re- registration fee of £144 (inclusive of VAT) to remain on Part 1 of the register thereafter. D. Cabinet agrees to maintain the existing entries on the register until 30 October 2019 after which date they will be re-assessed against the new eligibility criteria and subject to payment of the £144 annual fee for Part 1 registrations.

4. Reasons for decision 4.1 This report proposes the introduction of two local eligibility criteria that will apply to applications for registration on Haringey’s self-build register as follows:

 a Financial Resources Test: to be entered onto the register applicants would have to demonstrate that they have access to the finance needed to acquire land valued at £330,000 (land valuation evidence commissioned by officers indicates that this is the minimum likely cost of a 0.01ha serviced plot in Haringey suitable for development of a single home - see Appendix A for more information about the land valuation evidence); and

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Haringey Self-Build and Custom-Build Register: Eligibility Criteria and Charging FeesMinutes 10 pages DownloadRead as text
PDF
LB Haringey Self-build Report 11June19Minutes 13 pages Download

At this meeting

Whole meeting

On this subject at Haringey

Search all
  1. Haringey Self-Build and Custom-Build Register - Eligibility Criteria and Charging FeesThis decision
  2. Haringey Self-Build and Custom-Build Register – Eligibility Criteria and Charging FeesNoted

More from Haringey Regulatory Committee

All decisions
MeetingDecisionOutcome
14 Jan 2021 Urgent businessRESOLVED 1. To a gree the appointment of Councillor Sheila Peacock to the Planning Sub-Committee , replacing Councill... Agreed Open
5 Oct 2020 Recent Government Announcements on PlanningRESOLVED that: A) The response to the changes to the current planning system consultation, which was submitted on 1 O... Noted Open
2 Oct 2020 Establishment of Planning and Licensing Sub Committees 2020/21RESOLVED that: 1. The terms of reference of the Regulatory Committee as set out within the Council’s Constitution, at... Noted Open
31 Jul 2020 Business and Planning Act 2020 - Pavement Licence conditions and fees as part of the Covid 19 recovery measuresRESOLVED to i. Agree the p avement licence conditions as outlined in Appendix A which will be the Council’s published... Agreed Open
14 Jul 2020 Amendment to Committee MembershipsRESOLVED that i. Councillor Sarah Williams be appointed as Chair of the Planning Sub Committee, and Licensing Sub Com... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies